Combined Authority Board, Wednesday 23 September 2026 at 10.00am

Q1 26/27 Corporate Performance Report

Approved Committee 3 papers

AI summaryCambridgeshire and Peterborough Combined Authority Board noted Q1 2026/27 performance and approved changes to two Key Performance Indicators, removing one and splitting another into two separate measures.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThe Board noted performance information and progress on the Annual Business Plan, approved removal of the job vacancies KPI and split the job outcomes KPI into two separate measures.
MoneyNot stated
What happens nextQ2 2026/27 Corporate Performance ReportChanges to KPI 12 will apply from the Q2 report; KPI 10 removal applies from the following quarter.
Who it affectsThe Interim Outcomes FrameworkThe performance monitoring framework now contains 26 KPIs instead of 27, with KPI 12 replaced by two separate KPIs for lower and higher threshold job outcomes.

What was decided

The Board noted performance information relating to the 27 Key Performance Indicators in the Interim Outcomes Framework. Report P1

The Board approved the removal of KPI 10 (Number of job vacancies in the region) from the Interim Outcomes Framework. Report P1

The Board approved amending KPI 12 (Share of out of work participant starts to achieve a lower or higher threshold job outcome) into two separate KPIs. Report P1

Why

KPI 10 was removed because vacancy levels are not inherently positive or negative; a rise may indicate economic growth or skills shortages, and a fall may indicate weakness or successful filling of vacancies, with no clear interpretation of success.

KPI 12 is being split because reporting mechanisms have identified a need to measure and report separately on each level of job outcome, each with its own target.

Two KPIs were rated Red at Q1 2026/27: new homes started (23% below target) and new homes completed (15.4% below target), with both metrics outside direct CPCA control. Report P18

What happens next

The removal of KPI 10 will apply to the Q2 2026/27 Corporate Performance Report, with jobs data continuing via the State of the Region report.

The split KPI 12 will apply from the Q2 Corporate Performance Report, with separate targets for lower and higher threshold job outcomes.

Target setting work continues for KPIs still without targets, with 7 of 12 updated KPIs now having approved targets for 2026/27. Report 5.1

Options considered

  • Rejected: Keep KPI 10 (Number of job vacancies in the region) in the Interim Outcomes Framework. No target set and no consensus on preferred direction; vacancy levels have no clear interpretation of success.
  • Rejected: Keep KPI 12 as a single combined measure. Reporting mechanisms identified need to measure lower and higher threshold job outcomes separately.

Implications

  • Financial: This report is for monitoring purposes and has no immediate financial implications.
  • Legal: No direct legal implications from this performance report; individual projects will receive specific legal advice as required.
  • Equalities: No immediate equality, diversity and inclusion implications from this performance report.
  • Other: KPIs have implications for consideration by Thematic Committees and the Board, including linkages between skills and health.
  • Other: KPIs including the proportion of nature-rich land have environmental implications to be considered.

Who and where

  • Overview and Scrutiny Committee Report 1.1
  • Skills Committee
  • All local planning authorities in Cambridgeshire and Peterborough Report P18

Timeline

  • Q1 2026/27 (April to June 2026): Performance data reported for this quarter Report P15
  • Q2 2026/27: KPI 12 split applies; KPI 10 removal applies
  • 31 December 2029: Government target for completion of high-rise residential building remediation
  • 31 December 2031: Government target for completion of medium-rise residential building remediation

Plain English for the jargon

  • Interim Outcomes Framework (IOF): The Combined Authority's performance management framework containing Key Performance Indicators linked to the Corporate Plan 2025-2029
  • RAG rating: Red, Amber or Green status used to assess performance against targets, with Blue indicating results at least 5% better than target
  • Local Housing Need (LHN): Government's assessed target for the number of new homes to be delivered each year in a region, based on standard methodology
  • Annual Business Plan: Document setting out the most significant activities contributing to delivery of each Corporate Plan Strategic Objective
  • Connect to Work programme: Government programme supporting out of work participants to achieve job outcomes
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

It was resolved to : A Note performance information relating to the Combined Authority’s Key Performance Indicators in the Interim Outcomes Framework (IOF). B Note progress on delivery of the Annual Business Plan. C Approve the removal of KPI 10 (Number of job vacancies in the region) from the Interim Outcomes Framework. D Approve amending KPI 12 (Share of out of work participant starts to achieve a lower or higher threshold job outcome) into two separate KPIs for lower threshold and higher threshold job outcomes.
Word for word from the decision Cambridgeshire and Peterborough Combined Authority published for this meeting. Source: democracy.cambridgeshirepeterborough-ca.gov.uk

Follow this further

Built from Cambridgeshire and Peterborough Combined Authority's papers

What the report saysPro

Report to Combined Authority Board

Recommendations

A To scrutinise performance information relating to the Combined Authority’s Key Performance Indicators in the Interim Outcomes Framework (IOF). B To scrutinise progress on delivery of the Annual Business Plan. C To approve the removal of KPI 10 (Number of job vacancies in the region) from the Interim Outcomes Framework. D To approve amending KPI 12 (Share of out of work participant starts to achieve a lower or higher threshold job outcome) into two separate KPIs for lower threshold and higher threshold job outcomes.

Strategic Objectives:

The proposals within this report fit under the following strategic objective(s):

☒ Growth ☒ Jobs ☒ Resilience

☒ Connectivity ☒ Homes ☒ Performance The performance information presented in this report includes results for Corporate Key Performance Indicators (KPIs) at the end of Q1 2026/27 and is intended to strengthen scrutiny and accountability in line with expectations outlined in the English Devolution Accountability Framework (EDAF). These KPIs are linked to the Corporate Plan 2025-2029’s objectives, as set out in the IOF adopted in December 2025. The authority’s approach to Corporate Performance Reporting is set out in the Performance Management Framework 2025-2029 (PMF), which was also adopted in December 2025.

1. Purpose

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix: B ABP Report Q1 2627Appendix 295 KB Download
PDF
Q1 202627 Corporate KPIs DashboardAppendix A 1.6 MB Download
PDF
Q1 26/27 Corporate Performance ReportReport 226 KB DownloadRead as text

At this meeting

Whole meeting
2Minutes of the previous meetingApproved 5Public QuestionsDecided 7Forward PlanApproved 8Combined Authority Membership UpdateOn the agenda 9CPCA Meetings CalendarApproved 10Updates to the ConstitutionApproved 11Chief Executive Highlights ReportOn the agenda 12Rewiring the State - Opportunities for Cambridgeshire and PeterboroughNoted 13Process for Review and Refresh of the Annual Business Plan, Organisational Delivery Plan, and the Settings of the Medium-Term Financial Plan (2027/28 to 2030/31) – KD2026/063Approved 14Budget Update Report Q1 - KD2026/035Noted
15Q1 26/27 Corporate Performance ReportThis decision
16Corporate Risk ReportOn the agenda 17Future of Greater South-East Net Zero (GSENZ) HubNoted 18aBrownfield Housing Fund Programme - KD2026/049Approved 18bActive Travel Consolidated Settlement 2026-2030 (Business Case) - KD2026/059Approved 18cClosure of Subsidiary Cambridgeshire and Peterborough Business Growth Company Limited – KD2026/070Approved 18dBusiness Case Approvals - Officer DecisionsOn the agenda 19aEnergy GovernanceAgreed 19bSage Homes - KD2026/046Agreed 19cRegional Visitor Economy Branding and Narrative – KD2026/030Approved 20aAdult Skills Commissioning Strategy - KD2026/066Approved 21aDeveloper Funding Governance – KD2026/063Approved 21bBus Services Reimagined - Service Change Proposals – KD2026/064Approved 21cLocal Transport Delivery Plan - KD2026/026Approved 21dTiger on Demand Service Re-Procurement – KD2026/065Approved 21eBudget and Performance Report - Drawdown of Transport Capacity GrantApproved 22Update from Business BoardNoted 23Exclusion of the Press and PublicOn the agenda

Who was there

0 of 22 attended
PB
Paul Bristow Cambridgeshire and Peterborough Combined AuthorityChair, expected
KT
Councillor Katie Thornburrow Cambridge City CouncilCommittee Member, expected
LN
Councillor Lucy Nethsingha Cambridgeshire County CouncilCommittee Member, expected
AB
Councillor Anna Bailey East Cambridgeshire District CouncilCommittee Member, expected
CB
Councillor Chris Boden Fenland District CouncilCommittee Member, expected
SC
Councillor Sarah Conboy Huntingdonshire District CouncilCommittee Member, expected
SQ
Councillor Shabina Qayyum Peterborough City CouncilCommittee Member, expected
BM
Councillor Brian Milnes South Cambridgeshire District CouncilCommittee Member, expected
SG
Shaun Grady Business BoardCommittee Member, expected
DP
Darryl Preston Police and Crime CommissionerCo-Optee, expected
RP
Robin Porter Central East Integrated Care BoardCo-Optee, expected
CM
Councillor Christopher Morris Cambridgeshire and Peterborough Fire AuthorityCo-Optee, expected

All 22 on the meeting page

On this subject at Cambridgeshire and Peterborough Combined Authority

Search all
  1. Q1 26/27 Corporate Performance ReportThis decision
  2. Corporate Performance Report, Q1 2026/27Noted
  3. Q4 Corporate Performance ReportDecided
  4. Corporate Performance Report Q4 2025/26Noted
  5. Q3 Corporate Performance ReportDecided
  6. Corporate Performance ReportNoted

More from Cambridgeshire and Peterborough Combined Authority Combined Authority Board

All decisions
MeetingDecisionOutcome
23 Sep 2026 Minutes of the previous meetingThe minutes of the meeting held on 15 July 2026 were approved as an accurate record and signed by the Mayor. The acti... Approved Open
23 Sep 2026 Public QuestionsOne public question was received. The question is published . Decided Open
23 Sep 2026 Forward PlanIt was resolved to : A Approve the Forward Plan for September 2026 Approved Open
23 Sep 2026 CPCA Meetings CalendarIt was resolved to : A Approve the proposed amendments to the calendar of meetings for the 2026/27 Municipal Year B A... Approved Open
23 Sep 2026 Updates to the ConstitutionIt was resolved to : A Approve the changes to the Constitution as proposed in Sections 4 and 5 of the report and asso... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies