Single Assurance Framework Business Case Approvals: Officer Decisions
NotedCommittee1 paper
AI summaryCambridgeshire and Peterborough Combined Authority Funding Committee notes seven officer-approved change requests under £2m, including a £299,415 cut to an FE Coldspots project at Cambridge Regional College.
Written from the decision and the officer reportPDF Pro
OutcomeNotedBus Depot, Great Haddon, Retrofitting Your Home, three FE Coldspots projects
Money£299,415 cost reductionSt Neots immersive room project; plus £2,000 saved on comms plan
What happens nextNot stated
Who it affectsNot stated
What was decided
The Funding Committee noted seven officer-level change requests already approved under the Single Assurance Framework delegation, all under £2m. Report 1.1, 1.2
These cover a bus depot scheme, the Great Haddon affordable housing project, the Extending Retrofitting Your Home programme and three Further Education Coldspots projects run by Cambridge Regional College. Report 2.5, 2.6, 2.7, 2.8
The committee has no decision-making role at this stage and is informed for governance oversight only. Report P22
Why
The Single Assurance Framework requires officer decisions under £2m to be reported to the Funding Committee for transparency, even though the committee does not decide them. Report P5, P6, 1.1
Most of the change requests extend delivery deadlines because of project slippage, premises ownership problems, or the need to incorporate extra match funding. Report 2.5, 2.6, 2.7, 2.8
The St Neots immersive room was redesigned as a removable solution because the college did not own the building, allowing the same outcomes at lower cost. Report 2.8
What happens next
A new Grant Funding Agreement between the Combined Authority and Peterborough City Council will run from 01/11/25 to 30/06/26 to complete the bus depot appraisal. Report 2.5
The Great Haddon affordable housing completion date moves to June 2026, with a new GFA issued for that period. Report 2.6
The Retrofit Guide delivery deadline moves to the end of March 2026, with the communications plan removed and roughly £4,206 reallocated to consultant work. Report 2.7
The money
£200k of the dedicated £4m MHCLG capital budget Bus Depot project funding already agreed in 2023 Report 2.5
-£2k (saving, plus timing change) Extending Retrofitting Your Home change request Report P11, 2.7
£4,206 Reallocated from South Cambridgeshire District Council project officer time within a £9,700 budget to consultants Report 2.7
£299,415 Cost reduction on St Neots Immersive Room project, lowering total from £399,415.00 to approximately £100,000.00 Report P11, 2.8, P17
Options considered
Chosen: Note the officer decisions as recommended. Standard governance oversight under the Single Assurance Framework Report P1, P22
Rejected: Comment on the delegated decisions if considered appropriate. No indication the committee chose to comment Report P22
Implications
Financial: All officer approvals fit within the Combined Authority's Medium-Term Financial Plan resources, with one outright cost saving of £299,415. Report P22, 2.8
Legal: The legal basis covers the Chief Executive's delegated authority and good governance practice in reporting these to the Funding Committee. Report P22
Equalities: None recorded. Report P22
Climate: None recorded. Report P22
Staffing: Retrofit project changes shift £4,206 from council officer time to external consultants to meet the new deadline. Report 2.7
Risk: St Neots project was redesigned as a removable solution because the college did not own the premises, avoiding potential legal challenges over the capital investment. Report 2.8
Who and where
Cambridge Regional College, via its Huntingdon, Cambridge and St Neots campuses Report 2.8
Residents of St Neots accessing further education locally Report 2.8
Peterborough City Council as bus depot grant partner Report 2.5
Affordable housing delivery at the Great Haddon urban extension of Peterborough, 49 units Report 2.6
South Cambridgeshire District Council and Cambridgeshire Energy Retrofit Partnership members delivering the Retrofit Guide Report 2.7
Timeline
01/11/25 to 30/06/26: New Grant Funding Agreement period for the Peterborough Bus Depot project Report 2.5
26/11/2025: Combined Authority Board approved the updated Single Assurance Management Framework and Procedure Report 3.1, P18
December 2025 to June 2026: Extended completion window for the Great Haddon affordable housing project Report 2.6
02/12/2025: Funding Panel reviewed all seven change requests Report P11
16/12/2025: Chief Executive approved Bus Depot, Great Haddon and Executive Director approved Extending Retrofitting Your Home change requests Report P11, 2.5, 2.6, 2.7
17/12/2025: Chief Executive approved the three FE Coldspots change requests Report P11, 2.8
End of March 2026: New delivery deadline for the Retrofit Guide Report 2.7
March 2026 to 30 June 2026: Extended delivery timeframe for the Huntingdon Immersive Rooms project Report 2.8
March 2026 to 30 September 2026: Extended delivery timeframe for the Renewable Skills Training Bays and St Neots Immersive Room projects Report 2.8
Plain English for the jargon
Single Assurance Framework (SAF): The Combined Authority's set of systems and processes for appraising, assuring, risk-checking and performance-managing projects and programmes across their lifecycle.
ODN: Officer Decision Notice, the formal record of an officer-level approval under delegated authority.
FE Coldspots: Further Education Coldspots Skills Programme, targeting areas with limited access to further education provision.
GFA: Grant Funding Agreement, the contract setting out how a grant recipient spends the funding.
EDAF: English Devolution Accountability Framework, the government's standard for how devolved authorities demonstrate accountability and best value.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
A. To note the Officer business cases and change request decisions for projects less than £2m under the Single Assurance Framework. A. To note the Officer business cases and change request decisions for projects less than £2m under the Single Assurance Framework.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note the Officer Decisions for projects under the Single Assurance Framework delegation.
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☒ Jobs ☒ Resilience
☒ Connectivity ☒ Homes ☒ Performance The Single Assurance Framework (SAF) is a set of systems and processes designed to provide the CPCA with a consistent approach to appraisal, assurance, risk and performance, throughout the lifecycle of projects and programmes. It is focused on ensuring accountability, probity, transparency and legal compliance as well.
1. Purpose
1.1Under the SAF arrangements approved by the Combined Authority Board at its meeting on 26 November 2025, the Executive Directors have delegated authority to approve project investments of £500k and below plus timing change requests of up to 3 months, and the Chief Executive has delegated authority to approve project investments of over £500k and up to £2m.
1.2This report sets out the projects which have been approved by Officers in accordance with the delegated authority from the Board and is for noting. 2. Proposal
2.1Management of the CPCA’s investment priorities, plans and processes is critical to the successful delivery of its strategic aims and maximising the benefits to the region. To meet the standards set by Government – such as the English Devolution Accountability Framework (EDAF) – the Authority requires a specific assurance framework that shows how it will meet best value requirements and ensuring it is spending public money in the most effective way. In addition, the SAF was a key objective from the Improvement Programme and demonstrates robust governance in support of effective decision making.
2.2The table below sets out the Officer Decisions that have been taken under delegated authority as part of the SAF arrangements and these are listed in the table below.
Funding Panel Date Approver Approval Business Final CPCA Dates Case/Change Funding Approval Request 02/12/25 CEX 16/12/25 Bus Depot £0 (timing change) Change Request 02/12/25 CEX 16/12/25 Great Haddon £0 (timing change) Change Request 02/12/25 Executive 16/12/25 Extending -£2k (saving, plus Director Retrofitting your timing change) Home Change Request 02/12/25 CEX 17/12/25 Further Huntingdon - £0 Education (time change only) Coldspots Renewables - £0 Change (timing change Requests only) St Neots - £299,415 cost reduction plus timing change
2.3The following paragraphs provide a summary of each of the projects.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Funding Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.