Extra item of urgent business - Demolition of buildings at Canterbury Riverside - Urgent Decision by the Chief Executive

Noted Committee 2 papers

Council noted this item on Thursday 13 July 2017. Below is the council's own wording, with the papers it was decided on.

Item166

Resolved

RESOLVED – That the Council note the decision of the Chief Executive. A record of the voting was taken as follows:- For the resolution Councillors A Baker, B Baker, N Baker, Baldock, Bartley, Clark, A Cook, S Cook Dixey, Eden-Green, Fisher, Fitter-Harding, Glover, Hirst, Howes, R Jones, MacCaul, Metcalfe, Samper, Sonnex, Spooner, I Stockley, J Stockley, A Taylor, H Taylor, D Thomas, I Thomas, R Thomas, Todd, Walker, Westgate, Williams and Wimble (33) Against the resolution None Abstained from voting Councillor Doyle (1)
Word for word from the decision Canterbury published for this meeting. Source: democracy.canterbury.gov.uk

Follow this further

Built from Canterbury's papers

What the report saysPro

Report to Council

Recommendations

To authorise the Chief Executive

1. To require Linkcity to proceed with the urgent demolition of the following properties on the Canterbury Riverside site - Coldharbour, 1 Sturry Road and the old Serco depot - and any other properties that may need similar action - at a cost not exceeding £600,000 - on the condition that Linkcity carry out a tendering exercise to our satisfaction and to which we have access. 2. To ask the Director of Resources to amend the budget and capital programme as necessary 3. To consider the legal and financial advice relating to procurement and amendment to the Development Agreement, and to take the appropriate action

As part of the development of Canterbury Riverside, the Development Agreement (DA) with our developer, Linkcity, deals with the demolition - by contractual agreement, by Linkcity - of a number of buildings on the site to be developed.

The DA envisages that the demolition will take place once planning permission has been granted for the development, and the site becomes unconditional and effectively under the control of Linkcity. That is unlikely to take place until early 2018. In the meantime, a number of the properties have now been emptied and are secured against occupation or damage.

However, the properties at Coldharbour, 1 Sturry Road and the old Serco depot at Kingsmead which are now empty, are attracting anti-social behaviour. Despite having security panels fitted in an attempt to prevent access all properties have been been broken into since sitting vacant and now pose a potential safety risk.

The ongoing security issues on the site are also costing the council money to manage and the Council is liable for the payment of council tax and business rates on the properties.

Issues on the site include: ● Evidence of drug use inside the buildings. ● On 25th May a fire was set on the old depot site. Police are currently investigating. ● CCC has already incurred legal costs for evicting squatters twice. ● There is a cost attached to having the security panels in place ● In order to gain access to some buildings brickwork has been removed by members of the public. Any damage which has the potential to affect the structural integrity of a building creates a significant health and safety risk.

Development Agreement (DA) with Linkcity Under the terms of the DA Linkcity are liable for all demolition costs but demolition is not due to take place until planning consent has been achieved on the site. CCC has asked Linkcity whether they would consider starting demolition works early in order to assist the council in managing the issues around anti-social behaviour on the site. While Linkcity are more than happy to facilitate this, their board will not sign off any significant spend ‘at risk’ in advance of receiving planning consent. We have therefore discussed the possibility of CCC funding the demolition works up front and Linkcity paying the council back once the development goes unconditional.

If this financial arrangement were to be agreed, the cost to the Council would be minimal and related to cash flow. The risk, of course, is that planning permission is not granted, or that some other factor prevents the site becoming unconditional. However, under those circumstances, the site, when re-tendered, is likely to be more valuable to the Council by the extent of the cost of the demolition, as that will already have been carried out.

Linkcity have already sought a range of quotes from local contractors in order to inform their cost appraisal on the site. Based on those figures the necessary works will cost between £400k-£500k which would include the removal of a number of high risk materials including asbestos and the fuel tanks which sit underground on the old depot site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Early demolition of property on Sturry Road CanterburyReport 64 KB DownloadRead as text
PDF
Extra item of urgent business: Demolition of buildings at Canterbury Riverside: Urgent Decision by the Chief ExecutiveDecisions 142 KB Download

At this meeting

Whole meeting

On this subject at Canterbury

Search all
  1. Extra item of urgent business - Demolition of buildings at Canterbury Riverside - Urgent Decision by the Chief ExecutiveThis decision
  2. Extra item of urgent business - Assistant Director Strategy and Democracy - Change of job titleDecided
  3. Extra item of urgent business - Changes in Committee Memberships and Council Representation on Active LiveApproved
  4. Extra item of urgent business - Business Rates Consultations by the Department for Communities and Local GovernmentDecided
  5. Extra item of urgent business to be dealt with in public - Review of support to External Organisations - outcomesApproved
  6. Extra item of urgent business - Gambling Act 2005 Policy StatementApproved

More from Canterbury Council

All decisions
MeetingDecisionOutcome
16 Sep 2026 Community Governance Review: First round consultation resultsThat, following legal advice from King’s Counsel and noting the desire to preserve city status, the Lord Mayoralty an... Approved Open
16 Sep 2026 Changes to memberships of committees and boards and notification of changes to lead councillor rolesThe changes to memberships of committees and sub-committees, as set out on page 9 of the agenda, were noted. The elec... Noted Open
16 Sep 2026 Council - Thursday, 16 July 2026RESOLVED Record of voting For (34): Councillor Alan Baldock, Councillor Mike Bland, Councillor Keith Bothwell, Counci... Decided Open
16 Jul 2026 Motion: Hazara Community and Sanctuary SupportThat the Leader of Canterbury City Council, Alan Baldock, should write to Nesil Caliskan MP, Parliamentary Under-Secr... Decided Open
16 Jul 2026 Approval of the ConstitutionTo adopt the Constitution for the Council Year 2026/27.?? Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies