RESOLVED that 1. The contents of the report including the key projected variances to the revised 2010/11 budget and the projected total budget saving of £74,300 be noted. 2. Cabinet’s intention to recommend to Council, as part of the 2010/11 outturn report to Council on the 27 June 2011, that part of the projected budget saving be used to fund an interim solution relating to the Bath Road toilets be noted. 3. The use of £17,000 of the net underspend on new green waste schemes to fund the bringing forward of the full rollout of plastic bottles collection across the borough in 2011/12 be approved under the financial rules 4G, part 8.11.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 19 April 2011 Budget Monitoring Report 2010/11 – position as at February 2011
Accountable member Councillor John Webster, Cabinet Member for Finance and Community Development
Accountable officer Paul Jones, Head of Financial Services
Accountable scrutiny All committee
Ward(s) affected All
Key Decision No
Executive summary To update Members on the council’s current financial position for 2010/11 based on the monitoring exercise at the end of February 2011. The report covers the council’s revenue, capital, treasury management and the housing revenue account. The report identifies any known variations to the 2010/11 revised budget and a position statement on major schemes.
Recommendations 1. Note the contents of this report including the key projected variances to the revised 2010/11 budget and the projected total budget saving of £74,300.
2. Note the Cabinet’s intention to recommend to Council, as part of the 2010/11 outturn report to Council on 27th June 2011, that part of this projected budget saving be used to fund an interim solution relating to the Bath Road toilets (see paragraph 2.71).
3. Note the Cabinet’s approval, under financial rules 4G, part 8.11, to use the net underspend on new green waste schemes to fund the full rollout of plastic bottles collection across the borough in 2011/12 (estimated cost £17,000) (see paragraphs 2.55 and 2.56).
Financial implications As detailed throughout this report.
February budget monitoring report 19-4-2011 Page 1 of 21 Last updated 08 April 2011 HR implications Managers and HR Advisors have worked together to ensure vacancies are (including learning and managed effectively. The Executive Board has considered requests for organisational recruitment based on individual business cases. Assessments were made development) to see if any vacancies could be turned into permanent establishment savings.
Corporate and Key elements of the budget are aimed at delivering the corporate community plan objectives within the Corporate Business Plan. Implications
Environmental and None. climate change implications
February budget monitoring report 19-4-2011 Page 2 of 21 Last updated 08 April 2011 1. Background
1.1This report provides the last monitoring position statement for the financial year 2010/11. The purpose of this report is to notify members of the anticipated outturn position for 2010/11 including any known requests for budgets to be carried forward into 2011/12.
1.2The budget monitoring report to the end of August 2010 projected an overspend for the year of £801,700. As a direct result of that projection, the Senior Leadership Team (SLT) (in consultation with Cabinet) instigated an immediate recruitment freeze and a rigorous approach has now been adopted for future approval for any recruitment requests. In addition, officers have been instructed to reduce spend on supplies and services to essentials for the remainder of the financial year.
1.3These measures enabled the council to address the potential in year budget deficit and deliver a revised balanced budget which does not require a contribution from general balances. It is pleasing to note that the anticipated outturn position will deliver a saving of £74,300 against this revised budget.
1.4A number of savings are the result of delays or slippage in carrying out particular tasks which are still necessary and will need to be completed in the 2011/12 financial year. Where this applies, requests for carry forwards are noted in this report.
2. Net revenue position
2.1The table below summarises the net impact of the variances identified on the overall 2010/11 revised budget position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.