CAPITAL PROGRAMME 2015-16 UPDATE To report the variances within the capital programme
RECOMMENDATIONS / KEY DECISIONS REQUIRED: That the capital programme update report is received.
REASONS:
To provide Executive Board with an update of the latest budgetary position for the 2015/16 capital programme, as at the 31st October 2015.
Relevant scrutiny committees to be consulted N/A
Exec Board Decision Required YES Council Decision Required NO
EXECUTIVE BOARD MEMBER PORTFOLIO HOLDER:- Cllr David Jenkins Directorate Name of Head of Service: Designation: Tel No. Owen Bowen Head of Financial Services 01267 224886 Report Author: E Mail Address: Owen Bowen [email removed] v.uk EXECUTIVE SUMMARY EXECUTIVE BOARD 4TH JANUARY 2016
CAPITAL PROGRAMME 2015/16 UPDATE Purpose: To report the variances within the capital programme. This report provides members with an update on the Capital programme spend against budget for 2015/16 as at the 31st October 2015.
MAIN VARIANCES
COMMUNITIES
Public Sector Housing Voids to achieve CHS +£300k to meet demands on major works.
Planned M&E +£500k Higher than expected level of boiler failures at properties which were previously deemed to be compliant under the CHS, extra upgrades on Void works, additional costs linked to the sheltered scheme fire alarm upgrade works to connect to the Tunstall system. Additional costs to upgrade the sheltered complex heating plant (this needs to include new controls as well as the boiler plant itself).
Internal Refurbishment -£1,988k Due to postponement of various sites plus various tenant declines.
External Rendering +£60k Additional remedial works to cavities.
External Insulation over Cavity -£125k Due to less properties being identified.
Housing Development Programme -£832k Part of overarching Affordable Housing Delivery Plan. Money to be carried forward to support substantive programme over next five years.
Private Sector Housing County Steelwork £63k Less interest than anticipated.
Social Care Learning Disabilities £-228k Options are being considered for the location of future learning disability provision as part of a review of council buildings.
Leisure Y Ffwrnes -£23k Retention to be paid in 2016/17.
Countryside Projects -£28k Due to monies being retained to match fund.
Carmarthen Museum -£250k Scheme led by 3rd party - Payment to be made in 2016/17. ENVIRONMENT No Major Variances
EDUCATION AND CHILDREN MEP External Funding -£1,947k – Re-profiling required of 21st Century Schools grant from Welsh Government.
Ysgol Ffwrnes +£29k due to retention to be paid early due to works completed ahead of schedule.
Ysgol Maes Y Gwendraeth £450k Re-profile required due to delays in 2014/15 works carried forward to 15/16.
Seaside CP School -£3,000k delay in approving outline business case by Welsh Government. The full business case has now been approved.
Cwm Tywi New Area School -£50k A number of options for the area are considered as part of the draft strategic review.
Ysgol Trimsaran -£663k Awaiting confirmation on statutory process on dual stream, flying start grant to be used in 2015/16.
Ysgol Parc y Tywyn +£900k Re-profile required due to significantly more design development than originally intended during the year. Additional funding used to progress scheme to detailed design and submit planning application with a number of corporate sites in the Burry Port area.
Band B Schemes +£54k Re-profile required due to design development commencing site selection exercises and initial design development on Band B projects.
MEP-Other Projects +£40k Re-profile required.
Completed Schemes +£42k Retentions held and paid on contractors on various schemes in order to ensure they are completed as per contract.
CORPORATE SERVICES St David’s Park -£400k due to delay in procuring works.
IT -£200k due Microsoft Enterprise Agreement, Budget allocated for payment that is due 1st April 2016.
CHIEF EXECUTIVE Regeneration
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME 2015-16 UPDATE.Report | 373 KB | DownloadRead as text |
PDF |
Report: CapitalReport | 19 KB | Download |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.