Capital Outturn Report 2015-16 - General Fund and Housing Revenue Account
NotedCommittee2 papers
Policy Committee - Decomissioned 19/5/22 noted this item on Wednesday 13 July 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the carry forward of unspent capital budget provisions for those projects identified be noted, and that the realignment of the HRA capital budget be approved. Reason for the decision In order to complete these General Fund capital schemes, for which approval has already been given, but where expenditure on schemes has slipped, it is necessary for 2015/16 allocations to be carried forward to 2016/17. Many of these are now contractually committed but some expenditure will be incurred in 2016/17 rather than 2015/16. When making its decisions on this item a record of the voting was taken as follows: For the proposal Councillors Baldock, Bartley, A Cook, S Cook, Dixey, Doyle, Hirst, Samper, A Taylor, Todd, Walker, Waters and Williams (13) Against the proposal None Abstained from voting None
Word for word from the decision Canterbury published for this meeting.Source: democracy.canterbury.gov.uk
Report to Policy Committee - Decomissioned 19/5/22
POLICY & RESOURCE COMMITTEE 13 JULY 2016
Subject: Capital Outturn Report 2015-16 - General Fund and Housing Revenue Account
Author: Assistant Director – Finance & Procurement
Decision Issues: These matters are within the authority of the Policy & Resources Committee.
CCC Wards: All
Classification: This report is open to the public
Summary: Council approval of the capital programme relates to two years. This report details the position against General Fund and Housing capital spending for the last financial year, and advises on schemes that have slipped or overspent.
To Resolve To note the carry forward of unspent capital budget provisions for those projects identified, and to approve the realignment of the HRA capital budgets.
Next stage in process Approval of the resolution and amendment to the 2016-17 capital budget
SUPPORTING INFORMATION
1. Introduction
The General Fund and Housing Capital Accounts are complete and this report identifies the capital outturn position for 2015-16.
2 Provisional outturn – General Fund
The table below is the summary position by service. 2015/16 Net 2015/16 Net 2015/16 Net Net Variance Service Area Budget Actuals Slippage () = saving
Total Planning and Regeneration 1,611,730 770,617 836,078 (5,035) Total Strategy and Democracy 194,807 194,806 0 (0) Total Commissioned Services 4,974,259 422,929 4,600,148 48,818 Total Deputy Chief Executive 270,000 150,000 120,000 0 Total Direct Services 361,379 262,621 98,757 (1) Total Resources Department 3,477,960 3,110,825 141,629 (225,506) Total Coast Protection 0 0 0 0 Total Capital Projects 10,890,135 4,911,799 5,796,612 (181,724)
The detailed outturn per scheme is shown in Appendix A.
The financial procedures, set out in the Council's constitution, provide that where capital carry forwards are required to cover slippage on the schemes to which the budget relates, the Budget Director and Director of Resources are authorised to apply the carry forward. The constitution also provides that these carry forwards are subsequently reported to the relevant committee. This report meets that requirement.
The total requested carry-forward for the General Fund is £5,796,612 net (after taking account of specific grants, e.g. Heritage Lottery Fund and Housing schemes funded by housing capital receipts, grants and loans).
There are some other schemes that show an overspend position at year end. This is to be expected within the context of a multi million pound capital programme. Where possible scheme savings within service areas have been set against these overspends to mitigate the cost of capital on the general revenue budget.
The final net position for General Fund is a net underspend of £181,724.
Details of the main variations to the budget are as follows:
Planning and Regeneration
It has been agreed that a final overspend outturn of £6,101 for Quality Bus Partnership will be taken from the capital programme for 2016/17. This will therefore produce a negative slippage to the new financial year to cover the initial deficit in 2015/16.
The slippage of £39,000 for District Wide Conservation Grants has been requested due to the planned change to the use of these funds from individual owners to the public realm use.
A budget of £31,732 in Green Gap – New Accessways has been slipped to 2016/17 due to the project starting later than expected.
The funding for the Canterbury Football Hub is to be in line with the developer contributions that we hold for this scheme and so the budget has been amended to reflect that position. All other slippage for Planning and Regeneration is the result of each project starting at some point in 2015/16 and continuing into the new financial year.
A total budget slippage for Planning and Regeneration of £836,078 has been requested.
Commissioned Services
The two main capital projects within Commissioned Services are both delayed, resulting in the main slippage being for Amphenol Gym and Kingsmead Leisure Centre at £1,642,000 and £2,835,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy Committee - Decomissioned 19/5/22 at Canterbury and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.