AI summaryCombined Authority Board has authorised contingency planning for the possible closure of the Greater South East Net Zero Hub on 31 March 2027, with estimated redundancy costs of approximately £670,000.
Written from the decision and the officer reportPDF Pro
OutcomeNoted
MoneyApproximately £670,000Estimated redundancy and pension strain liability, including £80,000 for close-down interim staffing
What happens nextMinisterial decision by 20 September 2026Government decision expected on future of English Net Zero Hubs programme
Who it affectsNot stated
What was decided
The Board noted the current uncertainty on the future funding and remit of the Greater South East Net Zero Hub and the need to plan for the worst-case scenario that the Hub closes on 31 March 2027 and all Hub posts are made redundant or there is insufficient funding to maintain the current Hub establishment. Report P1
The Board authorised officers to undertake contingency planning for managed closure or restructure, including workforce consultation planning, programme exit planning, communications, financial provision and legal assurance. Report P1
The Board delegated authority to the Chief Executive, in consultation with the Monitoring Officer, Section 73 Officer and HR lead, to initiate statutory consultation and associated employment processes if the Ministerial decision impacts on staffing structure or if timing requires preparatory action to protect the Combined Authority's position. Report P1
Why
A Ministerial decision on the future of the English Hubs is expected by 20 September 2026, following a delay from July, creating a narrow window for the Combined Authority to take necessary employment, financial and programme-management actions.
On 9 September the Hubs were provided an update that the Minister is minded to keep the Hub programme operating beyond April 2027 while a transition model is developed, with DESNZ officials asked to establish minimum viable functions and costs.
The proposed approach enables the Combined Authority to manage financial and employment risk prudently while continuing to support local authorities and community energy organisations.
What happens next
Statutory consultation to commence by 30 September 2026 if required, to protect the statutory timetable and ensure staff receive timely formal communication. Report 2.1, 4.4
Programme exit and handover plan to be agreed by January 2027, confirming treatment of live programmes, grants, contracts, claims, records and partner communications. Report 4.4
Hub closure on 31 March 2027 to end operational activity and complete employment, financial and programme close-down actions. Report 4.4
The money
£670,000 Estimated redundancy and pension strain liability, including £80,000 for close-down interim staffing Report 2.1
£80,000 Close-down interim staffing within the total redundancy and pension strain estimate Report 2.1
Options considered
Chosen: Scenario 1: Hub closes on 31 March 2027. Board authorised officers to prepare for managed closure as a risk-management measure, with statutory consultation to commence by 30 September 2026 if required, and estimated redundancy and pension strain liability of approximately £670,000 Report 2.1, P1
Rejected: Scenario 2: Hub continues with reduced or different remit. Contingency planning only; continuation depends on Government confirming reduced objectives, scope and funding Report 2.1
Rejected: Scenario 3: Hub continues at current resource level. Contingency planning only; continuation depends on confirmed funding, clear mandate and robust business plan Report 2.1
Implications
Financial: Estimated redundancy and pension strain liability of approximately £670,000, including £80,000 for close-down interim staffing, with funds ringfenced
Legal: Closure or significant changes would require compliance with employment law, statutory consultation, redundancy, notice, redeployment and equality obligations
Equalities: An equality impact assessment and staff wellbeing plan will be developed to ensure fair, transparent and evidence-based processes
Staffing: All Hub posts would be placed at risk of redundancy if the Hub closes, with workforce consultation planning, redeployment options and wellbeing support required Report 4.1
Risk: High risks identified include Ministerial decision delayed beyond critical HR timetable and insufficient time to consult properly Report 4.5
Who and where
Staff at the Greater South East Net Zero Hub Report 4.1
Local authorities and community energy organisations Report 4.1
DESNZ (Department for Energy Security and Net Zero) Report 3.1
Timeline
20 September 2026: Ministerial decision expected on whether closure, reduced continuation or maintained resource is the planning assumption Report 4.4
30 September 2026: Statutory consultation to commence if required, to protect statutory timetable Report 2.1, 4.4
January 2027: Programme exit and handover plan to be agreed, confirming treatment of live programmes, grants, contracts, claims, records and partner communications Report 4.4
31 March 2027: Hub closure to end operational activity and complete employment, financial and programme close-down actions Report 2.1, 4.4
Plain English for the jargon
GSENZH: Greater South East Net Zero Hub, established in 2018 to deliver local energy programmes and community energy grants on behalf of DESNZ
DESNZ: Department for Energy Security and Net Zero, the Government department that funds the Hub programme
Pension strain: Cost arising when pension benefits become payable earlier than expected due to redundancy
Statutory consultation: Legal requirement to consult with employees and their representatives before making redundancies
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
It was resolved to : A Note the current uncertainty on the future funding and remit of the Greater South East Net Zero Hub and the need to plan for the worst-case scenario that the Hub closes on 31 March 2027 and all Hub posts are made redundant or there is insufficient funding to maintain the current Hub establishment. B Authorise officers to undertake contingency planning for managed closure or restructure, including workforce consultation planning, programme exit planning, communications, financial provision and legal assurance. C Delegate authority to the Chief Executive, in consultation with the Monitoring Officer, Section 73 Officer and HR lead, to initiate statutory consultation and associated employment processes if the Ministerial decision impacts on staffing structure or if timing requires preparatory action to protect the Combined Authority’s position.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting.Source: democracy.cambridgeshirepeterborough-ca.gov.uk
Follow this further
Built from Cambridgeshire and Peterborough Combined Authority's papers
A Note the current uncertainty on the future funding and remit of the Greater South East Net Zero Hub and the need to plan for the worst-case scenario that the Hub closes on 31 March 2027 and all Hub posts are made redundant or there is insufficient funding to maintain the current Hub establishment. B Authorise officers to undertake contingency planning for managed closure or restructure, including workforce consultation planning, programme exit planning, communications, financial provision and legal assurance. C Delegate authority to the Chief Executive, in consultation with the Monitoring Officer, Chief Finance Officer and HR lead, to undertake statutory consultation and all associated employment processes if the Ministerial decision impacts on staffing structure or if timing requires preparatory action to protect the Combined Authority’s position.
Strategic Objectives:
The proposals within this report fit under the following strategic objective(s):
☒ Growth ☐ Jobs ☒ Resilience
☐ Connectivity ☐ Homes ☐ Performance The GSENZH supports public sector and community energy organisations to develop local energy projects to support growth, provide local energy resilience and public benefit.
1. Purpose
1.1This report sets out the current position on the future of the Greater South East Net Zero Hub and seeks the Board’s steer on the approach to planning for three possible scenarios: closure of the Hub on 31 March 2027; continuation with a reduced or different remit; or continuation at broadly the current resource level. 1.2 The Board is asked to note the operational, financial, legal and workforce implications of each scenario, including the need to protect the Combined Authority’s position should redundancy consultation and close-down planning required before a Ministerial decision is confirmed. 1.3 The purpose is to enable timely decisions on risk management, workforce planning and programme continuity while maintaining flexibility to respond to the expected Ministerial decision on the future of the English Hubs.
2. Proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Combined Authority Board at Cambridgeshire and Peterborough Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.