Contracted Bus Services Review Framework

Decided Committee 3 papers

AI summaryCambridgeshire and Peterborough Transport Committee agrees to recommend resident engagement on bus service proposals, including four routes previously flagged for withdrawal. Recommendation B (immediate withdrawal) was withdrawn.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRecommend Board undertake resident engagement; Recommendation B withdrawn
MoneyUp to £2m potential savingsNetwork efficiency savings range £0.5m to £2m
What happens nextResident engagement Spring 2026Board consideration of changes anticipated mid-2026
Who it affectsBus passengers in CambridgeshireIncluding users of routes 13B, 19A, 65, 117, 129

What was decided

The Committee resolved to recommend to the Combined Authority Board that resident engagement be carried out on proposals affecting contracted bus services, including the four routes formerly listed for withdrawal. Report P1

Recommendation B, which would have approved the four routes for withdrawal, was withdrawn from the resolution. Report P1

Why

The framework, approved at the November 2025 Board, enables evidence-based decisions focused on passenger requirements and value for money during the transition to franchising. Report 1.1, 3.1

Officers argued that geographic reviews with engagement would deliver a more stable, integrated network than removing individual services from the 35 to 50% band more quickly. Report P14

What happens next

Resident engagement on the proposed service and area changes will begin in Spring 2026, following Board approval.

Final service-change proposals, including timetables, will be developed through Spring into early Summer 2026, with Board consideration anticipated mid-2026.

Procurement activity for any service changes will follow from mid-2026, taking around six to nine months where a new tender is required.

The money

  • £15.5m Annual CPCA spend budgeted on local bus journeys Report 1.2
  • £48,618.41 Annual operating cost of route 19A Cambridge to Landbeach Report 2.3
  • £16,445.00 Annual operating cost of route 13B Nosterfield End to Linton Report 2.3
  • £56,149.86 Annual operating cost of route 65 St Neots to Buckden Report 2.3
  • £11,301.24 Annual contract cost of routes 117 and 129 Ely market day services Report 2.3
  • £132,514.51 Total initial savings outlined in the paper
  • £214k Annual operating cost of Tiger 12 service Report P14
  • £750k Potential reduction from cutting Tiger 7 from three to one peak vehicle Report P14
  • up to £2m Potential network efficiency saving from up to 7.5 PVR reduction Report 2.5
  • between £0.5m, £2m Range of potential network efficiency savings Report 2.5

Options considered

  • Withdrawn: Recommend immediate withdrawal of four routes (13B, 19A, 117/129, 65) and approve delegated authority to implement. Recommendation B was withdrawn; replaced by engagement approach Report P1
  • Chosen: Undertake geographic based reviews with resident engagement before making changes. Officers said this would deliver a more stable, integrated network and allow a more informed decision in June Report P14, 2.5
  • Rejected: Remove individual bus services in the 35 to 50% framework band earlier to initiate savings faster. Faster savings but would remove services and network stability for residents and businesses Report P14

Implications

  • Financial: Initial savings outlined total £132,514.51; wider PVR efficiencies could reach £0.5m to £2m, though the 26/27 forecast relies on drawdowns from operational reserves.
  • Legal: The CPCA exercises its transport functions under the Cambridgeshire and Peterborough Combined Authority Order 2017, and the Bus Services Act 2025 strengthens local authority powers over routes, fares and timetables.
  • Equalities: Proposals aim to meet Equality Act standards, focus on low car ownership and higher deprivation areas, and avoid isolation in rural communities.
  • Climate: Encouraging public bus use is expected to support decarbonisation of transport in line with DfT guidelines.
  • Risk: Without intervention the current suite of interventions is not affordable in the long term, given forecast drawdowns from operational reserves increase in 27/28.
  • Other: Resident engagement during a pre-election period for 2026 local elections may require legal advice on whether it can proceed.

Who and where

  • Passengers using route 13B between Nosterfield End and Linton Report 2.3
  • Passengers using route 19A between Cambridge and Landbeach Report 2.3
  • Passengers using route 65 between St Neots and Buckden Report 2.3
  • Passengers using routes 117 and 129 between Ely, Wicken and Prickwillow Report 2.3
  • Residents across East Cambridgeshire, South Cambridgeshire, Fenland and the St Ives area where service reviews are proposed Report 2.5, 2.6
  • Bus operators running the affected contracted services Report 2.3

Timeline

  • November 2025: Strategic Framework for bus service review approved at Board Report 1.1, 3.1
  • December 2025: CA Board decided to continue support for the Tiger pass scheme alongside the supported bus service budget
  • January 2026: Introduction of new X75 service for South Cambridgeshire Report 2.5
  • 14 January 2026: Transport Committee decision on the Contracted Bus Services Review Framework
  • Spring 2026: Resident engagement on proposed service and area changes to commence
  • Mid-2026: Anticipated Board consideration and approval of changes to the network
  • From mid-2026 onwards: Procurement activity for service changes where required

Plain English for the jargon

  • CPCA: Cambridgeshire and Peterborough Combined Authority, the local transport authority for the area.
  • PVR: Peak Vehicle Requirement, the number of buses needed to operate services at the busiest time; a key driver of network cost.
  • DRT: Demand Responsive Transport, a flexible bus or shared transport service that runs in response to bookings rather than a fixed timetable.
  • Tiger on Demand: CPCA's demand responsive transport service, branded as Tiger, covering several zones across Cambridgeshire.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

