Budget and Performance Report

Noted Committee 1 paper

AI summaryCambridgeshire and Peterborough Combined Authority Transport Committee noted the Transport Division's Q3 25/26 financial position, with a £3.0m revenue variance and £10.7m of capital slippage.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTransport Division financial position to end of December 2025
Money£3.0m revenue variancePlus £10.7m of capital programme slippage
What happens nextCapital programme reviewFundamental review of capital programme planned
Who it affectsTransport DivisionOf the Cambridgeshire and Peterborough Combined Authority

What was decided

The Committee noted the financial position of the Transport Division for the financial year 25/26 to the end of Q3 in December 2025. Report P1

Why

The report updates performance against the 2025/26 budget up to the end of December 2025, covering income, revenue expenditure and the capital programme. Report 1.1, 3.1

Income is higher than the profiled budget due to two new LEVI grants for electric vehicles, while capital spending is being reprofiled against confirmed milestones. Report 3.3, 4.1

Forecast outturn shows a £3.0m revenue variance, of which £1.5m is requested to slip into 2026/27. Report 3.6

What happens next

The capital programme will be fundamentally reviewed as part of a forthcoming major transport capital programme review, to reset phasing assumptions and strengthen deliverability. Report 4.1

Officers are reviewing forecasting and challenge processes to strengthen confidence in future projections and identify delivery risks earlier. Report 4.1

The money

  • £3.0m Forecast revenue outturn variance Report 3.6
  • £1.5m Revenue amount requested to slip into 2026/27 Report 3.6
  • -£3,030k Total Transport Revenue Expenditure forecast outturn variance Report 3.4, P12, P13
  • £1,505k Total Transport Revenue Expenditure forecast deferral to 2026/27 Report 3.4, P12, P13
  • £10.7m Transport capital programme expected slippage Report 4.2
  • -£10,676k Total Transport Capital forecast outturn variance Report 4.1, P17, P18
  • £10,676k Total Transport Capital forecast deferral Report 4.1, P17, P18

Implications

  • Financial: No additional financial implications beyond those set out in the main body of the report. Report P21
  • Legal: The Combined Authority is required to prepare a balanced budget in accordance with statutory requirements. Report P22
  • Risk: Capital programme reprofiling reflects a reassessment of delivery assumptions and external dependencies, and is not a reduction in overall funding availability. Report 4.1
  • Risk: A key design risk on Cygnet Bridge has been de-escalated, giving more certainty to the delivery programme. Report 4.2

Who and where

  • Transport Division of the Combined Authority Report 1.1, 3.1
  • Public transport users in Cambridgeshire and Peterborough Report 3.4, P12, P13

Timeline

  • 31 December 2025: Period end for the Q3 25/26 financial position Report 3.1
  • Spring 2026: Mobilisation and construction of Cygnet Bridge expected Report 4.2
  • 2026/27: Active Travel revenue funding to be carried forward to next financial year Report 3.6
  • 2026/27: £1.5m of revenue spend to be applied to 2026/27 Report 3.6

Plain English for the jargon

  • LEVI: Local Electric Vehicle Infrastructure, grants supporting electric vehicles
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

A. To note the financial position of the Transport Division for the financial year 25/26 to end of Q3 in December 2025. To note the financial position of the Transport Division for the financial year 25/26 to end of Q3 in December 2025
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Transport Committee

Recommendations

A Note the financial position of the Transport Division for the financial year 25/26 to end of Q3 in December 2025

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☐ Resilience

☐ Connectivity ☐ Homes ☒ Performance

1. Purpose

1.1To provide an update of the financial position for 2025/26 and to provide analysis against the 2025/26 budgets, up to the period ending December 2025.

Background

3.1This report provides an update of the performance against budget up to the period ending December 2025. Tables show approved budgets. 3. Revenue Income and Expenditure

3.2A breakdown of the Transport income for the period to 31 December 2025 is set out in Table 1 below. Table 1 25/26 25/26 25/26 25/26 25/26 25/26 Actual Budget Variance Budget FO Variance Transport Income YTD YTD YTD FY FY FY £k £k £k £k £k £k Highways Maintenance and Pothole Fund -28,115 -28,115 0 -37,487 -37,487 0 Local Transport Grant -3,475 -3,475 0 -4,633 -4,633 Bus Service Improvement Plan (BSIP+) -10,179 -10,179 0 -10,179 -10,179 0 Public Transport - Bus Service Operators -409 -409 0 -409 -409 0 Grant Active Travel -3,795 -3,795 0 -3,795 -3,795 0 LEVI Pavement Channels -317 0 -317 0 -362 -362 LEVI Capacity -202 0 -202 0 -202 -202 Transport capacity grant -614 -614 0 -819 -819 0 Transport Levy -10,981 -10,981 0 -13,727 -13,727 0 Total Transport Income -58,087 -57,568 -519 -71,049 -71,613 -564

3.3The income received to date in the year is higher than the profiled budget, this is due to 2 new LEVI grants received. Both are to support electric vehicles.

3.4A breakdown of the Transport Revenue Expenditure for the period to 31 December 2025 is set out in Table 2 below. Table 2

25/26 25/26 25/26 25/26 25/26 25/26 25/26 Actual Budget Variance Budget FO Variance Deferral Transport Revenue Expenditure YTD YTD YTD FY FY FY

£k £k £k £k £k £k £k Active Travel Grant 0 50 -50 100 0 -100 100 Active Travel 0 0 0 1,295 183 -1,112 1,112 Civil Parking Enforcement 0 0 0 150 150 0 - Cycle Safety and Security 0 0 0 18 18 0 - Local Electric Vehicle Infrastructure 60 0 60 239 239 0 - (LEVI) Local Transport & Connectivity Plan 212 333 -121 693 500 -193 193 Market Towns Cycle Support 0 50 -50 100 0 -100 100 Try-BeforeYou-Buy eCargo bikes 0 0 0 36 36 0 - project Telraam Traffic Monitors 0 0 0 13 13 0 - Contributions from Mayoral Precept -8,910 -8,944 34 -11,138 -11,138 0 - Development of Bus Franchising 402 585 -183 772 772 0 - Public Transport - Bus Service 0 0 0 409 409 0 - Operators Grant Public Transport - Bus Services 9,869 11,225 -1,356 15,096 14,346 -750 - Public Transport - Concessionary 5,492 6,010 -518 9,002 8227 -775 - Fares Public Transport - Contact Centre 13 52 -39 312 312 0 - Public Transport - Fare Cap 2,549 2,916 -367 2,916 2,916 0 Extension Public Transport - Reduced Fares 3,297 2,790 507 4,346 4,346 0 - for Under 25´s Public Transport - RTPI, 379 254 125 339 339 0 - Infrastructure & Information Public Transport - Team and 642 718 -76 957 957 0 - Overheads Total Transport Revenue 14,005 16,039 -2,034 25,655 22,625 -3,030 1,505 Expenditure 3.5 Expenditure to date is £2.0m lower that budget to date mainly the area of public transport for the following reasons. Public Transport Bus Services - largely due to the later starting of some contracted services, which will result in an underspend at year end of £750k. Any underspend will be transferred to the passenger transport operations reserve. Public Transport Concessionary Fares – number of passengers continues to be below pre-Covid levels. Increases from the introduction of pre 9.30 use have yet to be seen resulting in an expected underspend of £775k. Any underspend will be transferred to the passenger transport operations reserve.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget and Performance ReportReport 166 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 17 attended
RJ
Richard JeremyOfficer, expected
CB
Councillor Chris Boden Mayor's RepresentativeChair, apologies
KT
Councillor Katie Thornburrow Cambridge City CouncilCommittee Member, present
AB
Councillor Alex Beckett Cambridgeshire County CouncilVice-Chair, present
AS
Councillor Alan Sharp East Cambridgeshire District CouncilCommittee Member, present
CS
Councillor Chris Seaton Fenland District CouncilCommittee Member, present
SW
Councillor Sam Wakeford Huntingdonshire District CouncilCommittee Member, present
PM
Councillor Peter McDonald South Cambridgeshire District CouncilCommittee Member, present
AE
Councillor Angus Ellis Peterborough City CouncilCommittee Member, present
JN
Councillor Jon Neish Overview and Scrutiny Committee RapporteurGuest, apologies
SS
Councillor Simon Smith Cambridge City CouncilSubstitute
LD
Councillor Lorna Dupre Cambridgeshire County CouncilSubstitute

All 17 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Budget and Performance ReportThis decision
  2. Budget and Performance Report - Drawdown of Transport Capacity GrantApproved
  3. Budget and Performance ReportNoted
  4. Budget & Performance ReportNoted
  5. Budget and Performance ReportNoted
  6. Budget and Performance ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Transport Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi... Approved Open
9 Sep 2026 Forward PlanA. That the Combined Authority Forward Plan be noted A. That the Combined Authority Forward Plan be noted. ACTION: 1.... Noted Open
9 Sep 2026 Developer Funding Governance(Unanimous) A. To note the CPCA action plan to improve governance and delivery of developer funding for bus services ... Noted Open
9 Sep 2026 Bus Services Reimagined – Final Service Change ProposalsA. To note the outcome of the contracted bus services review, including the evidence base, consultation feedback and ... Noted Open
9 Sep 2026 Local Transport Delivery Plan(Unanimous) To recommend to the Combined Authority Board that they: A. Approve the (LTDP) – Cambridgeshire County Cou... Approved Open