AI summaryTiger on Demand bus services across four Cambridgeshire districts will be re-procured as two lots from 11 January 2027, after the Transport Committee unanimously recommended the move to the Combined Authority Board.
Written from the decision and the officer reportPDF Pro
OutcomeNotedUnanimous vote to recommend reprocurement to Board
MoneyNo figure givenOfficers not anticipating large cost change, subject to tender
What happens nextBoard to decideCombined Authority Board will consider recommendations
Who it affectsFour Cambridgeshire districtsEast Cambridgeshire, Fenland, South Cambridgeshire, Huntingdonshire
What was decided
The Committee unanimously recommended that the Combined Authority Board approves re-procurement of the Tiger on Demand services from 11 January 2027, following expiry of current contracts on 10 January 2027. Report P1
The Committee recommended a two-lot procurement approach: a Northern Lot covering Fenland and East Cambridgeshire, and a Southern Lot covering Huntingdonshire and South Cambridgeshire. Report P1, 2.1
The Committee recommended delegated authority for the Assistant Director, Public Transport, with the Director for Legal and Governance and the Chief Finance Officer, to finalise procurement, award contracts and make minor amendments. Report P1
Why
Current contracts expire on 10 January 2027 and re-procurement is needed to maintain continuity of service and avoid disruption for communities relying on the service. Report 1.1
The lot structure is intended to support operational resilience, encourage market interest, align related operating areas and provide flexibility for future contract management.
Re-procurement offers the opportunity to strengthen performance expectations, contract management, operational resilience and alignment with the transition towards franchising.
What happens next
The Combined Authority Board will consider the recommendations to approve the re-procurement, the two-lot structure and the delegated authority. Report P1
Officers will progress the procurement process, with tender outcomes assessed for cost and quality, and finance officers engaged on the outcome. Report P12
The new contract will run from 11 January 2027, with the South Cambridgeshire zone reflecting its July 2026 expansion and potential use of a vehicle to support transport to Swavesey Village College.
Options considered
Chosen: Approve and recommend re-procurement with two-lot structure and delegated authority. Ensures continuity from 11 January 2027 and supports resilience Report P1, 1.1
Implications
Financial: Procurement to proceed within available budget envelope, subject to affordability checks and tender outcomes; no large change in ongoing contract costs anticipated. Report P12
Legal: Procurement must comply with applicable procurement law, subsidy control requirements, contractual requirements and public law principles. Report P12
Equalities: Maintaining accessible public transport supports access to healthcare, education, employment, shopping, leisure and social participation, particularly for residents with limited alternative transport options. Report P12
Climate: Demand responsive transport can support more sustainable local travel and reduce reliance on private car journeys where practical. Report P12
Other: Contract should maintain flexibility to respond to user feedback, local network changes, school transport integration opportunities and future franchising requirements. Report P12
Who and where
Residents in East Cambridgeshire, Fenland, South Cambridgeshire and Huntingdonshire who use the service Report 1.1
Passengers travelling to Huntingdon Bus Station, Huntingdon Railway Station, Hinchingbrooke Hospital, Ely Market, Ely Rail Station, March Railway Station, Cambourne Village College and Morrisons in Cambourne Report 2.4
Students potentially travelling to Swavesey Village College, in partnership with Cambridgeshire County Council
Bus operators and bidders responding to the tender Report P1, 2.1
Timeline
July 2026: South Cambridgeshire zone expansion
End of July 2026: Performance data: 0.2% of booked trips (93 trips) had no drivers available Report 2.4
10 January 2027: Expiry of current Tiger on Demand contracts Report 1.1
11 January 2027: Proposed start of new re-procured Tiger on Demand contracts Report 1.1
Plain English for the jargon
Tiger on Demand: A flexible, bookable public transport option that complements the wider bus network in areas with limited fixed-route services.
Lot: A portion of a procurement contract, in this case split into a Northern Lot and a Southern Lot.
CPCA: Cambridgeshire and Peterborough Combined Authority.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
(Unanimous) A. To note the performance, development and strategic role of the Tiger on Demand services across East Cambridgeshire, Fenland, South Cambridgeshire and Huntingdonshire. B. To recommend that the Combined Authority Board approves the re-procurement of the Tiger on Demand services from 11 January 2027, following expiry of the current contracts on 10 January 2027 C. To recommend that the Combined Authority Board approve the proposed procurement approach comprising two lots: a Northern Lot covering Fenland and East Cambridgeshire, and a Southern Lot covering Huntingdonshire and South Cambridgeshire. D. To recommend that the Combined Authority Board approves delegated authority for the Assistant Director, Public Transport, in consultation with the Director for Legal and Governance and the Chief Finance Officer, to take all necessary steps to finalise the procurement, award and enter into contracts, and make any minor amendments required to give effect to the approved approach, subject to affordability, legal compliance and statutory requirements
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A To note the performance, development and strategic role of the Tiger on Demand services across East Cambridgeshire, Fenland, South Cambridgeshire and Huntingdonshire. B To recommend that the Combined Authority Board approves the re-procurement of the Tiger on Demand services from 11 January 2027, following expiry of the current contracts on 10 January 2027. C To recommend that the Combined Authority Board approve the proposed procurement approach comprising two lots: a Northern Lot covering Fenland and East Cambridgeshire, and a Southern Lot covering Huntingdonshire and South Cambridgeshire. D To recommend that the Combined Authority Board approves delegated authority for the Assistant Director, Public Transport, in consultation with the Director for Legal and Governance and the Chief Finance Officer, to take all necessary steps to finalise the procurement, award and enter into contracts, and make any minor amendments required to give effect to the approved approach, subject to affordability, legal compliance and statutory requirements.
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☐ Growth ☒ Jobs ☒ Resilience
☒ Connectivity ☐ Homes ☒ Performance 1. Purpose
1.1This report seeks approval to re-procure the Tiger on Demand services, enabling continuity of provision from 11 January 2027 when the current contracts expire. 1.2 Tiger on Demand provides a flexible, bookable public transport option in locations where conventional fixed-route services are limited, less viable or unable to meet dispersed local travel needs. The service is intended to complement, rather than replace, the wider bus network by improving access to rail stations, education, healthcare, employment and community facilities across East Cambridgeshire, Fenland, South Cambridgeshire and Huntingdonshire. The re-procurement is needed to secure continuity from 11 January 2027, following expiry of the current contracts on 10 January 2027, and to ensure that the service remains aligned with changing passenger demand and local network requirements. The new contract also provides an opportunity to strengthen performance expectations, contract management arrangements and operational resilience, including the ability to respond to zone expansion, school transport integration opportunities and passenger feedback. 1.3 The service has developed during the current contract through measures including, targeted stop additions, community engagement, event travel, zone expansion and practical arrangements that support school travel where this can be delivered cost-effectively. These developments demonstrate the strategic role of Tiger on Demand in supporting connectivity for communities that have fewer practical alternatives and provide the basis for re-procuring the service on a more resilient footing.
2. Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport Committee at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.