Herne Bay Pier - Future short term use (2012) of the deck post demolition of the Pier Pavilion

Approved Executive 2 papers

Executive approved this item on Thursday 2 February 2012. Below is the council's own wording, with the papers it was decided on.

Item197

Resolved

RESOLVED - That option (iii) be approved and implemented, the estimated revenue expenditure of £6,000 be funded from the Executive contingency and that the additional capital expenditure of £50,000 be funded from the Pier Reserve. (Councillor A Cook did not participate in the discussion on this item or vote on the above resolution because he had declared a personal interest in the item).
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Executive

Herne Bay Pier Pavillion Estimated Savings Not accounted for in Existing Forecast One off Additional existing Description budget spend Annual saving saving budget budget

Maintainance on the building £25,000.00 £25,000.00 £25,000.00 £0.00 Insurance on the Pier including building £26,000.00 £18,000.00 £8,000.00 £8,000.00 Tide gauge (P Brookes) £5,000.00 £3,000.00 £2,000.00 £2,000.00 Gifford Report £19,000.00 £15,000.00 £4,000.00 £4,000.00 Structure charges (Tracy) Sub total £75,000.00 £61,000.00 £33,000.00 £6,000.00 £0.00 £14,000.00 Money allocated from Seafront improvement budget (Richard Griffiths) £13,000.00 £13,000.00 Total additional savings/income £27,000.00

Additonal costs Exisiting Forecast Budget Capital Costs Budget Spend Contingency variance Gates £6,500.00 £10,000.00 £3,500.00 Electrical reinstatement works (inc conduit to Tarmacadam slab) £0.00 £10,000.00 £10,000.00 Removal & making good of bund wall £5,000.00 £10,000.00 £5,000.00 Navigation Lights (P Brookes) £8,200.00 £10,300.00 £2,100.00 Total capital shortfall £19,700.00 £40,300.00 £20,600.00 Contingency £20,000.00 £20,000.00 Additional capital budget requested £40,600.00

Revenue costs Option 1 Option 2 Option 3 Option 4 Officer time £0.00 £6,000.00 £6,000.00 £0.00 Programming £0.00 £10,000.00 £0.00 £0.00 Total events budget required £0.00 £16,000.00 £6,000.00 £0.00

Notes: 1. A £20,000 capital contingency is also requested to cover any unforseen issues as the current budgets contains no contigency. 2. Staff time in options 2 and 4 is calculated on the hourly rate for the Senior Events Officer for 56 days from February to September. 3. Option 4 would incur charges to the Pier Trust as per the Events application charges schedule.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Executive 2 Feb 2012 Draft budget for pier platform 2012Report 40 KB DownloadRead as text
PDF
Herne Bay Pier: Future short term use (2012) of the deck post demolition of the Pier PavilionReport 98 KB Download

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. Herne Bay Pier - Future short term use (2012) of the deck post demolition of the Pier PavilionThis decision
  2. Application No. CA/24/01903/FUL North of Bullockstone Road / Canterbury Road Roundabout, Sth of Thanet Way, Herne BayAgreed
  3. Licensing Act 2003 - Review of the Premises Licence for Kaneera Express, 141 Station Road Herne Bay CT6 5QADecided
  4. Licensing Act 2003 - Review of the Premises Licence for Kaneera Express, 141 Station Road Herne Bay CT6 5QADecided
  5. Submission of a North Thanet (Herne Bay and coastal) Levelling Up Fund Round 3 applicationApproved
  6. Proposed lease of the unused Herne Bay BMX ParkDecided

More from Canterbury Executive

All decisions
MeetingDecisionOutcome
6 May 2015 Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... Approved Open
23 Apr 2015 Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... Decided Open
23 Apr 2015 Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... Approved Open
23 Apr 2015 Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... Approved Open
23 Apr 2015 Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies