Contracted Bus Services Review

Approved Committee 4 papers

AI summaryCambridgeshire and Peterborough Combined Authority Transport Committee approved a draft bus service review framework and recommended continuing most contracted routes, projecting £237,050 annual savings for 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThree highest-cost services recommendation failed to pass
Money£237,050 savingAnnual reduction in passenger transport budget for 2026/27
What happens nextFurther reviews from January 2026Board to make final decisions on all recommendations
Who it affectsBus passengers across Cambridgeshire and PeterboroughIncludes possible loss of routes 8A and 15

What was decided

The Committee recommended to the Combined Authority Board that the draft bus service review framework be approved, with the Executive Director of Place and Connectivity applying it to the existing contracted bus network. Report P1

The Committee recommended to the Board that specific bus services with contract expiry dates of 31 May 2026 be re-tendered on a like-for-like basis, excluding service number 15, and gave delegated authority to enter into contracts with successful bidders.

Recommendation C covering the three highest cost per passenger services (15 Haslingfield to Royston, 8A March to Milton Park and Ride, and South Cambridgeshire Tiger on Demand) did not meet the voting criteria requiring approval by the two Highways Authorities and was not passed; it will go to the Board without a Committee recommendation.

Why

A framework is needed to provide a strategic, value-for-money approach to prioritising contracted bus spending during the transition to franchising and to ensure a stable base network. Report 1.1, 2.1

Officers assessed the upcoming contract expiries against the previous cost per passenger metric, recommending retention and re-tender for services with strong scores and community links. Report 1.3

The framework uses a weighted scoring approach: 20% Social Value Access, 20% Social Value Demographics, 20% Minimum Service Levels and 40% Value for Money. Report 3.1

What happens next

The Combined Authority Board will consider all three recommendations, with recommendation C going forward without a Transport Committee recommendation.

Tender preparation for the 1 June 2026 start date must begin now to avoid a service gap; further service recommendations will come to Transport Committee from January 2026. Report 1.1

If approved, officers will apply 112 days' traffic commissioner and contractual notice to cease services 8A and 15, and will work with South Cambridgeshire District Council on revising the Tiger on Demand zone. Report P15

The money

  • £15.5m Annual CPCA budget for supported local bus services Report 1.2, P18
  • £609,425 p.a. Total of contracts being proposed for continuation or replacement (15, 8A and Tiger on Demand) Report P18
  • £237,050 Projected decrease on current equivalent contract costs, as a saving on 2026/27 passenger transport budgets Report P18
  • £188,753.02 Current contract price for service 8A
  • £48,297.00 Current contract price for service 15
  • £372,376 Current contract cost for Tiger on Demand (South Cambridgeshire) Report P15
  • £500k Approximate S106 developer funding expected to be unlocked for public transport Report P15
  • £133,720 Contract price for service 8 Cambridge to Dry Drayton, Papworth Everard
  • £359,459 Contract price for service 5A St Ives to Fenstanton, Bar Hill, Longstanton P&R, Willingham, Over, Swavesey
  • £162,584 Contract price for service 27 Stamford to Wittering, Peterborough

Options considered

  • Chosen: Service 8 Cambridge - Dry Drayton - Papworth Everard. Strong cost per passenger score, increased patronage and community links
  • Chosen: Service 46A Newmarket - Dullingham - Linton. Strong cost per passenger score and community links
  • Chosen: Service 5A St Ives to Swavesey. Strong cost per passenger score; bringing two separate contracts together may achieve efficiencies
  • Chosen: Service 27 Stamford - Wittering - Peterborough. Strong cost per passenger score and community links; further engagement on timetable
  • Chosen: Service 15 Haslingfield - Bassingbourn - Royston. Framework assessment; cost per passenger of £180.32 led to recommendation to cease and not replace
  • Chosen: Service 61 Eynesbury - St Neots - Eaton Ford. Strong cost per passenger score and community links
  • Chosen: Service 68 Wisbech Town Service. Historically strong scores; further engagement with Fenland District Council on capacity and route
  • Chosen: Service V4 St Ives Bus Station - Fenstanton - Hilton - Elsworth - Boxworth. Recent changes may improve performance; may be reviewed in fuller network assessment

Implications

  • Financial: Net saving of £237,050 p.a. on passenger transport budgets for 2026/27, but the service remains reliant on reserve drawdowns in current and next financial year, indicating long-term unaffordability. Report P18
  • Legal: The framework is an advisory mechanism; approval would give greater strength to CPCA in the event of judicial review, particularly in the context of the Bus Services Bill progressing through Parliament in 2025. Report P18
  • Legal: CPCA exercises statutory transport functions under the Cambridgeshire and Peterborough Combined Authority Order 2017 (SI 2017/251). Report P18
  • Climate: Encouraging public bus use can contribute to climate change efforts, improved air quality and reduced transport carbon footprint. Report P18
  • Other: Public health: providing public transport options supports resident access across the region and can connect with active travel. Report P18
  • Risk: If an effective solution is not put in place for the Tiger on Demand area, approximately £500k of S106 developer funding may be relinquished and lost to the public transport network. Report P15

Who and where

  • Bus passengers across Cambridgeshire and Peterborough, particularly users of services 8, 46A, 5A, 27, 61, 68 and V4 (continuing) and services 15 and 8A (proposed cessation)
  • Residents in South Cambridgeshire villages potentially within an expanded Tiger on Demand zone, including Hauxton, Trumpington Park and Ride, Comberton, Shepreth and Duxford Report P15
  • South Cambridgeshire District Council, as a partner in Tiger on Demand delivery and S106 funding discussions Report P15
  • Fenland District Council, for engagement on Wisbech Town Service vehicle capacity and route design
  • Bus operators tendering for the 1 June 2026 contract start

Timeline

  • July 2025: Transport Committee and CPCA Board considered the 15, 8A and Tiger on Demand services following the 2024/25 cost per passenger assessment Report 2.2, 3.1
  • 15 September 2025: Previous Transport Committee paper on Bus Network Contracted Services and Tiger Pass Report P18
  • October 2025: Member workshop held on the framework and context Report 3.1
  • 17 November 2025: Transport Committee considered this report
  • From January 2026: Further service recommendations to be brought to Transport Committee Report 1.1
  • Early 2026: Aim to advance tendering for services starting 1 June 2026
  • 31 May 2026: Expiry of current contracts for specified services
  • 1 June 2026: Planned commencement of re-tendered services
  • 112 days' notice: Traffic commissioner and contractual notice required to cease services 8A and 15

Plain English for the jargon

  • CPCA: Cambridgeshire and Peterborough Combined Authority, the local transport authority for the area.
  • Contracted bus services: Bus journeys funded by the authority where they are not provided commercially; about 12% of the CPCA network by daily bus mileage.
  • Tiger on Demand: A demand-responsive bus service; the South Cambridgeshire zone has operated since January 2025.
  • S106 funding: Developer contributions secured through Section 106 planning obligations, used here for public transport solutions.
  • Franchising: A model where the authority sets routes, fares and timetables and contracts operators to run them; relevant to the future CPCA network.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED To recommend to the Combined Authority Board: A. To approve the draft bus service review framework and to agree that the Executive Director of Place and Connectivity will apply the framework to the existing contracted bus network to inform recommendations on future service changes. Further service recommendations to come forward to Transport Committee from January 2026 B. To approve the recommendations related to specific bus services, which have contract expiry dates of 31 May 2026, (excluding the No.15 service) and to approve delegated authority for the Executive Director of Place and Connectivity to enter into contracts with successful bidders following a procurement process. * text in bold denotes an amendment to the recommendation The following recommendation was also presented and put to the vote but did not meet the voting criteria, which required approval by the two Highways Authorities, and therefore was not passed. The recommendation would be presented to the Board at their meeting but without a Committee recommendation. C. To approve the recommendations related to the three highest cost per passenger bus services: • 15 Haslingfield to Royston (Wednesday only service) • 8A March to Milton Park and Ride • South Cambridgeshire Tiger on Demand and approve delegated authority for the Executive Director of Place and Connectivity, in consultation with the Director for Legal & Governance and Chief Finance Officer to implement the recommendedchanges Strategic Objectives
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Transport Committee

Recommendations

A To recommend to the Combined Authority Board to approve the draft bus service review framework and to agree that the Executive Director of Place and Connectivity will apply the framework to the existing contracted bus network to inform recommendations on future service changes. Further service recommendations to come forward to Transport Committee from January 2026 B To recommend to the Combined Authority Board to approve the recommendations related to specific bus services, which have contract expiry dates of 31 May 2026, and to approve delegated authority for the Executive Director of Place and Connectivity to enter into contracts with successful bidders following a procurement process. C To recommend to the Combined Authority Board to approve the recommendations related to the three highest cost per passenger bus services: • 15 Haslingfield to Royston (Wednesday only service) • 8A March to Milton Park and Ride • South Cambridgeshire Tiger on Demand and approve delegated authority for the Executive Director of Place and Connectivity, in consultation with the Director for Legal & Governance and Chief Finance Officer to implement the recommended changes

