AI summaryCheltenham Cabinet notes Q2 budget monitoring showing a forecast £564,000 overspend on the General Fund, with reserves projected to fall below the Section 151 Officer's optimum level by March 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNo separate decision; report contents and projected variances noted
MoneyForecast £564,000 overspendGeneral balance forecast to fall to £1.283m vs optimum £1.764m
What happens nextRevised budget to December CabinetFull savings reset required for unachieved £542k
Who it affectsGeneral Fund services, HRA, capital programmePlanning, bereavement, waste, housing, property
What was decided
Cabinet noted the contents of the quarterly budget monitoring report covering variances against the general fund and Housing Revenue Account budgets approved on 21 February 2025. Report P9
Cabinet noted the actions being taken to reduce overspends by the end of the financial year. Report P9, 1.3
Why
Monitoring at 30 November 2025 shows a £564,000 forecast overspend on the General Fund, driven by £710,000 of combined pressure from reduced recycling material sales income and lower cremation income, against a £200,000 contingency. Report P5, P6, 3.1
Of the £1.130m 2025/26 savings target, only £588,000 is forecast to be delivered on track, with £542,000 at risk and needing a full reset. Report 5.1, 5.3, P72
The Housing Revenue Account is forecast to come in on budget with an £82,500 planned contribution to reserves, reaching approximately £686,000 by 31 March 2026. Report P7, P83, 7.1
What happens next
A revised budget will be presented to December Cabinet alongside the draft 2026/27 budget proposal, and the Budget Scrutiny Working Group will meet in December to discuss the position. Report 11.1, P104
A full reset of the unachieved £542,000 of savings is required, and the 2026/27 budget will need to include additional provision to restore general balances to the recommended level. Report 5.3, P6
A detailed review of capital financing is under way, with a full update due with the February 2026 budget; further CIL and Section 106 allocations will be reported separately. Report 6.3, 8.1, 8.4
The money
£560,803 Planned contribution to general balances by 31 March 2026 Report P3, 9.2
£1.764m Optimum general balance assessed by Section 151 Officer Report P5, 9.2
£564,000 Forecast net General Fund overspend for 2025/26 Report P5, 3.1, 9.2
£1.283m Forecast general balance at 31 March 2026 Report 9.2
£710,000 Combined pressure from reduced recycling and cremation income Report P6
£200,000 Contingency held in 2025/26 budget for such risks Report P6
£1.130m 2025/26 base budget savings target Report 2.1, 5.1
£588,000 Savings forecast on track at end of November 2025 Report 5.2, P72
£542,000 Savings forecast as at risk requiring reset Report 3.1, 5.3, P72
£603,500 HRA reserve balance at end of 2024/25 Report P83
£82,500 Planned 2025/26 contribution to HRA reserve Report P7, P83
£686,000 Forecast HRA reserve balance at 31 March 2026 Report P7, P83
£41.420m Approved 2025/26 capital programme including 2024/25 carry forwards Report 6.1
£500,000 Forecast staffing underspend on General Fund Report 4.1, P25
£340,000 Forecast overspend on bereavement services Report 4.3, P27
Chosen: Note the report and current monitoring position (as decided). Cabinet recommendation was to note the position and the actions to reduce overspends by year-end. Report P9
Implications
Financial: Forecast £564,000 overspend will reduce general balances to £1.283m, below the £1.764m optimum, requiring additional reserves contribution in the 2026/27 budget. Report P5, P6, 9.2
Financial: HRA position is stabilising but faces resource challenges re-letting voids and delivering fire safety compliance within the Housing Improvement Plan. Report P7
Financial: Capital programme of £41.420m is significant over the next three years, with timing of capital receipts described as crucial to delivery. Report 6.1, 6.3
Equalities: Housing benefits overspend of £310,000 reflects a higher share of supported accommodation claims that do not qualify for full subsidy, creating pressure on other services. Report 4.9, P58
Climate: Capital investment and the countywide Climate Co-ordinator role support carbon reduction, but further revenue investment is needed to maintain progress against the Climate Emergency Action Plan. Report 1.2, P16
Risk: Risk register flags ongoing risks on long-term budget gap, capital prioritisation, low general balances, and changes to business rate retention funding. Report P113, P114, P115, P116, P117, P119
Legal: Officers confirm no legal implications arise from the recommendation. Report 1.1, P14
Who and where
Council tax payers in Cheltenham, as general balances fall below the recommended level Report P5, 9.2
Planning applicants, as planning application income is £315,000 below budget Report 4.2, P26
Bereaved families using cremation services, with service income down 10% on the prior year Report 4.3, P27
Waste and recycling service users, given reduced kerbside collections affecting material sales Report 4.4, P28
Council housing tenants, with HRA voids and fire safety compliance under pressure Report P7
Residents in supported accommodation not provided by a Registered Provider, contributing to the housing benefits pressure Report 4.9, P58
Council staff, with vacancies held across the organisation following housing services transfer on 1 July 2024 Report 4.1
Timeline
21 February 2025: Council approved General Fund and HRA 2025/26 revenue and capital budgets including £1.130m savings target Report 2.1, 6.1
30 November 2025: Cut-off date for the monitoring position reported to Cabinet Report P2, 2.2
December 2025: Revised budget to be presented to Cabinet with 2026/27 draft; Budget Scrutiny Working Group to meet Report 11.1, P104
16 December 2025: Cabinet meeting at which the report was noted Report P1
February 2026: Full update on capital programme financing due with 2026/27 budget; further HRA update also due Report 6.3, P82
31 March 2026: Forecast year-end; general balance projected at £1.283m and HRA reserve at approximately £686,000 Report P7, 9.2, P83
Plain English for the jargon
General Fund: The council's main revenue account for non-housing services, funded by council tax, business rates and government grants.
Housing Revenue Account (HRA): A ring-fenced account for income and spending on council housing, kept separate from the General Fund.
Section 151 Officer: The statutory chief finance officer responsible for the proper administration of the council's financial affairs.
Section 25 report: An assessment by the Section 151 Officer on the robustness of budget estimates and adequacy of reserves.
Community Infrastructure Levy (CIL): A charge developers pay to fund local infrastructure, with strategic and neighbourhood elements.
Section 106: Planning obligations under which developers contribute to infrastructure or affordable housing.
EPR grant: Extended Producer Responsibility funding paid to local authorities to meet recycling and waste management obligations.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
RESOLVED THAT: - the contents of the report, including the key projected variances to the general fund and Housing Revenue Account (“HRA”) 2025/26 revenue and capital budgets approved by Council on 21 February 2025, and the actions to ensure overspends are reduced as far as possible by the end of the financial year, are noted.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
This report provides the monitoring position for the 2025/26 financial year against the budget approved by Council on 21 February 2025. Its purpose is to inform Members of any significant variations to the approved budget and highlight key financial issues.
Regular budget monitoring is undertaken in collaboration with Directors and cost centre managers, with updates shared with the Lead Member for Finance and Assets and Cabinet. The primary objective of this process is to identify major variations from the approved budget. Any revenue budget variations exceeding £50,000 as at 30 November 2025 are detailed within this report.
The 2025/26 General Fund budget anticipated a contribution of £560,803 to general balances by 31 March 2026, based on the Section 25 report prepared by the Section 151 Officer, which
Page 1 of 14 Report for Cabinet, 16 December 2025
assessed the required level of general balances at £1.764m. Current monitoring indicates an estimated overspend of £564,000, reducing the forecast general balance to £1.28m by year- end below the optimum level.
This shortfall reflects several risks identified in the Section 25 assessment materialising. In particular, reduced income from recycling material sales and cremation services has created a combined pressure of £710,000. While the 2025/26 budget included a contingency of £200,000 to mitigate such risks, this will reduce the planned contribution to general balances. Consequently, the 2026/27 budget will need to include provision for an additional contribution to restore reserves to the recommended level.
The Housing Revenue Account (HRA) position has stabilised following the overspend in 2024/25. Known cost pressures remain, driven by resource challenges in re-letting void properties and delivering high-priority actions within the Housing Improvement Plan, including fire safety compliance. Current forecasts indicate that the 2025/26 outturn will be on budget, with a planned contribution of £82,500 to the HRA reserve, increasing the balance to approximately £686,000 by year-end. Additional finance resources are being onboarded to strengthen capacity and support service managers in ongoing budget and forecasting work.
Recommendations: That Cabinet:
- notes the contents of this report including the key projected variances to the general fund and Housing Revenue Account (“HRA”) 2025/26 revenue and capital budgets approved by Council on 21 February 2025 and the actions to ensure overspends are reduced as far as possible by the end of the financial year.
1. Implications
1.1Financial, Property and Asset implications As detailed throughout this report.
1.1Legal implications None arising from the report recommendations
Signed off by: One Legal, [email removed], 01684 272012
1.2Environmental and climate change implications The investment set out in the capital programme and through the countywide Climate Co- ordinator role will help progress countywide carbon reduction initiatives. However, increased revenue investment is needed to maintain progress against the actions set out in the Climate Emergency Action Plan and this will continue to present a challenge for the council's budget without further funding support from central government.
Page 2 of 14 Report for Cabinet, 16 December 2025
Signed off by: Maizy McCann, Climate Change Officer
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.