Resolved
6.1 that the Capital Programme update report be received; 6.2 that the new projects be noted and agreed, to be funded from current year capital charges.
Cabinet noted this item on Monday 31 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
6.1 that the Capital Programme update report be received; 6.2 that the new projects be noted and agreed, to be funded from current year capital charges.
CABINET 31 MARCH 2025
CAPITAL PROGRAMME 2024/25 UPDATE
Purpose: To report the latest projected outturn of the capital programme for the financial year.
Recommendations / key decisions required: 1. That the capital programme update report is received. 2. That the new projects are noted and agreed.
Reasons: To provide an update of the latest budgetary position for the 2024/25 capital programme, as at the 31st December 2024.
Cabinet Decision Required YES Council Decision Required NO
CABINET MEMBER PORTFOLIO HOLDER: Cllr. Alun Lenny (Resources)
Directorate: Designations: Tel: 01267 224886 Name of Head of Service: Head of Financial Email addresses: Randal Hemingway Services [email protected]
Report Author: Randal Hemingway EXECUTIVE SUMMARY
CABINET 31 MARCH 2025
CAPITAL PROGRAMME 2024/25 UPDATE The current capital programme is based on information available as at the end of December 2024. Appendix A shows a forecasted net spend of £96,088k compared with a working net budget of £131,145k, giving a -£35,057k variance.
The net budget includes the original H.R.A. and General Fund capital programmes approved by Full Council, and slippage from 2023/24. Some of the budgets have been amended to account for differences in actual grant allocations compared with the anticipated allocations at the time the programme was approved, new grant awards received during the year and virements approved. The projected outturn for the year is £186m gross which includes £48m on Canolfan, Zone1 of the Pentre Awel development, £7m on the Towy Valley Path, £17m on the Carmarthen Hwb and £13m on projects supported by the Shared Prosperity Fund countywide.
Appendix B details the main variances within each department.
New Projects and virements to note and approve for the current year:
Communities: Private Housing Acceleration of £900k from the 2025/26 budget against the Market Street North development.
Additional strategic land purchases to be funded from slippages and underspends in the annual budget.
Leisure: A new award of £61.5k funding from the Welsh Government’s Collections Management Capital Improvement Programme for Storage Improvements at Carmarthenshire Museum at Abergwili.
Place and Infrastructure: An award of £172.8m from The Woodland Investment Grant (TWIG) for woodland restoration and improvements to accessibility at Pentremawr and Bynea.
Economic Development: The budgets for the Shared Prosperity Fund capital projects have been uploaded. Previously only the projected outturns and income were reported. £12.2m
Education, Children and Family: Additional government Sustainable Communities for Learning grant award as a contribution towards additional costs at Ysgol Y Castell - £609k. Additional Funding for Community Focused Schools Grant for £1,472k for Glan-y-mor 3G pitch.
DETAILED REPORT ATTACHED? YES IMPLICATIONS
I confirm that other than those implications which have been agreed with the appropriate Directors / Heads of Service and are referred to in detail below, there are no other implications associated with this report:
Signed: Randal Hemingway Head of Financial Services
Policy, Legal Finance ICT Risk Staffing Physical Biodiversity Crime & Management Implications Assets & Climate Disorder Issues Change and Equalities
NONE NONE YES NONE NONE NONE YES YES
3. Finance The capital programme shows an in-year forecasted variance of -£35,057k against the 2024/25 approved budget as at 31st December 2024.
7. Physical Assets The capital programme will have an impact on the physical assets owned by the Authority.
8. Biodiversity and Climate Change Some schemes within the Capital Programme relate to decarbonisation measures to help reduce our carbon footprint. CONSULTATIONS
I confirm that the appropriate consultations have taken in place and the outcomes are as detailed below:
Signed: Randal Hemingway Head of Financial Services
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
& BAppendix A | 120 KB | Download |
PDF |
CAPITAL PROGRAMME 2024/25 UPDATEReport | 100 KB | DownloadRead as text |
Follow Cabinet at Carmarthenshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | To sign as a correct record the minutes of the meeting of the cabinet held on the 7th september 2026RESOLVED that the minutes of the meeting of the Cabinet held on the 7 th September 2026 be signed as a correct record. | Decided | Open |
| 21 Sep 2026 | Corporate safeguarding annual report 2025/26RESOLVED that the Annual Report be received. | Decided | Open |
| 21 Sep 2026 | Revision of the corporate safeguarding policyRESOLVED that the revised Corporate Safeguarding Policy be approved. | Approved | Open |
| 21 Sep 2026 | Carmarthenshire waste and recycling service policyRESOLVED that the revised Waste and Recycling Services Policy be approved. | Approved | Open |
| 21 Sep 2026 | Council’s revenue budget monitoring reportRESOLVED that the Budget Monitoring report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.