Cambridgeshire and Peterborough Combined Authority
Combined Authority Board, Wednesday 15 July 2026 at 10.00am

Business Case Approvals - Officer Decisions

Noted Committee 1 paper

AI summaryCombined Authority Board notes officer decisions on multiple project investments and change requests approved under the Single Assurance Framework since March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo vote required
MoneyNot stated
What happens nextNot stated
Who it affectsProject and fund recipientsSkills, transport and digital projects

What was decided

The Board noted officer decisions for projects under the Single Assurance Framework delegation from Funding Panels held on 03 March, 15 April, and 02 June 2026. Report P4

No vote was required because the item was for noting only. Report P4

The report covered both business case approvals and change request approvals made by officers since the March Board. Report P4, P5

Why

Under the SAF arrangements approved by the Board on 26 November 2025, Executive Directors have delegated authority to approve project investments of £500k and below and timing change requests of up to three months. Report P4

The Chief Executive has delegated authority to approve project investments of over £500k and up to £2m. Report P4

The report is for noting by the Board to record decisions made under delegated authority. Report P4

What happens next

The report does not set out any next steps because it is for noting only. Report P4

The money

  • £500k and below Executive Director delegation threshold for project investments Report P4
  • over £500k and up to £2m Chief Executive delegation threshold for project investments Report P4

Options considered

  • Chosen: Note the officer decisions. To record decisions made under delegated authority from the Board Report P4

Implications

  • Governance: Decisions on projects up to £2m continue to be made by officers under delegated authority without full Board approval. Report P4
  • Other: Approved projects align with strategic objectives of Connectivity, Homes and Performance, and with Growth, Jobs and Resilience arrangements. Report P4

Who and where

  • Further Education construction skills training providers Report P4
  • Changing Futures programme partners (2025-28) Report P4
  • National Cycle Network school neighbourhood projects Report P4
  • UK Shared Prosperity Fund and Rural England Prosperity Fund recipients Report P5
  • Connect to Work digital platform providers Report P5
  • Local Electric Vehicle Infrastructure fund delivery partners Report P5
  • Wysing Arts and Wildlife Trust (Opportunity Fund) Report P5
  • Rough sleeping prevention and recovery service providers Report P5

Timeline

  • 26 November 2025: SAF arrangements approved by Combined Authority Board Report P4
  • 2 March 2026: FE Teacher Industry Exchange Programme (Construction) approved Report P4
  • 3 March 2026: First Funding Panel held Report P4
  • 15 April 2026: Second Funding Panel held; Careers Hub extension approved Report P4, P5
  • 2 June 2026: Third Funding Panel held Report P4
  • 9 June 2026: Rough Sleeping Prevention and Recovery Grant approved Report P5
  • 22 June 2026: Funding Committee meeting Report P2
  • 15 July 2026: Combined Authority Board notes officer decisions Report P1

Plain English for the jargon

  • SAF: Single Assurance Framework
  • UKSPF: UK Shared Prosperity Fund
  • REPF: Rural England Prosperity Fund
  • LEVI: Local Electric Vehicle Infrastructure
  • RSPARG: Rough Sleeping Prevention and Recovery Grant
  • NCN: National Cycle Network
  • FE: Further Education
  • RPF4: Regulatory Platform for Startup Ecosystem Navigation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16a

Resolved

It was resolved to : A Note the Officer Decisions for projects under the Single Assurance Framework delegation from Funding Panels held on 03 March, 15 April, and 02 June 2026.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Combined Authority Board 15 July 2026

Title: Funding Committee Decisions Committee Date: 22 June 2026 Meeting Link: Funding Committee 22 June 2026

Agenda Item Officer Decisions

Recommendations: To note the Officer Decisions for projects under the Single Assurance Framework delegation from Funding Panels held on 03 March, 15 April, and 02 June 2026. Voting No vote required Arrangements: Strategic Growth Jobs Resilience Objectives: Connectivity Homes Performance Purpose: Under the SAF arrangements approved by the Combined Authority Board at its meeting on 26 November 2025, the Executive Directors have delegated authority to approve project investments of £500k and below plus timing change requests of up to three months, and the Chief Executive has delegated authority to approve project investments of over £500k and up to £2m. This report sets out the projects which have been approved by Officers in accordance with the delegated authority from the Board and is for noting. Decisions taken: The table below sets out the Business Case Approvals under delegated authority since the March Board. Decision Date Link FE Teacher Industry 2 March 2026 Decision - FE Teacher Industry Exchange Programme Exchange Programme (Construction) (Construction) Changing Futures (2025-28) 25 February 2026 Decision - Changing Futures National Cycle Network 15 May 2026 Decision - NCN School (NCN) School Neighbourhoods Neighbourhoods

The table below sets out the Change Request Approvals under delegated authority since the March Board. Decision Date Link UK Shared Prosperity Fund 17 March 2026 Decision - UK Shared Prosperity Fund (UKSPF) and Rural England (UKSPF) and Rural England Prosperity Prosperity Fund (REPF) Fund (REPF) KD2026/016 Connect to Work 11 February 2026 Decision - Change Request - Connect to Work Digital Platform for 17 March 2026 Decision - Digital Platform for Businesses RPF4 Businesses RPF4 (Regulatory Platform for Startup Ecosystem Navigation) Careers Hub Annual Grant 15 April 2026 Decision - Careers Hub Annual Grant Extension Extension UK Shared Prosperity Fund 27 April 2026 Decision - UK Shared Prosperity Fund (UKSPF) (UKSPF) Change Request Active Travel Fund 4 17 March 2026 Decision - Active Travel Fund 4 Extension Extension Change Request - ODN021- 2026 LEVI – Capital Fund 17 March 2026 Decision - Local Electric Vehicle Infrastructure (LEVI) fund - Capital Fund Delivery of the Digital 30 April 2026 Decision - Delivery of the Digital Connectivity Strategy 2025- Connectivity Strategy 2025-2029 - 2029 ODN026-2026 Opportunity Fund – Wysing 30 April 2026 Decision - Opportunity Fund - Wysing Arts and Wildlife Trust Arts and Wildlife Trust ODN025-2026 Rough Sleeping Prevention 9 June 2026 Decision - Rough Sleeping Prevention and Recovery Grant and Recovery Grant (RSPARG) - ODN029-2026

Full Funding SAF Business Case Approvals - Officer Decisions Committee report: Background Single Assurance Framework Review Papers:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Business Case Approvals: Officer DecisionsDecisions 175 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 23 attended
PB
Paul Bristow Cambridgeshire and Peterborough Combined AuthorityChair, present
KT
Councillor Katie Thornburrow Cambridge City CouncilCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, present
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, apologies, sent representative
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, present
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, present
SQ
Councillor Shabina Qayyum Peterborough City CouncilCommittee Member, present
BM
Councillor Brian Milnes South Cambridgeshire District CouncilCommittee Member, present
SG
Shaun Grady Business BoardCommittee Member, apologies
DP
Darryl Preston Police and Crime CommissionerCo-Optee, apologies
RP
Robin Porter Central East Integrated Care BoardCo-Optee, apologies, sent representative
CM
Councillor Christopher Morris Cambridgeshire and Peterborough Fire AuthorityCo-Optee, present

All 23 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Business Case Approvals - Officer DecisionsThis decision
  2. Active Travel Consolidated Settlement 2026-2030 (Business Case) - KD2026/059Approved
  3. Update on A141 Outline Business CaseNoted
  4. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved
  5. Single Assurance Framework Business Case Approvals: Officer DecisionsNoted
  6. Single Assurance Framework Business Case Approvals: Funding Committee DecisionsApproved

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open