Resolved
RESOLVED that : 11.1 the capital programme update report 2021/22 be received; 11.2. the new projects as detailed within the report be noted and agreed.
Cabinet noted this item on Monday 17 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that : 11.1 the capital programme update report 2021/22 be received; 11.2. the new projects as detailed within the report be noted and agreed.
CABINET 17th JANUARY 2022 CAPITAL PROGRAMME 2021/22 UPDATE Purpose: To report the latest projected outturn of the capital programme for the financial year and to agree the reprofiling of the budget.
Recommendations / key decisions required: 1. That the capital programme update report is received. 2. That the new projects are noted and agreed.
Reasons: 1. To provide an update of the latest budgetary position for the 2021/22 capital programme, as at the 31st October 2021.
Relevant scrutiny committee to be consulted N/A
Cabinet Decision Required YES Council Decision Required NO
CABINET MEMBER PORTFOLIO HOLDER: Cllr. David Jenkins
Directorate: Corporate Designations: Tel: 01267 224886 Services Email addresses: Name of Head of Service: [email protected] Head of Financial Randal Hemingway Services Report Author: Randal Hemingway EXECUTIVE SUMMARY CABINET th 17 JANUARY 2022
CAPITAL PROGRAMME 2021/22 UPDATE The current capital programme is based on information available as at the end of October 2021. Appendix A shows a forecasted net spend of £74,790k compared with a working net budget of £105,168k, giving a -£30,378k variance. The variance projected at this time relates mainly to delays with regeneration projects.
The net budget includes the original H.R.A. and General Fund capital programmes approved by Council on 3rd March and slippage from 2020/21 and, amendments approved by Cabinet on 25th October 2021. Some of the budgets have also been amended to account for differences in actual grant allocations compared with the anticipated allocations at the time the programme was approved.
Appendix B details the main variances within each department.
New Projects to note and approve for the current year: Private Housing: Additional grant has been awarded to the ENABLE programme of £338k. taking the total amount of grant for this project to £307k in 2021/22 which is 100% funding by the grant.
Social Care: £375k has been awarded in Intermediate Care Fund (ICF) grant funding for various projects.
Regeneration: As part of Westminster Government’s Levelling Up programme across the United Kingdom the Carmarthen West and Pembrokeshire South bid was successful in attracting £15.86m grant funding for the Carmarthen Hub. The grant requires a match funding from the County Council of £3.748m. This funding will be identified as part of the five-year budget setting process, however, £544k match funding is required in 2021/22 for the initial stages of the project. It is proposed to fund this from underspends within the current year and slip the variance as negative slippage to future years at the end of year.
Environment: The Dinefwr bid for Levelling up was also successful and awarded £16.775m to deliver the Towy Valley Path. This bid requires £1.864m match funding from the County Council which will be identified as part of the five-year budget setting process. £563k match funding is required during the current year and it is proposed to fund this from underspends on other projects and slip the variance as negative slippage to future years. As part of the current five-year programme, in-house council funding was reduced against this project as it had historically not been supported by external funds, however, a commitment was given to restore that funding should external funding materialise. Supporting the match funding for this this project will deliver on that commitment.
Education and Children: £600k ICF grant has been awarded for the refurbishment of the residential accommodation at Rhydygors.
Slippage to future years of the five-year capital programme. Regeneration: £20.594m of expenditure on City Deal projects to be slipped forward to future years to correlate with the construction phase. Environment: £6.249m of expenditure on the fleet replacement programme. social welfare buses, refuse and highways lorries not being replaced in this financial year. The slippage will be built into future years of the five-year capital programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 17 KB | Download |
PDF |
Appendix BAppendix B | 89 KB | Download |
PDF |
CAPITAL PROGRAMME 2021/22 UPDATEReport | 350 KB | DownloadRead as text |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.