Resolved
RESOLVED – That the report be noted.
Executive noted this item on Thursday 29 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report be noted.
EXECUTIVE
29 MARCH 2012
Subject: Nine month monitoring of Capital Programme – Financial Year 2011/12.
Head of Service: Head of Finance
Decision Issues: These matters are within the authority of the Executive
Decision type: Non-key
Classification: This report is open to the public.
CCC Ward(s): All
Summary: This report is open to the public.
To Resolve: That the report be noted
Next stage in process
SUPPORTING INFORMATION
1. Introduction
This year's Capital Programme was approved at Full Council on 17 February 2011. The net cost of schemes for 2011/12 after external funding contributions, is £5,462k.
Executive on 27 July 2011 gave authority to carry forward the unspent capital budget provisions for certain projects of £5,435k for General Schemes, of which £3,919k had a direct impact on the council's capital financing requirement from major capital receipts.
Since the original capital programme approval, Management Team has carried out a mini capital star chamber meeting in September with appropriate Heads of Service. This has resulted in changes, particularly in the phasing of estimated costs and income, and these were reflected in the capital schedule which formed part of the budget report presented to Executive Committee on 17 November 2011 (and Overview on 10 November 2011). This report takes account of the revised position.
The position for the current year is now as follows:
Table 1 – General Fund Schemes £'000 (excluding Coast Protection and Flood Works)
Net original cost of schemes for 2011/12 5,462 Plus approved carry forwards (net) 3,919 Plus star chamber adjustments -77 Total requiring financing 9,304 Financing General Fund Capital Receipts (1905k + 3919k c/f - £258k star 5.566 chamber adjustments) Internal borrowing 3,738 (pending capital receipts expected in 2013/14)
Total Financing Projected (excluding borrowing) 9,304
Balance = Prudential Borrowing 0
In addition the coast protection and flood works approved programme is now estimated to cost £686k in the current year. Under the new funding arrangements all this expenditure should be funded by Defra grant.
2. Review of Schemes
As a result of the star chamber adjustments it is expected that the overall programme should be more on target against the budget, unless some unforeseen circumstances arise later in the year. Where there is an anticipated variance against the budget, brief details are given below. Gross budget, means the total estimated spend on a scheme, whereas net budget is the estimated net cost to the council, after grants, contributions and receipts specific to a particular scheme are deducted.
Head of Culture and Enterprise
2.1Beaney Institute Development (AC6032): Budget £5549k gross, £-22k net.
The redevelopment and extension is progressing well. The budget has been reviewed and adjusted to reflect the latest timetable of project spend, with a contract completion date of 6 January 2012. Additional works have been necessary associated with the condition of the roof, and problems with the front elevation, and this has extended the contract period, but the budget has been increased to reflect the current position.
2.2Marlowe Theatre Development (AC3240): Budget 4662k gross, £3395k net.
The project is now complete, on time and within budget. There is now a one year period during which the contractor ISG Jackson is responsible for the rectification of build defects. As with any development of this size there will inevitably be some defects that need to be dealt with, but this should have no impact on the council as far as costs are concerned.
2.3Marlowe Fundraising (AC3241): Budget (incorporated in 2.2 above)
The fundraising target has been exceeded, but the agreed terms for some of the donations means that although the money has been pledged, some will not be released until after the current financial year. However, this is a relatively small sum, and should not impact on the overall financing requirement this year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Executive 29 Mar 2012 Capital Monitoring Report App 1Appendix | 71 KB | Download |
PDF |
Nine month monitoring of Capital Programme: Financial Year 2011/12Report | 116 KB | DownloadRead as text |
Follow Executive at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 May 2015 | Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... | Approved | Open |
| 23 Apr 2015 | Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... | Decided | Open |
| 23 Apr 2015 | Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... | Approved | Open |
| 23 Apr 2015 | Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... | Approved | Open |
| 23 Apr 2015 | Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.