Transport Committee, Wednesday 9 September 2026 at 10.00am

Budget and Performance Report

Noted Committee 1 paper

AI summaryCambridgeshire and Peterborough Transport Committee notes 2026/27 Transport Division position to June and backs £125,000 draw from capacity grant for connectivity plan work.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNote financial position; recommend capacity grant drawdown
Money£125,000 grant drawdownLocal transport capacity grant for plan work
What happens nextCA Board to decide drawdownRecommendation B referred to Combined Authority Board
Who it affectsTransport Division and usersBus, cycle, highways, stations schemes

What was decided

The Committee noted the Transport Division's financial position for 2026/27 to June 2026. Report P1

The Committee recommended that the Combined Authority Board approve the drawdown of Transport Capacity Grant to fund work on the transport and connectivity plan. Report P2

Why

The report gave the year-to-date position against the 2026/27 Transport budget and sought approval to spend £125,000 of capacity grant on continued Local Transport and Connectivity Plan development. Report 1.1, 1.2, P7

Strategic objectives identified were Growth, Jobs and Connectivity. Report P5, P6

What happens next

The Combined Authority Board will be asked to approve the £125,000 capacity grant drawdown. Report 1.2

A procurement exercise is under way for the Local Electric Vehicle Infrastructure scheme, which is now expected to start in quarter 4 of 2026/27.

The money

  • £125,000 Drawdown from local transport capacity grant for the Local Transport and Connectivity Plan Report 1.2
  • £19m Transport income received to date, in line with expectations
  • £1.7m Year-to-date revenue expenditure underspend against budget, mainly in public transport bus services Report P14
  • £125k Forecast outturn revenue variance, due to Market Towns Cycle support delay spread over 3 years Report P14

Options considered

  • Chosen: Note the 2026/27 Transport financial position to June 2026 Report P1
  • Chosen: Recommend CA Board approval of Transport Capacity Grant drawdown for the connectivity plan. Funds continued strategy work under the Local Transport and Connectivity Plan Report P2, 1.2

Implications

  • Financial: Revenue forecast outturn is in line with the expected budget aside from a £125k variance from the delayed Market Towns Cycle support. Report P19
  • Financial: Public Transport Bus Services are underspent year to date because of a lag in contractor billing. Report P14
  • Legal: The Combined Authority is required to prepare a balanced budget in line with statutory requirements. Report P19

Who and where

  • Transport Division of the Combined Authority Report P1, 2.1
  • Public transport bus passengers and operators Report P14
  • Users of cycle, active travel and market town cycling schemes Report P14
  • Electric vehicle infrastructure users awaiting LEVI rollout Report P17
  • Residents and road users on A10, March junction, A141 and other capital schemes Report 4.1, P17

Timeline

  • 30 June 2026: Year-to-date position used for the report Report 2.1, 3.1, 4.1
  • Quarter 4 of 2026/27: LEVI project now expected to get underway
  • 2026-09-09: Transport Committee considered the report

Plain English for the jargon

  • CA Board: Combined Authority Board of Cambridgeshire and Peterborough
  • LEVI: Local Electric Vehicle Infrastructure scheme
  • BSIP+: Bus Service Improvement Plan
  • LUF: Levelling Up Fund
  • SOBC: Strategic Outline Business Case
  • FO Variance: Forecast Outturn Variance against the full-year budget
  • RTPI: Real Time Passenger Information
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

A. Note the financial position of the Transport Division for the financial year 26/27 to June 2026. B. Recommend to the CA Board to approve the drawn down of Transport Capacity Grant to fund work on the transport and connectivity plan * text in bold denotes changes to the recommendation. A. Note the financial position of the Transport Division for the financial year 26/27 to June 2026. B. Recommend to the CA Board to approve the drawn down of Transport Capacity Grant to fund work on the transport and connectivity plan * text ... view the full minutes text for item 15.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Transport Committee

Recommendations

A Note the financial position of the Transport Division for the financial year 26/27 to June 2026

B To approve the drawn down of Transport capacity grant to fund work on the transport and connectivity plan.

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☐ Resilience

☒ Connectivity ☐ Homes ☒ Performance

1. Purpose

1.1To provide an update of the financial position for 2026/27 and to provide analysis against the 2026/27 budgets, up to the period ending June 2026

1.2To approve the draw of £125,000 from the local transport capacity grant to fund continued work on the development of strategies under the Local Transport and Connectivity Plan

Background

2.1This report provides an update of the performance against budget up to the period ending June 2026. 3. Revenue Income and Expenditure

