Resolved
RESOLVED that: 13.1 the capital programme update report be received; 13.2 the additional projects detailed in the report be approved.
Cabinet approved this item on Monday 22 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: 13.1 the capital programme update report be received; 13.2 the additional projects detailed in the report be approved.
EXECUTIVE BOARD
22ND MARCH 2021
CAPITAL PROGRAMME 2020/21 UPDATE Purpose: To report the latest projected outturn of the capital programme for the financial year.
Recommendations / key decisions required: That the capital programme update report is received, and the additional projects detailed in the report be approved.
Reasons: To provide an update of the latest budgetary position for the 2020/21 capital programme, as at the 31st December 2020.
Relevant scrutiny committee to be consulted NA Exec. Board Decision Required YES Council Decision Required NO
EXECUTIVE BOARD MEMBER PORTFOLIO HOLDER: Cllr David Jenkins Directorate: Corporate Designations: Tel: 01267 224886 Services Email addresses: Name of Head of Service: [email protected] Head of Financial Randal Hemingway Services Report Author: Randal Hemingway EXECUTIVE SUMMARY
EXECUTIVE BOARD 22ND MARCH 2021
CAPITAL PROGRAMME 2020/21 UPDATE
This report provides an update on expenditure on the Capital programme against the budgets for 2020/21 as at the 31st December 2020.
Budgets slipped forward to future years: The October capital monitoring reported a net variance from budget of -£63,153k. £38m of this variance has now been built into future years’ budgets as part of the 2021/22 to 2025/26 five- year capital programme budget setting exercise which was considered by Executive Board on 18th January 2021 and by Policy and Resources Scrutiny on 3 rd February 2021. Budgets have been amended to reflect this slippage to future years in the December 2020 monitoring presented in this report.
Additional Schemes to the Capital Programme to be noted and approved:
HRA: £4.02m ICF funding has been awarded by the regional joint health panel for the purchase and refurbishment of several properties for sheltered housing, adaptations and supported living projects. Funds will be applied this year and in the new year to deliver the projects.
Regeneration: £230k has been secured in Western Valleys Task Force funding towards the ongoing project at Glanaman Industrial Estate.
Leisure: £15k awarded from the Risk Management reserve towards works at Carmarthen Leisure Centre.
Education and Children: A grant of £157k for the purchase of play equipment and the purchase of a van has been awarded from the All Wales Play Opportunities Grant for a number of sites across the county.
Appendix A shows a forecasted net spend of £44,717k compared with a working net budget of £76,284k, giving a -£31,567k variance. The significant variance projected at this time continues to be in large part attributable to restrictions associated with the Covid-19 pandemic and follows an adjustment to the budgets to reflect £38m slipped to future years.
Appendix B details the main variances within each department.
DETAILED REPORT ATTACHED? YES IMPLICATIONS
I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report:
Signed: Randal Hemingway Head of Financial Services
Policy, Crime & Legal Finance ICT Risk Staffing Physical Disorder and Management Implications Assets Equalities Issues
NONE NONE YES NONE NONE NONE YES
3. Finance The capital programme shows an in-year forecasted variance of -£31,567k against the 2020/21 approved budget.
7. Physical Assets The capital programme will have an impact on the physical assets owned by the Authority .
CONSULTATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 17 KB | Download |
PDF |
Appendix BAppendix B | 88 KB | Download |
PDF |
CAPITAL PROGRAMME 2020/21 UPDATEReport | 391 KB | DownloadRead as text |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.