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☐ Growth ☒ Jobs ☒ Resilience

☒ Connectivity ☐ Homes ☐ Performance 1. Purpose

1.1The draft bus services review framework enables a strategic approach focused on passenger needs and requirements and value for money. It will enable the CPCA to consider the wider public transport network (including Tiger On-Demand and community transport services) and will allow for a more logical approach to prioritising spending on contracted bus services, both during the transition period through to franchising and to ensure a stable base network for the future. It will support decisions in line with local and national policy, focused on value for money, social access to services and a balanced network operating budget and evidence based decision making.

1.2CPCA currently budgets to spend £15.5m per year on providing local bus journeys for its residents. This is provided through contracted local bus services which provide journey opportunities not provided by commercial bus services. Contracted bus services form approximately 12% of the bus network (based on bus mileage operated on a daily basis) The level to which the CPCA has contracted and supported the bus network via public subsidy has increased in recent years, with the increase funded primarily via the Mayoral precept. This paper enables a proactive strategic approach to this network management making recommendations regarding immediate procurement and proposals for services that are performing less well.

1.3The paper also makes recommendations about services requiring decisions for re-procurement imminently and where officers were asked to bring forward recommendations for the three services which showed the highest cost per passenger journey in May 2025.

2. Proposal

2.1Bus Services Review Framework The Contracted Bus Services Review Framework will guide officer recommendations on future contracted bus service changes. This delivers a robust assessment for decision making on a reactive basis, for example when a commercial operator gives notice of ending a route and a decision is required as to whether CPCA provides funding for a contracted service.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CPCA Service EvaluationsAppendix A 530 KB Download
PDF
Key Definitions for Bus Service EvaluationsAppendix A1 61 KB Download
PDF
Draft CPCA Contracted Bus Service Review FrameworkAppendix B 4.3 MB Download
PDF
Contracted Bus Services ReviewReport 742 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
RJ
Richard JeremyOfficer, expected
CB
Councillor Chris Boden Mayor's RepresentativeChair, present
KT
Councillor Katie Thornburrow Cambridge City CouncilCommittee Member, present
AB
Councillor Alex Beckett Cambridgeshire County CouncilVice-Chair, present
AS
Councillor Alan Sharp East Cambridgeshire District CouncilCommittee Member, present
CS
Councillor Chris Seaton Fenland District CouncilCommittee Member, present
SW
Councillor Sam Wakeford Huntingdonshire District CouncilCommittee Member, present
PM
Councillor Peter McDonald South Cambridgeshire District CouncilCommittee Member, present
AE
Councillor Angus Ellis Peterborough City CouncilCommittee Member, present
RS
Rebecca Stephens Business BoardCo-Optee, apologies
JN
Councillor Jon Neish Overview and Scrutiny Committee RapporteurGuest, expected
SS
Councillor Simon Smith Cambridge City CouncilSubstitute

All 18 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Contracted Bus Services ReviewThis decision
  2. Contracted Bus Service Review – KD2025/081Approved
  3. Contracted Bus Services Review FrameworkDecided
  4. Contracted Bus Services Review - KD2025/045Approved
  5. Bus Network - Contracted Services and Tiger PassNoted

More from Cambridgeshire and Peterborough Combined Authority Transport Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi... Approved Open
9 Sep 2026 Forward PlanA. That the Combined Authority Forward Plan be noted A. That the Combined Authority Forward Plan be noted. ACTION: 1.... Noted Open
9 Sep 2026 Developer Funding Governance(Unanimous) A. To note the CPCA action plan to improve governance and delivery of developer funding for bus services ... Noted Open
9 Sep 2026 Bus Services Reimagined – Final Service Change ProposalsA. To note the outcome of the contracted bus services review, including the evidence base, consultation feedback and ... Noted Open
9 Sep 2026 Local Transport Delivery Plan(Unanimous) To recommend to the Combined Authority Board that they: A. Approve the (LTDP) – Cambridgeshire County Cou... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies