Resolved
RESOLVED – That an additional £ 1,101 be added to the budget for Capital Grant applications and that the 8 highest scoring projects be funded in full this year.
Executive decided this item on Thursday 31 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That an additional £ 1,101 be added to the budget for Capital Grant applications and that the 8 highest scoring projects be funded in full this year.
Subject: Parish Councils Capital Grant scheme
Head of Service: Head of Community Development and Outdoor Leisure
Decision Issues: These matters are within the authority of the Executive
Decision type: Non-key
Classification: This report is open to the public
CCC Wards: Barham Downs, Blean Forest, Chartham & Stone Street, Harbledown, Herne and Broomfield, Little Stour, Marshside, North Nailbourne, Sturry South and Sturry North
Summary: This report details the parish council capital grant applications for 2011-2012 and sets out options for the allocation of the £39,207 budget.
Option 1 – Fund the 7 highest scoring projects in full, leaving a balance of £885 to be carried forward into next year’s parish capital programme budget Option 2 – Fund the 7 highest scoring projects in full, and offer to fund the 8th highest through a part payment of £885 this year and the balance of their bid (£1,101) paid out from next year’s budget when available on 1 April 2012. Option 3 – Fund the 7 highest scoring projects in full this year, and offer a part payment only up to the available budget of £885 to the 8th highest, in order to remain in budget this year and not affect next year’s. Option 4 – Fund the 7 highest applications this year, and transfer the balance of £885 to the council’s general fund for use elsewhere
To resolve: How the parish capital grant funding should be allocated for 2011-12
SUPPORTING INFORMATION
1. Introduction
An appraisal process as a way of scoring and prioritising parish council capital applications against the available budget has been in place since 2005-2006. This is a rolling programme with projects previously appraised and not yet funded rolled forward. 2. Budget
The available budget for 2011-12 is £39,207, made up of the £35,000 annual budget for 2011-12, plus last year’s surplus £4,207 brought forward, giving £39,207 for allocation this year.
3. Capital Grant Applications 2011-2012 There are 11 projects for consideration this year. As all projects submitted were funded last year there are no carried forward projects.
Total amount requested by the 11 capital applications received this year is £ 57,188. Self-appraisal forms have been scrutinised by the officer, and re-scored where necessary, based on CIFT criteria, using a consistent approach. The table below details parishes’ projects submitted and the shaded projects are those that fall within the available budget. Note re Barham village hall application The village needs a building for the Nailbourne Community Store and Post Office, which is currently based in a temporary portacabin on the village hall site and run by the local community. The village hall committee wish to extend the hall to include space suitable for the community shop/PO and to make the kitchen area and second hall more usable and welcoming. This is a large capital project with project costs in excess of £300,000. The capital grant application is for Phase 1 of the project – for design work in order to be able to go out to tender. The village hall committee is actively fund-raising to progress Phase 2, the actual build (or a scaled-down Phase 2 if necessary).
Score Parish Project Amount Running Sought Total £ £
83 Petham To resurface the car park at Petham village 2,006 2,006 hall
74 Upper Hardres To renovate the village hall male, female and 3,819 5,825 disabled toilet facilities together with associated plumbing and drainage works.
73 Chartham To provide various different items of fitness 3,389 9,214 equipment (Outdoor Gym) at the Memorial playing field close to the children’s existing play equipment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Overall CIFT Totals All Parishes 2011-12Appendix 1 | 60 KB | Download |
PDF |
Parish Councils Capital Grant SchemeReport | 88 KB | DownloadRead as text |
Follow Executive at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 May 2015 | Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... | Approved | Open |
| 23 Apr 2015 | Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... | Decided | Open |
| 23 Apr 2015 | Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... | Approved | Open |
| 23 Apr 2015 | Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... | Approved | Open |
| 23 Apr 2015 | Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.