Resolved
RESOLVED that the capital programme update report be received and the virement detailed therein be approved.
Cabinet approved this item on Monday 21 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the capital programme update report be received and the virement detailed therein be approved.
EXECUTIVE BOARD 21ST MARCH 2016
CAPITAL PROGRAMME 2015-16 UPDATE To report the proposed virements and variances within the capital programme
RECOMMENDATIONS / KEY DECISIONS REQUIRED: That the capital programme update report is received and that the virements within the report are approved.
REASONS:
To provide Executive Board with an update of the latest budgetary position for the 2015/16 capital programme, as at the 31st December 2015.
Relevant scrutiny committees to be consulted N/A
Exec Board Decision Required YES Council Decision Required NO
EXECUTIVE BOARD MEMBER PORTFOLIO HOLDER:- Cllr David Jenkins Directorate: Corporate Services Designation: Tel No. Name of Head of Service: Interim Head of Financial Services 01267 224886 Owen Bowen E Mail Address: Report Author: [email removed] Owen Bowen v.uk EXECUTIVE SUMMARY EXECUTIVE BOARD 21ST MARCH 2016
CAPITAL PROGRAMME 2015/16 UPDATE Purpose: To report the variances within the capital programme. This report provides members with an update on the Capital programme spend against budget for 2015/16 as at the 31st December 2015.
MEMBER APPROVED VIREMENTS CORPORATE SERVICES Llandeilo Municipal Buildings £120k – relocation of library to the municipal buildings to be funded either by the capital receipt from the sale of the current building or income via letting.
MAIN VARIANCES COMMUNITIES Public Sector Housing Fuel Switch – Gas Infrastructure -£130k -Installation of mains gas pipeline delayed due poor weather conditions affecting programme or works.
Planned M&E +£644k Higher than expected level of boiler failures at properties which were previously deemed to be compliant under the CHS, extra upgrades on Void works, additional costs linked to the sheltered scheme fire alarm upgrade works to connect to the Tunstall system. Additional costs to upgrade the sheltered complex heating plant (this needs to include new controls as well as the boiler plant itself).
Internal Refurbishment -£1,988k Due to postponement of various sites plus various tenant declines.
Housing Minor Works -£149k Delay in external works due to poor weather conditions.
External Rendering +£98k Additional remedial works to cavities.
External Insulation over Cavity -£125k Due to fewer properties being identified.
Re-Roofing Works -£100k Delays due to adverse weather conditions
Adaptations for the Disabled -£200k Large scale adaption to be carried out in 16/17
Housing Development Programme -£638k Part of overarching Affordable Housing Delivery Plan. Money to be carried forward to support substantive programme over next five years.
Private Sector Housing Renewal Assistance -£299k Due to delay with partners
County Steelwork -£225k Less interest than anticipated. Social Care Learning Disabilities £-231k Options are being considered for the location of future learning disability provision as part of a review of council buildings.
Leisure Y Ffwrnes -£22k Retention to be paid in 2016/17.
Countryside Projects -£27k Due to monies being retained for match funding purposes.
Carmarthen Museum -£250k Scheme led by 3rd party - Payment to be made in 2016/17.
ENVIRONMENT Bridge Strengthening - £36k due to construction cost being lower than anticipated
EDUCATION AND CHILDREN Disabled Discrimination Acts - +£296k Higher demand for pupil led adaptations, legal requirement.
MEP External Funding -£1,947k – Re-profiling required of 21st Century Schools grant from Welsh Government.
Ysgol Ffwrnes +£29k due to retention to be paid early due to works completed ahead of schedule.
Ysgol Maes Y Gwendraeth +£455k Re-profile required due to delays in 2014/15 works carried forward to 15/16.
Seaside CP School -£1,954k delay in approving outline business case by Welsh Government. The full business case has now been approved.
Cwm Tywi New Area School -£50k A number of options for the area are considered as part of the draft strategic review.
Ysgol Trimsaran -£664k Awaiting confirmation on statutory process on dual stream, flying start grant to be used in 2015/16.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 19 KB | Download |
PDF |
CAPITAL PROGRAMME 2015-16 UPDATEReport | 351 KB | DownloadRead as text |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.