Shared HR/Payroll Business Case - Report to the East Kent (Joint Arrangements) Committee on 8 April 2009

Agreed Executive 4 papers

Executive agreed this item on Tuesday 21 April 2009. Below is the council's own wording, with the papers it was decided on.

Item326

Resolved

RESOLVED - (a) That with effect from 1 June 2009 Canterbury City Council enters into the joint administrative arrangements described in the Administrative Collaboration Agreement at Appendix 1 to the joint report of the Director of Corporate Services of the City Council and the Corporate Director, Organisational Performance, Shepway District Council to the meeting of the East Kent (Joint Arrangements) Committee on 8 April 2009 with one or more of Dover District Council, the District Council of Shepway and Thanet District Council and that, subject to the recommendation and resolution below, these arrangements be RECOMMENDED to Full Council (b) That Full Council be recommended to agree (in so far as the Administrative Collaboration Agreement relates to functions which are the functions of the Council) that the functions set out in the Agreement shall be discharged by the East Kent Joint Arrangements Committee subject to the terms, conditions and limitations contained in the Agreement with effect from 1 June 2009 and that the Chief Executive be given the power to approve any amendments to the Agreement to ensure the effectiveness of the arrangements. (c) That (in so far as the Administrative Collaboration Agreement relates to functions which are the functions of the Executive) the functions set out in the Agreement shall be discharged by the East Kent (Joint Arrangements) Committee subject to the terms, conditions and limitations contained in the Agreement with effect from 1 June 2009 and that the Chief Executive be given the power to approve any amendments to the Agreement to ensure the effectiveness of the arrangements.
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Executive

Special Executive – 21 April 2009 APPENDIX 1 (Contd)

Project Assumptions and financial protocols

Protocol / Assumptions / Issues

1 Pension Back funding

Staff are to be costed at current cost including a % for back funding. When staff transfer to a host employer, their share of the deficit will transfer with them. The back funding on the deficit will then be included in the trading account and will be part of the costs to be recharged to partners. However, the protocols also need to cope with closure of the project. If, staff transfer to SHREK, then the project folds, the host could be left with significant pension deficits. If there has been a revaluation in the meantime, then the deficits could be even greater on staff the host has employed, on behalf of others, for a short period.

It is proposed that pension deficits relating to staff remaining with the project at the time of closure are shared in, say, 1/20ths, (reflecting an average sort of career).

If the project folds the host will retains 1/20 * no of years the staff were hosted, and the original employer will bear the balance of the deficit - either through a lump sum payment to the host, or an annual payment. The deficits on staff recruited after the project started will be shared equally between the partners.

2 Closure / Exit from the shared service

If an authority chooses to leave the partnership, they will be responsible for meeting the costs, including redundancy / actuarial strain arising from redundancy / early retirement that this causes, up to a maximum of 25% of all staff (when 1 of the 4 leaves), 33% of staff if there are three authorities left etc.

The remaining authorities will determine which staff are selected for redundancy.

3 Minimising costs

All authorities will use best endeavours to minimise the costs of their payroll & HR teams where this will reduce any potential redundancy costs to the project. 4 Set up costs, one off premises costs etc –

These will be shared by the participating authorities and will not be refundable.

5 Charging for the service:

General • Charging will aim to provide a fair attribution of costs, but also to provide as much certainty as possible. • The budget for the coming year will be prepared by the Head of HR and presented to district s151s every autumn. It will include the costs of payroll based on an SLA between the EK JAC and KCC, and it will also include the basis for provision of the service to additional authorities. • The host authority will charge overheads (premises, ICT etc) to the payroll and HR team on the same unit basis as it charges to its other services. For payroll :- • Every October the Head of HR will agree with the districts an estimated no of payslips, based on: o Headcount o weekly paid staff o monthly paid staff o temporary / casual staff o vacancy levels • The annual charge will then be calculated based on KCC costs and the estimated total number of payslips.

• If the actual number of payslips, in total, and between districts, is not materially different, then the actual charge will be the previously agreed annual charge. • If the actual number of payslips for an authority is more than 10% above the estimated number, then the charge from KCC will be adjusted pro rata. If other authorities have less than 10% above the estimated number of payslips, but the aggregate charge by KCC will be at or above the estimated level, then their charges will be adjusted down pro rata.

For HR:- • Base cost of 25% of total costs, split equally as a "membership" cost • Remaining 75% of costs pro rata to employees in each authority • Additional work bought in on a day rate for consultants shared by those requesting the work. L&D

• Pro rata to employees in each authority

H&S

• Split equally.

Welfare

• Canterbury only cost, not included in the model.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
21 April 2009 (Special exec) Appx 1 contdReport 135 KB DownloadRead as text
PDF
21 April 2009 (special exec) Appx 1Report 169 KB Download
PDF
21 April 2009 (special exec) Appx 1 contd2Report 178 KB Download
PDF
Shared HR/Payroll Business Case: Report to the East Kent (Joint Arrangements) Committee on 8 April 2009Report 86 KB Download

At this meeting

Whole meeting
326Shared HR/Payroll Business Case - Report to the East Kent (Joint Arrangements) Committee on 8 April 2009This decision
327Short Topic Scrutiny Review into Beach HutsApproved 328Thanington Neighbourhood Resource Centre - Disposal of Public Open SpaceAgreed 329Marlowe Theatre change control proceduresApproved

On this subject at Canterbury

Search all
  1. Shared HR/Payroll Business Case - Report to the East Kent (Joint Arrangements) Committee on 8 April 2009This decision
  2. Shared Human Resources / Payroll Business CaseApproved
  3. Shared hr/payroll projectAgreed
  4. Human Resources and Payroll Shared Services Project for East KentAgreed

More from Canterbury Executive

All decisions
MeetingDecisionOutcome
6 May 2015 Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... Approved Open
23 Apr 2015 Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... Decided Open
23 Apr 2015 Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... Approved Open
23 Apr 2015 Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... Approved Open
23 Apr 2015 Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies