Fire safety report

Decided Committee 1 paper

Council decided this item on Thursday 13 July 2017. Below is the council's own wording, with the papers it was decided on.

Item155

Resolved

RESOLVED accordingly. A record of the voting was taken as follows:- For the resolution Councillors A Baker, B Baker, N Baker, Baldock, Bartley, Butcher, Clark, A Cook, S Cook, Dixey, Eden-Green, Fisher, Fitter-Harding, Glover, Hirst, Howes, R Jones, MacCaul, Metcalfe, Samper, Sonnex, Spooner, I Stockley, J Stockley, A Taylor, H Taylor, D Thomas, I Thomas, R Thomas, Todd, Walker, Waters, Westgate, Williams and Wimble (35) Against the resolution None Abstained from voting Councillor Doyle (1)
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Council

Summary

This report advises councillors of the action that has been undertaken in light of the dreadful fire at Grenfell Tower in London. It outlines the steps taken to review, and where appropriate, improve fire safety in the council's residential tower blocks, the action taken to reassure residents of those blocks, planned activity and preparations, fire safety in the council's public buildings and gives an update on other fire safety issues in the district. It covers the latest emerging guidance and approach from national government. It also seeks approval for associated expenditure.

Recommendations

Councillors are asked to:

i) consider the report, and

ii) give authority to the Chief Executive to use the general fund or HRA working balances to fund additional works required to improve the fire safety of either general fund or HRA properties where that expenditure would fall outside the current budget framework.

1.0Introduction

This report has been prepared to advise and update full Council on the action being taken by the Council and East Kent Housing in connection with their fire safety responsibilities.

Whilst the legal obligations in relation to fire safety have been in existence for some time the dreadful event at Grenfell House has triggered a re-evaluation of those provisions. Arising from this the Council has adopted a proactive stance in both assessing risk and evaluating fire safety in relation to its residential and public buildings as well as the broader Council area as set out in this report. Furthermore it will continue to monitor and implement any relevant findings as they arise from the ongoing investigation into the causes of the Grenfell Tower fire.

At national government level the Department for Communities and Local Government (DCLG) is actively collecting information from councils, and has set up an independent inquiry which they anticipate will be wide-ranging, and will investigate how well - or badly - the whole system of social housing operates and the contribution that might make to incidents like the Grenfell fire. They also envisage conducting a thorough review of regulations - particularly Building Control - and Fire Safety methods. Their developing conclusions - supported by our council’s officers - are that the question of the type of cladding fixed to buildings is only part of the issue. The safety of tenants and building occupants depends very much on the whole safety ‘system’ of fire prevention materials and techniques, procedures and tests.

2.0Council tower blocks

The council owns three tower blocks that are managed and maintained on its behalf by East Kent Housing (EKH) all of which have had cladding works carried out during the last three years. EKH is the “Responsible Person” in law for fire safety responsibilities in the council’s housing stock. Of the three blocks, Windsor House is a sheltered housing scheme, Margaret Court is occupied by people over 55 and Elizabeth Court provides general needs housing. There is one leaseholder in Elizabeth Court; the residents in the other blocks are all secure tenants.

Address Number of Storeys Approximate flats number of occupiers

1-70 Windsor House, Whitstable 70 12 85

1-27 Elizabeth Court, Herne Bay 27 7 40

1-36 Margaret Court, Herne Bay 36 9 49

2.1Tower block insulation

All three tower blocks have External Wall Insulation. In addition, numbers 28-58 Elizabeth Court, Herne Bay are in blocks of three to five storeys.The works carried out were part of a government grant funded initiative to improve energy efficiency, sponsored by the then Department of Energy and Climate Change. The insulation works were completed by the contractor Hamilton's between October 2014 and June 2015. The council's building control service was employed at Elizabeth Court and the other two blocks were overseen by an external building control assessment company appointed by the contractor.

3.0Fire Safety Regulations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fire safety reportReport 120 KB DownloadRead as text

At this meeting

Whole meeting

More from Canterbury Council

All decisions
MeetingDecisionOutcome
16 Sep 2026 Community Governance Review: First round consultation resultsThat, following legal advice from King’s Counsel and noting the desire to preserve city status, the Lord Mayoralty an... Approved Open
16 Sep 2026 Changes to memberships of committees and boards and notification of changes to lead councillor rolesThe changes to memberships of committees and sub-committees, as set out on page 9 of the agenda, were noted. The elec... Noted Open
16 Sep 2026 Council - Thursday, 16 July 2026RESOLVED Record of voting For (34): Councillor Alan Baldock, Councillor Mike Bland, Councillor Keith Bothwell, Counci... Decided Open
16 Jul 2026 Motion: Hazara Community and Sanctuary SupportThat the Leader of Canterbury City Council, Alan Baldock, should write to Nesil Caliskan MP, Parliamentary Under-Secr... Decided Open
16 Jul 2026 Approval of the ConstitutionTo adopt the Constitution for the Council Year 2026/27.?? Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies