Canterbury City Council
Executive, Thursday 17 January 2013 at 6.30pm

Herne Bay Gateway

Decided Executive 1 paper

Executive decided this item on Thursday 17 January 2013. Below is the council's own wording, with the papers it was decided on.

Item131

Resolved

RESOLVED - That a commitment be given, in principle, to participate in the Gateway project subject to a financial appraisal. Reasons for the decision 1. It would enable Members to commit or to withdraw from the project at a later date and gives the County Council some assurance about the City Council’s commitment to the project but does not incur any immediate capital or revenue expenditure. 2. This decision minimises the council’s financial risk but enables sufficient information to be gathered to enable the Executive to determine the matter before April 2013.This gives Kent County Council and local resident’s some reassurance about the council’s support for the project.
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Executive

Subject: Herne Bay Gateway

Director/Head of Service: Deputy Chief Executive

Decision Issues: These matters are within the authority of the Executive

Decision type: Non-key

Classification: This report is open to the public

CCC Ward(s): Heron

Summary: Kent County Council have agreed to progress the development of a Gateway at the Herne Bay library. Detailed planning to enable the next stage of decision and to commit the necessary expenditure by county council officers has commenced. Canterbury City Council has been asked to confirm its commitment to join the Gateway and to contribute £120,000 towards the capital cost of £1.23 million.

To Resolve: A commitment in principle to participate in the Gateway project subject to a financial appraisal.

Next stage in process Kent County Council advised of the Executive’s decision.

SUPPORTING INFORMATION

1. Introduction

Gateway is a joint initiative between the Kent County Council and the district councils across Kent. The aim of a Gateway is to provide comfort, convenience and customer service that reflects the needs of the particular community served. Services are delivered by a range of partners including the county and district councils, the voluntary sector and other public sector organisations. Officers have been working with the county to help identify a suitable location for a Gateway in Herne Bay. Several options have been considered including an extension of the council offices, a new build option as part of the Herne Bay Central Development Area and the conversion of Kent County Council’s library building. The feasibility studies have shown the library building option to be the most sustainable, affordable and viable.

2. Detail

Kent County Council has given its officers permission to plan the next stage in the Gateway development programme. This means that work to progress the refurbishment and remodelling of the library building, identification of partners and tenants, the assessment of running costs and other matters to be considered before a final decision to proceed will be made by Kent County Council in April 2013. The County Council has made capital provision of £1.23 million for project to go ahead, subject to additional capital resources of £120,000 from the Canterbury City Council. There is currently £27,000 allocated to the Gateway project in the council’s capital programme for 2013-14.

In considering whether to proceed with the project and to commit further capital resources the council will need to determine: • The cost of additional borrowing for the capital sum • One off costs of relocation of the divisional office activities • The future revenue costs of operating from KCC run premises • Any resources that could be released to the freeing up of other council and asset for sale or leasing • The social and community value of improved premises and services to Herne Bay residents • Any regeneration impact Little of this information is fully available at this time but an in principal decision to proceed with participation in the Gateway project is now required to reassure Kent County Council of the Council's support and commitment to a Gateway in Herne Bay.

3. Relevant Council Policy/Strategies/Budgetary Documents

Pledge 7 - We will support excellent and diverse cultural facilities and activities for our residents. The Gateway will enable and improved library and educational experience in Herne Bay

Pledge 8 – We will tackle disadvantage within our district. The Gateway would enable more services that meet local needs to be a available in one building for Herne Bay residents.

4. Consultation planned or undertaken

The council’s Corporate Plan was largely based on resident’s priorities.

Herne Bay Area Member Panel 15 January 2012

5. Options available with reasons for suitability

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Herne Bay GatewayReport 94 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. Herne Bay GatewayThis decision
  2. Application No. CA/24/01903/FUL North of Bullockstone Road / Canterbury Road Roundabout, Sth of Thanet Way, Herne BayAgreed
  3. Licensing Act 2003 - Review of the Premises Licence for Kaneera Express, 141 Station Road Herne Bay CT6 5QADecided
  4. Licensing Act 2003 - Review of the Premises Licence for Kaneera Express, 141 Station Road Herne Bay CT6 5QADecided
  5. Submission of a North Thanet (Herne Bay and coastal) Levelling Up Fund Round 3 applicationApproved
  6. Proposed lease of the unused Herne Bay BMX ParkDecided

More from Canterbury Executive

All decisions
MeetingDecisionOutcome
6 May 2015 Call-in for the Executive Decision at Minute No. E227 - Petition to Full Council concerning household projections figures and the Draft Local PlanRESOLVED - That the Council does not withdraw the local plan and progresses with the forthcoming public examination. ... Approved Open
23 Apr 2015 Matters referred to the Executive by either the Overview or the Scrutiny and Audit Committees for considerationRESOLVED accordingly. Reason for the decision The current number of audit days is sufficient for the delivery of the ... Decided Open
23 Apr 2015 Key Performance Indicators - Targets for 2015/16RESOLVED – That the proposed list of corporate key performance indicators and targets for 2015/16 are approved. Reaso... Approved Open
23 Apr 2015 Litter Project ReviewRESOLVED - That approval be given to the continuation of the project as an extended pilot until 31 March, 2016 during... Approved Open
23 Apr 2015 Additional and Selective LicensingRESOLVED – That it be recommend strongly to the next Council that a full student impact review be conducted as soon a... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies