RESOLVED that a working group be established including all Members of the Board to allocate responsibility and resources to the Strategic Plan Implementation Plan.
Whitstable Harbour Board decided this item on Friday 22 January 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that a working group be established including all Members of the Board to allocate responsibility and resources to the Strategic Plan Implementation Plan.
Whitstable Harbour Work Plan January 14,2010
Ref Action Priority Responsible Due date Observations
STANDING ISSUES (ANNUAL)
S1 Review and update Harbour Board Constitution n/a HB Mar
S2 Review Port Marine Safety Code issues and compliance n/a HB Mar
S3 Review annual financial results n/a IMW Jun
S4 Prepare Annual Report and Annual Meeting n/a WG Sep
S5 Recruit new Harbour Board member(s) n/a MD Nov
S6 Review dredging requirements n/a HB Nov
S7 Submit five year revenue and capital expenditure summary n/a IMW Nov
S8 Submit and approve annual budget and five year forecast n/a IMW Jan
S9 Confirm adjustments to port charges n/a MW Jan Whitstable Harbour Work Plan January 14,2010
Ref Action Priority Responsible Due date Observations
DEVELOPMENT ISSUES
4.1(a) Determine marketing approach in conjunction with other 2 03/2010 parties within the Harbour and with other parties developing the profile of the town
4.1(a) Prepare structure and content of Harbour website for 2 01/2010 inclusion within CCC website or for separate but linked site
4.1(c) Confirm additional parking arrangements with Indoor Bowls 1 01/2010 Club
4.1(e) Review regeneration plans for Angling Club building 2
4.1(e) Determine nature and extent of upgrade to toilet facilities 1 MB 01/2010
4.1(e) Determine nature and extent of upgrade to waste disposal 1 01/2010 arrangements
4.1(e) Conclude on revised pedestrian safety arrangements 1 MB 01/2010
4.1(e) Introduce parking facilities for cyclists 1 01/2010
4.2(a) Review landscaping issues with Brett Aggregates 2
4.2D(a) Review environmental issues with Brett Aggregates 2 Whitstable Harbour Work Plan January 14,2010
Ref Action Priority Responsible Due date Observations
4.2D(b) Re-address the potential development of cold storage and 2 IMW 03/2010 ice-making equipment with the fishing community
4.2D(c) Confirm marketing approach to key decision makers for 2 contracted support services to wind-farm industry
4.2D(c) Liaise with Vestas to determine support service opportunities 2
4.2D(e) Support marketing activities for pleasure craft activities 2
4.2D(e) Construct suitable embarkation facilities for pleasure craft 2 To be done in conjunction with quay wall repair works
4.2B(a) Develop weather-resistant accommodation for retail trading 2 SQDWG 03/2010
4.2B(b) Develop accommodation for small business and business 2 SQDWG 03/2010 start-up units
4.2B(c) Develop accommodation for creative enterprises 2 SQDWG 03/2010
4.2B(d) Support and help co-ordinate the grant funding and 1 AR 01/2010 development of Dead Man's Corner
4.2B(d) Promote the proposed development of a children's play area 3 Awaiting proposals from Nick Dewhirst on land adjacent to the west Quay
4.2B(e) Provide land area for the construction of a barge museum. 1 SQDWG 01/2010 Awaiting confirmation from Dolphin Barge Museum Consideration to be given to expanding the role of the facility
4.3(c) Liaise with WRWUG to ensure the optimal use of land and 3 appropriate facilities are in place on the Long Beach Whitstable Harbour Work Plan January 14,2010
Ref Action Priority Responsible Due date Observations
4.3(d) Assess the development potential for additional beach huts 2 ongoing dependent on demand conditions and CCC's alternative supply and pricing arrangements
4.3(d) Establish timetable for painting of existing beach huts 3
OTHER ISSUES
1 Complete the rent review negotiations with Brett Aggregates 1 MB 01/2010
2 Conclude in water injection or conventional dredging 2 DWG 01/2010 arrangements
3 Conclude on lease arrangements with WOFC 1 MB 01/2010
4 Prepare licence application for Harbour (Licensing Act 2003) 1 MW 01/2010
5 Install water supply facilities on Long Beach 2 MW 03/2010
Notes Responsible
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
100122 HARBOUR WORK PLAN OUTLINEReport | 50 KB | DownloadRead as text |
PDF |
Whitstable Harbour Strategic Plan ImplementationReport | 83 KB | Download |
Follow Whitstable Harbour Board at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Jun 2026 | Election of a Chair for 2026/27RESOLVED that: Councillor Chris Cornell be Chair for 2026/2027. A recorded vote was taken as follows: For (7): Counci... | Decided | Open |
| 26 Jun 2026 | Annual Harbour Outturn Report 25/26RESOLVED that: The report was NOTED. A recorded vote was taken as follows: For: (8) Councillors Chris Cornell, Dixey,... | Noted | Open |
| 26 Jun 2026 | Membership of the South Quay Task and Finish GroupRESOLVED that: The membership of the South Quay Task and Finish Group remain unchanged. A recorded vote was taken as ... | Decided | Open |
| 26 Jun 2026 | Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc... | Decided | Open |
| 16 Jan 2026 | Exclusion of the press and publicRESOLVED by general assent that under Section 100(A)(4) of the Local Government Act 1972, the press and public be exc... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.