RESOLVED that: Approval for bidding and governance arrangements in relation to the two identified funds set up by Council, which are being resourced using the New Homes Bonus allocation for 2011-12 be delegated as follows:- The Environmental Improvements fund to be subject to a bidding process by internal Council departments only, with bids prioritised by a member panel drawn from the Cabinet and comprising the Council Leader and Cabinet Members for Built Environment and Sustainability; Environment Overview and Scrutiny committee to be requested to look at the prioritised bids for the Environmental Improvements fund and provide feedback to Cabinet prior to allocations being agreed; In respect of the Promoting Cheltenham fund, a panel, including external business and cross-party member representation and the appropriate Cabinet portfolio holders for Economic Development and Culture and Finance, will be established to sign off the bidding criteria (see draft at Appendix B) and advise Cabinet on allocations and appropriate performance monitoring arrangements.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 26th July, 2011 Economic development update and proposals for administering New Homes Bonus funding Report of the Leader of the Council
Accountable member Council Leader, Steve Jordan
Accountable officer Director Built Environment
Accountable scrutiny Environment, EBI committee
Ward(s) affected All
Key Decision Yes
Executive summary This report provides details of the proposals for administering ‘New Homes Bonus’ funding which was recently allocated by Council to:
1. Environmental improvements; and
2. Promoting Cheltenham.
Recommendations Cabinet is recommended to delegate approval for bidding and governance arrangements in relation to the two identified funds set up by Council, which are being resourced using the New Homes Bonus allocation for 2011-12, as follows:-
1.1The Environmental Improvements fund to be subject to a bidding process by internal Council departments only, with bids prioritised by a member panel drawn from the Cabinet and comprising the Council Leader and Cabinet members for Built Environment and Sustainability;
1.2Environment Overview and Scrutiny committee to be requested to look at the prioritised bids for the Environmental Improvements fund and provide feedback to Cabinet prior to allocations being agreed;
1.3In respect of the Promoting Cheltenham fund, a panel, including external business and cross-party member representation and the appropriate Cabinet portfolio holders for Economic Development and Culture and Finance, will be established to sign off the bidding criteria (see draft at Appendix B) and advise Cabinet on allocations and appropriate performance monitoring arrangements.
Note: Proposals for New Homes Bonus are being considered by the Economy and Business Improvement Overview and Scrutiny Committee on 18th July 2011 and there will be a verbal update at Cabinet on feedback received.
There will also be a further report relating to the Environmental Improvements
$iigpsvjp.doc Page 1 of 7 Last updated 15 July 2011 fund, which will be go to Environment O&S in September. Final allocations will need to be ratified by Cabinet in due course, once the bidding processes have been completed.
Legal implications The payment of funding from the environmental improvements fund to internal council departments will not require any legal documentation. However, the payment of funding from the Promoting Cheltenham fund may require the production of documentation, based on the council’s ‘Community Giving Grant’ template, to ensure that any funding is properly spent in accordance with the approved application.
HR implications There may be capacity issues that will need to be fully considered, depending (including learning and on what decisions are made as to the use of the New Homes Bonus. organisational development) Contact officer: Julie McCarthy
E-mail: [email protected] Tel no: 01242 264355 Key risks Financial – it will be important to ensure that any funds allocated, particularly to external organisations are the subject of appropriate (See also Appendix A) controls to make sure they effectively deliver target outcomes;
Capacity – staffing resources are currently stretched and the allocation and support mechanisms for the two funding schemes therefore need to take this into account, to minimise the risk of impacts on other corporate priorities.
$iigpsvjp.doc Page 2 of 7 Last updated 15 July 2011 Corporate and The two schemes being supported using New Homes Bonus funding have community plan the potential to contribute to one or more of the following corporate priorities:- Implications Cheltenham has a clean and well maintained environment;
Cheltenham’s built and natural environment is enhanced and protected;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.