3.1A breakdown of the Transport income for the period to 30 June 2026 is set out in Table 1 below. Table 1 26/27 26/27 26/27 26/27 26/27 26/27 Actual Budget Variance Budget FO Variance Transport Income YTD YTD YTD FY FY FY £k £k £k £k £k £k Highways Maintenance and - -10,935 -10,935 0 -43,741 0 Pothole Fund 43,741 Bus Service Improvement Plan - -2,619 -2619 0 -10,477 0 (BSIP+) 10,477 Public Transport - Bus Service 0 0 0 -411 -411 0 Operators Grant Active Travel -1,656 -1656 0 -6624 -6624 0 Peterborough Station Quarter 0 0 0 -10536 -10536 0 - Transport Levy -4,422 -4,422 0 -14,742 0 14,742 - Total Transport Income -19,632 -19632 0 -86,531 0 86,531 3.2 The income received to date in the year is £19m in line with expectations. 3.3 The forecast outturn is in line with the expected budget 3.4 A breakdown of the Transport Revenue Expenditure for the period to 30 June 2026 is set out in Table 2 below. Table 2

26/27 26/27 26/27 26/27 26/27 26/27 26/27 Transport Revenue Actual Budget Variance Budget FO Variance Deferral Expenditure YTD YTD YTD FY FY FY

£k £k £k £k £k £k £k Active Travel Grant 0 0 0 150 150 0 - Active Travel 0 0 0 790 790 0 - Cycle Safety 0 0 0 9 9 0 - and Security Local Electric Vehicle 32 5 27 73 73 0 - Infrastructure (LEVI) Local Transport & 125 272 -147 1263 1263 0 - Connectivity Plan Market Towns Cycle 0 0 0 150 25 -125 125 Support Try-Before You-Buy 0 0 0 18 18 0 - eCargo bikes project Telraam Traffic 8 0 8 13 13 0 - Monitors Contributions from - -3,390 -3,387 -3 -11,288 0 - Mayoral Precept 11,288 Development of Bus 132 382 -250 1,725 1,725 0 - Franchising Public Transport - 2,709 3,690 -981 15,777 15,777 0 - Bus Services Public Transport - 1,994 2,124 -130 9,202 9,202 0 - Concessionary Fares Public Transport - 7 79 -72 318 318 0 - Contact Centre Public Transport - Reduced Fares for 1,069 1,185 -116 4,290 4,290 0 - Under 25´s Public Transport - RTPI, Infrastructure & 82 86 -4 345 345 0 - Information Public Transport - 249 249 0 996 996 0 - Team and Overheads Total Transport Revenue 3,017 4,685 -1,668 23,831 23,706 -125 125 Expenditure 3.5 Expenditure to date is £1.7m lower that budget to date mainly the area of public transport for the following reasons. Public Transport Bus Services - the underspend here is because of a lag in billing from contractors 3.6 Forecast outturn shows a variance of £125k as the start of the Market Towns Cycle support was delayed and will now be spread over 3 years.

4. Capital Expenditure

4.1A breakdown of the Transport Capital Expenditure for the period to 30 June 2026 is set out below. Table 3

26/27 26/27 26/27 26/27 26/27 26/27 26/27 Transport Capital Actual Budget Variance Budget FO Variance Deferral Expenditure YTD YTD YTD FY FY FY

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget and Performance ReportReport 149 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 20 attended
RG
Rachel GoodwinCouncil Staff, expected
PM
Peter MannOfficer, expected
TJ
Terence JamesCouncil Staff, expected
RJ
Richard JeremyOfficer, expected
CB
Councillor Chris Boden Mayor's RepresentativeChair, present
TB
Councillor Tim Bick Cambridge City CouncilCommittee Member, present
AB
Councillor Alex Beckett Cambridgeshire County CouncilCommittee Member, apologies, sent representative
AE
Councillor Angus Ellis Peterborough City CouncilCommittee Member, present
BM
Councillor Brian Milnes South Cambridgeshire District CouncilCommittee Member, apologies, sent representative
TS
Councillor Tom Sanderson Huntingdonshire District CouncilCommittee Member, apologies, sent representative
AS
Councillor Alan Sharp East Cambridgeshire District CouncilCommittee Member, present
CS
Councillor Chris Seaton Fenland District CouncilCommittee Member, apologies, sent representative

All 20 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Budget and Performance ReportThis decision
  2. Budget and Performance Report - Drawdown of Transport Capacity GrantApproved
  3. Budget and Performance ReportNoted
  4. Budget & Performance ReportNoted
  5. Budget and Performance ReportNoted
  6. Budget and Performance ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Transport Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of the previous meetingThe minutes of the meeting on 17 June 2026 were approved as an accurate record. The Action Log was noted by the Commi... Approved Open
9 Sep 2026 Forward PlanA. That the Combined Authority Forward Plan be noted A. That the Combined Authority Forward Plan be noted. ACTION: 1.... Noted Open
9 Sep 2026 Developer Funding Governance(Unanimous) A. To note the CPCA action plan to improve governance and delivery of developer funding for bus services ... Noted Open
9 Sep 2026 Bus Services Reimagined – Final Service Change ProposalsA. To note the outcome of the contracted bus services review, including the evidence base, consultation feedback and ... Noted Open
9 Sep 2026 Local Transport Delivery Plan(Unanimous) To recommend to the Combined Authority Board that they: A. Approve the (LTDP) – Cambridgeshire County Cou... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies