Resolved
RESOLVED that : 7.1 the capital programme update report 2022/23 be received. 7.2 the new projects as detailed within the report be noted and agreed.
Cabinet noted this item on Monday 27 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that : 7.1 the capital programme update report 2022/23 be received. 7.2 the new projects as detailed within the report be noted and agreed.
CABINET 27th MARCH 2023 CAPITAL PROGRAMME 2022/23 UPDATE Purpose: To report the latest projected outturn of the capital programme for the financial year and to agree the reprofiling of the budget.
Recommendations / key decisions required: 1. That the capital programme update report is received. 2. That the new projects are noted and agreed.
Reasons: 1. To provide an update of the latest budgetary position for the 2022/23 capital programme, as at the 31st December 2022.
Cabinet Decision Required YES
Council Decision Required NO
CABINET MEMBER PORTFOLIO HOLDER: Cllr. Alun Lenny (Resources)
Directorate: Designations: Tel: 01267 224886 Corporate Services
Name of Head of Service: Head of Financial Email addresses: Randal Hemingway Services [email protected]
Report Author: Randal Hemingway EXECUTIVE SUMMARY
CAPITAL PROGRAMME 2022/23 UPDATE The current capital programme is based on information available as at the end of December 2022. Part of the General Fund budget (£56,878k net) has been slipped to future years and has been incorporated into the new Capital Programme 2023-2028. This brings the working budget more in-line with the projected outturn for the year. HRA budgets remain unchanged. Appendix A therefore shows the position after this slippage has been stripped out of the current year’s budget. It shows a forecasted net spend of £56,590k compared with a working net budget of £92,515k, giving a -£35,925k variance (£15,567k General Fund and £20,358k HRA).
Some of the budgets have also been amended to account for differences in actual grant allocations compared with the anticipated allocations at the time the programme was approved, and new grant awards received during the year to date.
Appendix B details the main variances within each department.
New Projects and virements to note and approve for the current year: A slippage Virement from 2022-23 to future years of the new capital programme: Gross £119,883k less External Funding £63,005k = £56,878 Net. Appendix C set out the individual detail. This slippage is incorporated into the new five-year capital programme approved by County Council on 1st March 2023. Leisure: A new project for the Upgrade of Electrical Infrastructure at Pembrey County Park introduced to the programme which will be funded by direct revenue funding. £106k. Regeneration: The residual budget of £380k relating to the purchase of the Grillo Site in Burry Port has been withdrawn from the programme because the purchase amount was lower than expected.
DETAILED REPORT ATTACHED? YES IMPLICATIONS
I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report:
Signed: Randal Hemingway Head of Financial Services
Policy, Crime & Legal Finance ICT Risk Staffing Physical Disorder and Management Implications Assets Equalities Issues
NONE NONE YES NONE NONE NONE YES
3. Finance The capital programme shows an in-year forecasted variance of -£35,925k against the 2022/23 approved budget as at 31st December 2022.
7. Physical Assets The capital programme will an impact on the physical assets owned by the Authority. CONSULTATIONS
I confirm that the appropriate consultations have taken in place and the outcomes are as detailed below
Signed: Randal Hemingway Head of Financial Services
(Please specify the outcomes of consultations undertaken where they arise against the following headings) 1. Scrutiny Committee request for pre-determination N/A If yes include the following information: Scrutiny Committee Date the report was considered: Scrutiny Committee Outcome/Recommendations:
2.Local Member(s) N/A 3.Community / Town Council N/A 4.Relevant Partners N/A 5.Staff Side Representatives and other Organisations N/A
CABINET MEMBER PORTFOLIO Include any observations here HOLDER(S) AWARE/CONSULTED NO
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
to CAppendix A | 108 KB | Download |
PDF |
CAPITAL PROGRAMME 2022/23 UPDATEReport | 100 KB | DownloadRead as text |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.