On being proposed by the Chair and seconded by Cllr Beckett it was resolved: A. To recommend to the Combined Authority Board to undertake appropriate resident engagement on the proposals affecting contracted bus services, as set out in section 2.5. and 2.6, and to include the routes listed below (formerly shown in recommendation B) 13B Nosterfield End to Linton 19A Cambridge to Landbeach 117 and 129 Ely to Upware and Ely to Black Horse Drove 65 St Neots to Buckden *Text in bold denotes additional wording to the recommendation. Recommendation B was withdrawn.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Transport Committee

Recommendations

A Following the Board approval of the Strategic Framework for the review of bus services in November 2025, Transport Committee is asked to recommend to the Combined Authority Board to undertake resident engagement on the proposals affecting contracted bus services, as set out in section 2.5 B To recommend to the Combined Authority Board to approve the following routes listed below identified in the framework for withdrawal: • 13B Nosterfield End to Linton • 19A Cambridge to Landbeach • 117 and 129 Ely to Upware and Ely to Black Horse Drove • 65 St Neots to Buckden and approve delegated authority for the Executive Director of Place and Connectivity, in consultation with the Director for Legal & Governance and Chief Finance Officer, to implement the recommended changes.

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☐ Growth ☒ Jobs ☒ Resilience

☒ Connectivity ☐ Homes ☐ Performance

1. Purpose

1.1The bus services review framework was approved at Board on 26 November 2025. The framework enables a strategic approach focused on passenger requirements and value for money. The framework enables CPCA to consider the wider public transport network (including Tiger On- Demand and community transport services) and a more logical approach to prioritising spending on contracted bus services, both during the transition period through to franchising and to ensure a stable base network for the future. The framework enables evidence-based decision making in line with local and national policy, focused on value for money, social access to services and a balanced network operating budget.

1.2CPCA currently budgets to spend £15.5m per year on providing local bus journeys for its residents. This is provided through contracted local bus services which provide journey opportunities, not provided by commercial bus services. Contracted bus services form approximately 12% of the bus network (based on bus mileage operated on a daily basis) The level to which the CPCA has contracted and supported the bus network via public subsidy has increased in recent years, with the increase funded primarily via the Mayoral precept. The current Medium-term financial plan (out for public consultation) does not propose to increase the Mayoral precept further. The use of this framework to ensure prudent cost-effective proposals within a balanced budget is key for the management of an affordable and sustainable bus network. 1.3 This paper makes recommendations about bus services that have been assessed using the approved framework. The paper and appendices outline the summaries for each bus service listed and the categorisation of services that require action. Four services are identified for withdrawal. The rationale is set out below for each route in 2.3 but these four routes achieve savings with minimum customer impact due to the low number of passengers journeys or the alternative options being proposed. For the longer list of routes under review in section 2.1 below, this categorisation will inform resident engagement after board approval to gather feedback on the service proposals. Officers have not defined proposals on specific timetables at this stage, reflecting the importance of resident engagement on the trade-offs of providing revised services that better meet the outcomes the CPCA is striving to deliver from the bus network.

2. Proposal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Assessment of Bus ServicesAppendix A 3.4 MB Download
PDF
Key Definitions for Bus Service Framework EvaluationAppendix B 61 KB Download
PDF
Contracted Bus Services Review FrameworkReport 172 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
RJ
Richard JeremyOfficer, expected
CB
Councillor Chris Boden Mayor's RepresentativeChair, present
KT
Councillor Katie Thornburrow Cambridge City CouncilCommittee Member, present
AB
Councillor Alex Beckett Cambridgeshire County CouncilVice-Chair, present
AS
Councillor Alan Sharp East Cambridgeshire District CouncilCommittee Member, present
CS
Councillor Chris Seaton Fenland District CouncilCommittee Member, present
SW
Councillor Sam Wakeford Huntingdonshire District CouncilCommittee Member, present
PM
Councillor Peter McDonald South Cambridgeshire District CouncilCommittee Member, present
AE
Councillor Angus Ellis Peterborough City CouncilCommittee Member, present
JN
Councillor Jon Neish Overview and Scrutiny Committee RapporteurGuest, expected
SS
Councillor Simon Smith Cambridge City CouncilSubstitute
LD
Councillor Lorna Dupre Cambridgeshire County CouncilSubstitute

All 17 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Contracted Bus Services Review FrameworkThis decision
  2. Contracted Bus Service Review – KD2025/081Approved
  3. Contracted Bus Services Review - KD2025/045Approved
  4. Contracted Bus Services ReviewApproved
  5. Bus Network - Contracted Services and Tiger PassNoted

More from Cambridgeshire and Peterborough Combined Authority Transport Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi... Approved Open
9 Sep 2026 Forward PlanA. That the Combined Authority Forward Plan be noted A. That the Combined Authority Forward Plan be noted. ACTION: 1.... Noted Open
9 Sep 2026 Developer Funding Governance(Unanimous) A. To note the CPCA action plan to improve governance and delivery of developer funding for bus services ... Noted Open
9 Sep 2026 Bus Services Reimagined – Final Service Change ProposalsA. To note the outcome of the contracted bus services review, including the evidence base, consultation feedback and ... Noted Open
9 Sep 2026 Local Transport Delivery Plan(Unanimous) To recommend to the Combined Authority Board that they: A. Approve the (LTDP) – Cambridgeshire County Cou... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies