AI summaryThe Transport Committee noted progress and stakeholder engagement findings on the Greater Cambridge Transport Strategy, with a draft due in June 2026 and final approval targeted for November 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFeedback invited on planned next steps toward approval
MoneyNo new moneyFunding within existing MTFP, approved March 2024
What happens nextDraft to June 2026, final to November 2026Transport Committee then Board for approval
Who it affectsGreater Cambridge areaResidents, businesses, commuters and stakeholders
What was decided
The Committee noted GCTS progress to date and provided feedback on planned next steps to achieve strategy approval in line with the Statement of Intent. Report P1
The Committee noted the findings from the independent report on engagement with key stakeholders. Report P1
Officers were asked to explore an additional steering group meeting for members and to establish a schedule of monthly updates and briefings.
Why
The GCTS will sit beneath the CPCA's adopted Local Transport and Connectivity Plan and set out connectivity requirements for Greater Cambridge, supporting the Local Plan, larger-scale growth ambitions, and investment decisions. Report 1.1, 2.1
The strategy will deliver the Corporate Plan's Connectivity and Growth objectives, covering better roads, faster trains, new stations, light rail, integrated ticketing, and infrastructure-led development. Report 2.2
The strategy must cover background and context, strategic sites, active travel, mobility hubs, heavy rail, freight, highways, parking, and a strategic transport solution including mass rapid transit. Report 3.3
What happens next
A draft GCTS and summer engagement proposals will go to the Transport Committee in June 2026, with the finalised strategy for approval at Transport Committee and Board in November 2026. Report 3.4
Officers will explore convening an additional member steering group meeting in the coming weeks to review emerging options.
Officers will explore establishing monthly updates and briefings for members through the strategy development process.
The money
approved at March 2024 CA Board GCTS funding is included within the existing Medium Term Financial Plan Report P19
Options considered
Chosen: Recommendation A: note GCTS progress and provide feedback on planned next steps toward strategy approval Report P1
Chosen: Recommendation B: note findings from the independent stakeholder engagement report Report P1
Implications
Financial: Funding for the GCTS is included in the existing MTFP and was approved at the March 2024 CA Board; no new money requested in this paper. Report P19
Legal: CPCA procurement colleagues are awarding a contract for consultancy work following the recent procurement process. Report P19
Equalities: Positive public health implications expected through better connectivity, healthier journeys, and improved access to healthcare. Report P19
Climate: The GCTS is expected to deliver positive environmental outcomes and align with regional and national objectives. Report P19
Other: No other significant implications identified. Report P19
Who and where
Greater Cambridge residents, commuters and transport users Report 1.1, 2.2
Private sector, local authority and other key local stakeholders who took part in engagement Report 3.5
Employers and businesses represented through Cambridge Ahead's Transport Group Report 3.5
Greater Cambridge Shared Planning team working on the Local Plan Report 3.1, 3.4
Cambridge Growth Company, on Mass Rapid Transit options Report 3.1
Timeline
March 2024: GCTS funding approved at CA Board within existing MTFP Report P19
November 2025: Six stakeholder focus groups held, with 6 to 12 participants each Report 3.5
April to June 2026: Ongoing GCTS drafting, technical assessment and modelling, and co-working with CGC on Mass Rapid Transit Report 3.4
June 2026: Transport Committee to consider draft GCTS and summer engagement proposals Report 3.4
July to August 2026: Provisional engagement exercise and continued modelling and drafting Report 3.4
Summer 2026: CGC Strategic Outline Case for Mass Rapid Transit due to complete
September to November 2026: GCTS updated to reflect engagement outcomes; finalised modelling Report 3.4
November 2026: Transport Committee and Board to consider and approve the finalised GCTS Report 3.4
December 2026: Proposed submission of the Greater Cambridge Local Plan to Government Report 3.4
4 December 2026: CPCA officers invited to Cambridge Ahead's Transport Group meeting Report 3.5
Plain English for the jargon
GCTS: Greater Cambridge Transport Strategy
CPCA: Cambridgeshire and Peterborough Combined Authority
LTCP: Local Transport and Connectivity Plan, the CPCA's adopted plan under which the GCTS sits
MRT: Mass Rapid Transit, a strategic public transport option being examined for Cambridge
CGC: Cambridge Growth Company, commissioning the Strategic Outline Case for MRT
GCSP: Greater Cambridge Shared Planning, the team preparing the Greater Cambridge Local Plan
MHCLG: Ministry of Housing, Communities and Local Government
MTFP: Medium Term Financial Plan
SOC: Strategic Outline Case, the first phase of scheme development under DfT guidance
CaPCAM: CPCA's transport model used for preliminary public transport scenario modelling
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
A. To note and provide feedback on GCTS progress to date and planned next steps to achieve the Strategy approval in line with the Statement of Intent. B. To note the findings from the independent report on engagement with key stakeholders. A. Note and provide feedback on GCTS progress to date and planned next steps to achieve the Strategy approval in line with the Statement of Intent. B. Note the findings from the independent report on engagement with key stakeholders. ACTIONS: Officers to explore the possibility of convening an additional steering group meeting for Committee members in the coming weeks to review emerging options. Officers to explore establishing a schedule of regular updates and briefings, aiming for a monthly frequency, to ensure Committee members remain informed throughout the strategy development process.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A Note and provide feedback on GCTS progress to date and planned next steps to achieve the Strategy approval in line with the Statement of Intent B Note the findings from the independent report on engagement with key stakeholders
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☒ Jobs ☐ Resilience
☒ Connectivity ☒ Homes ☐ Performance
1. Purpose
1.1The GCTS will sit beneath the CPCA’s adopted LTCP and provide a Greater Cambridge focussed strategy for transport across the sub-region. The GCTS will set out connectivity requirements and measures, including how transport will contribute to the aspirations for growth of the economy, jobs and homes as set out in the draft Greater Cambridge Local Plan, our adopted Local Growth Plan, and emerging proposals for further growth proposed by the Cambridge Growth Company (CGC). The purpose of this paper is three-fold:
1.2Progress update: to update Transport Committee on progress with the GCTS since the November 2025 paper;
1.3Forward Look: to provide an overview of our proposed approach to strategy development over this period and a high-level work programme through to December 2026 and proposed adoption of the GCTS;
1.4Autumn 2025 Stakeholder Engagement Report: to provide members with the independent Stakeholder Engagement Report and a high level summary of key themes. 2. Proposal
2.1The CPCA is preparing the GCTS for three key reasons. These are to: Support the Greater Cambridge Local Plan: providing key transport evidence to support Local Plan growth ambitions alongside other transport evidence prepared by Cambridgeshire County Council as local highway authority; Support larger-scale growth ambitions: assessing and exploring implications of greater growth scenarios aligned with the Corporate Plan, the Local Growth Plan, and initiatives led by the Cambridge Growth Company (CGC); and Inform investment and funding decisions: setting out a high-level delivery framework for transport in Greater Cambridge to strengthen the case for resources supporting local growth and connectivity ambitions over the short, medium, and long term.
2.2The GCTS will support delivery of objectives across our Corporate Plan against our objectives for Connectivity and Growth: Connectivity: The GCTS will seek to set out how the Greater Cambridge transport network will ‘increase connectivity through better roads, faster trains, new stations and stops, and more modes of transport, like light rail. Public transport should be affordable, reliable and frequent, with integrated, multi-mode ticketing. Better transport links will connect more people to employment, leisure, essential services and training to unlock opportunity and drive growth.’ Growth: The GCTS will support the creation of ‘the conditions for growth through infrastructure-led development.’
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.