Subject: Half Year monitoring of Capital Programme – Financial Year 2010/11
Director/Head of Service: Director of Finance/Head of Finance
Decision Issues: These matters are within the authority of the Executive
Decision type: Non-key
Classification: This report is open to the public
CCC Wards: All
Summary: This report advises Councillors on the position of the General Fund Capital Budget for 2010/11 and its financing, six months through the financial year.
To Resolve That the report be noted
SUPPORTING INFORMATION
1. Introduction
This year's Capital Programme was approved at Full Council on 18 February 2010. The net cost of schemes for 2010/11, after external funding contributions, is £15,637k.
Executive on 29 July 2010 gave authority to carry forward the unspent capital budget provisions for certain projects of £9,825k for General Schemes, of which £6,085k had a direct impact on the council's capital financing requirement - £4,107k from major capital receipts and £1,978k from borrowing.
Since the original capital programme approval, Management Team have carried out a mini capital star-chamber meeting in October with appropriate Heads of Service. This has resulted in changes particularly in the phasing of estimated costs and income, and these are reflected in the capital schedule which appends the capital budget report being presented to Executive on 18 November 2010 (and Overview & Scrutiny on 11 November 2010). This report takes account of the revised position, on the assumption that formal approval will be in place by the time the monitoring report is considered.
The position for the current year is now as follows:
TABLE 1 – GENERAL FUND SCHEMES (excluding Coast Protection & Flood Works) £ ‘ 000 NET ORIGINAL COST OF SCHEMES FOR 2010/11 9,692 Plus approved carry forwards (net) 6,085 Plus Star chamber adjustments 2,282 TOTAL REQUIRING FINANCING 18,059
FINANCING General Fund Capital Receipts (4777k + 4107k c/f-88k Star chamber 8,796 adjustments)
TOTAL FINANCING PROJECTED (excluding borrowing) 8,796
BALANCE = PRUDENTIAL BORROWING 9,263
In addition the coast protection and flood works approved programme is now estimated to cost £780k in the current year. Under the new funding arrangements all this expenditure should be funded by Defra grant.
2 Review of Schemes
As a result of the Star Chamber adjustments it is expected that the overall programme should be on target against the budget, unless some unforeseen circumstances arise later in the year. Where there is an anticipated variance against the budget brief details are given below. Gross budget means the total estimated spend on a scheme, whereas net budget is the estimated net cost to the council, after grants, contributions and receipts specific to a particular scheme are deducted.
Head of Culture and Enterprise
2.1Beaney Institute Development (AC6032): Budget £4122k gross, £1562k net.
The budget has been reviewed and adjusted to reflect a realistic timetable of project spend. Additional works have been necessary associated with the condition of the roof, and problems with the front elevation. However, at this stage the financing of the additional costs is subject to possible claims or draw down from the project contingency.
2.2Marlowe Theatre Development (AC3240): Budget £11,763k gross, £9,563k net.
The budget has been reviewed and adjusted to reflect a realistic timetable of project spend. The total cost is still set at the figure of £25.659 million approved by Council on 19 March 2009.
Some in-house staffing costs that are proper charges to the scheme will be met from the contingency.
2.3Marlowe Fundraising (AC3241): Budget ( incorporated in 2.2 above)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2 Dec 2010 Capital Monitoring Report App 1 18.11.10, 02/12/2010 ExecutiveAppendix | 81 KB | Download |
PDF |
Half Year monitoring of Capital Programme: Financial Year 2010/11Report | 126 KB | DownloadRead as text |
Follow Executive at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 May 2015 | Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... | Approved | Open |
| 23 Apr 2015 | Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... | Decided | Open |
| 23 Apr 2015 | Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... | Approved | Open |
| 23 Apr 2015 | Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... | Approved | Open |
| 23 Apr 2015 | Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.