Capital Outturn Report 2014-15 - General Fund and Housing Revenue Account
ApprovedCommittee2 papers
Policy Committee - Decomissioned 19/5/22 approved this item on Wednesday 15 July 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED - That the carry forward of unspent capital budget provisions for those projects identified, and to approve the realignment of the HRA capital budgets be noted. Reason for the decision The report is for information only. In order to complete these General Fund capital schemes, for which approval has already been given, but where expenditure on schemes has slipped, it is necessary for 2014/15 allocations to be carried forward to 2015/16. Many of these are now contractually committed but some expenditure will be incurred in 2015/16 rather than 2014/15.
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Policy Committee - Decomissioned 19/5/22
Subject: Capital Outturn Report 2014-15 - General Fund and Housing Revenue Account
Author: Assistant Director – Finance & Procurement
Decision Issues: These matters are within the authority of the Policy & Resources Committee.
CCC Wards: All
Classification: This report is open to the public
Summary: Council approval of the capital programme relates to two years. This report details the position against General Fund and Housing capital spending for the last financial year, and advises on schemes that have slipped or overspent.
To Resolve To note the carry forward of unspent capital budget provisions for those projects identified, and to approve the realignment of the HRA capital budgets.
Next stage in process Approval of the resolution and amendment to the 2015-16 capital budget
SUPPORTING INFORMATION
1. Introduction
The General Fund and Housing Capital Accounts are complete and is report identifies the capital outturn position for 2014-15.
2 Provisional outturn – General Fund
The table below is the summary position by service. 2014/15 2014/15 Net 2014/15Net Net 2014/15 Net Variance () = Service Area Budget Actuals Slippage saving Total Commissioned Services 1,689,929 171,889 1,115,382 (402,658) Total Deputy Chief Executive 361,612 241,612 120,000 0 Total Direct Services 300,830 67,943 229,729 (3,158) Total Planning and Regeneration 1,408,296 785,581 647,730 25,015 Total Resources Department 4,922,239 2,279,949 2,633,021 (9,270) Total Strategy and Democracy 269,489 269,489 0 0 Total Coast Protection 0 0 0 0 Total Capital Projects 8,952,395 3,816,463 4,745,861 (390,070)
The detailed outturn per scheme is shown in Appendix A.
The financial procedures, set out in the Council's constitution, provide that where capital carry forwards are required to cover slippage on the schemes to which the budget relates, the Budget Director and Director of Resources are authorised to apply the carry forward. The constitution also provides that these carry forwards are subsequently reported to the relevant committee. This report meets that requirement.
The total requested carry-forward for the General Fund is £4,745,861 net (after taking account of specific grants, e.g. Heritage Lottery Fund and Housing schemes funded by housing capital receipts, grants and loans).
There are some other schemes that show an overspend position at year end. This is to be expected within the context of a multi million pound capital programme. Where possible scheme savings within service areas have been set against these overspends to mitigate the cost of capital on the general revenue budget.
The final net position for General Fund (excluding Coast Protection) is a net underspend of £390,070 in a reduced borrowing requirement to fund capital expenditure.
Details of the main variations to the budget are as follows:
Commissioned Services
There were in year savings of £402,704 in New Waste Contract Containers. This is due to a contribution from KCC for the purchase of the containers that was not included within the initial budget estimate
A total budget slippage for Commissioned Services of £1,115,382 has been requested.
Deputy Chief Executive
A total budget slippage for Herne Bay Gateway project of £120,000 has been requested as the scheme has not yet started. Direct Services
A saving of £3,156 was made in CSU Vehicle. This is due to an underspend in a part exchange of a vehicle.
A total budget slippage for Direct Services of £229,729 has been requested.
Planning and Regeneration
There was an overspend of £5,670 relating to the Herne Bay Pier Redevelopment. This was due to a slight increase in project costs.
A final overspend outturn of £3,325 for Reculver Caravan/Camping Park was due to the project starting before the allocation of the budget in 2015/16’s Capital programme.
The Herne Bay Market move resulted in an overspend of £16,021. This was due to an overspend of the total costs of the move.
A total budget slippage for Planning and Regeneration of £647,730 has been requested
Resources Department
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.