Herne Bay Memorial Park Working Group - Phase one

Approved Executive 1 paper

Executive approved this item on Thursday 4 February 2010. Below is the council's own wording, with the papers it was decided on.

Item205

Resolved

RESOLVED – a) That a consent order for Dering Road and tender for a catering concession in Memorial Park to start spring 2010 be sought. b) That the installation of public toilet near to playground and pavilion with an estimated capital cost of £50,000 subject to appropriate permissions take place. c) That the football pavilion be upgraded at a cost of £7,000. d) That the installation and replacement of 2 CCTV cameras with “dome CCTV cameras” take place in the park. e) That £20,000 be set aside to upgrade existing footpaths and install cycleway in the Park f) That £10,000 be set aside for a youth led project to improve youth provision in the park subject to attracting external funding and final approval. g) That £10,000 be set aside for sustainable horticultural initiatives in Memorial Park with Community Groups, Family Investment Homes and Britain in Bloom subject to external funding and final approval. h) That £25,000 be set aside for signage and work with the Friends Group subject to external funding and final approval. (Prior to the consideration of the item, Dick Eburne spoke as a local resident in support of the proposals and outlined some typographical errors in the document).
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Executive

Subject: Memorial Park Working Group – progress report

Director/Head of Service: Head of Environment and Street Scene

Decision Issues: These matters are within the authority of the Executive

Decision: Non Key Decision

Classification: Non-confidential

CCC Wards: Heron

Summary: Update the Executive on progress so far and seek approval for works to be carried out in 2010/11.

To Resolve: That the Executive approves the proposed works at memorial park:

• Seek a consent order for Derring Road and tender for a catering concession in Memorial Park to start spring 2010.

• Installation of public toilet near to playground and pavilion with an estimated capital cost of £50,000 subject to appropriate permissions.

• Upgrade of football pavilion at a cost of £7,000

• Installation of and replace 2 CCTV cameras with “dome CCTV cameras” in the park

• Set aside £20,000 to upgrade existing footpaths and install cycleway in the Park

• Set aside £10,000 for a youth led project to improve youth provision in the park subject to attracting external funding and final approval.

• Set aside £10,000 for sustainable horticultural initiatives in Memorial Park with Community Groups, Family Investment Homes and Britain in Bloom subject to external funding and final approval • Set aside £25,000 for signage and work with the Friends Group subject to external funding and final approval.

1 Next stage in process To implement the proposals.

1. Introduction

The Memorial Park Working Group met on November 2009 and considered a range of issues regarding the enhancement of memorial park and propose allocation of approved budget.

The action in 2009/10 is the upgrade of the playground at Memorial Park. This has been successfully tendered and following local consultation shaping the final design Kompan was selected. At the time of writing they are currently installing the playground with the aim of an opening in March 2010.

The rest of the report focuses on proposed work in 2010/11. The available budget is:

Memorial Park Capital Fund £275,000 Off site open space developer contributions – Herne bay £ 10,503

Total available in 2010/11 £285,503

2. Detail

The Memorial Park working group considered the following for 2010/11.

Year Funding Source Project Estimated Revenue Capital cost implications 2010 £275,000 CCC MPCF Install new £50,000 Increased public toilets cost £10,503 Off site dev Demolition £6,500 Revenue cont Tennis neutral Pavilion Upgrade £7,000 Revenue Football neutral pavilion Install new £60,000 Revenue CCTV neutral Upgrade £20,000 Revenue footpaths / neutral cycleway Community led £10,000 Revenue youth project neutral Community £10,000 Revenue horticultural neutral projects Interpretational £15,000 Revenue and directional neutral signage

Fees at 10% £18,850 Contingency £78,153 Total 285,503 £285,503 2011/12 £125,000 CCC MPCF Lighting £125,000 To be project developed

2 Total £125,000

Note - any contingency not spent would be carried forward into the next financial year.

1 Community Steering Group: the first meeting took place in May 2009. The partners who have agreed to join are: Friends of Memorial Park, Herne Bay Chamber of Commerce, Parkside Youth / Children’s Centre, Serco and Police. This group will report to the Executive Sub group.

2 Playground: The Council has successfully submitted a bid to Playbuilder for £50,000 to support the £100,000 the Council set aside for a new playground in the Memorial Park. The tendering process has led to Kompan being appointed contractor to deliver the project in early 2010 with an opening being planned for March 2010.

3 Asset management in Memorial Park

Existing central pavilion: The Council has been approached by two organisations seeking to redevelop the building. A meeting has taken place with one who is keen but seems to lack the capital resources to re-build a community facility or the revenue resources to sustain it.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Herne Bay Memorial Park Working Group: Phase oneReport 87 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. Herne Bay Memorial Park Working Group - Phase oneThis decision
  2. Application No. CA/24/01903/FUL North of Bullockstone Road / Canterbury Road Roundabout, Sth of Thanet Way, Herne BayAgreed
  3. Licensing Act 2003 - Review of the Premises Licence for Kaneera Express, 141 Station Road Herne Bay CT6 5QADecided
  4. Licensing Act 2003 - Review of the Premises Licence for Kaneera Express, 141 Station Road Herne Bay CT6 5QADecided
  5. Submission of a North Thanet (Herne Bay and coastal) Levelling Up Fund Round 3 applicationApproved
  6. Proposed lease of the unused Herne Bay BMX ParkDecided

More from Canterbury Executive

All decisions
MeetingDecisionOutcome
6 May 2015 Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... Approved Open
23 Apr 2015 Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... Decided Open
23 Apr 2015 Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... Approved Open
23 Apr 2015 Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... Approved Open
23 Apr 2015 Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies