RESOLVED that: Authority be delegated to the Director Operations in consultation with the Cabinet Member, Sustainability and the Council Leader, to go forward with a tendering process to undertake the first phase of the proposed works in Imperial Gardens Tentage designs for Montpellier gardens be restricted to approximately 4700M2, (excluding walkways and gazebos) and authority be delegated to the Director Operations in consultation with the Cabinet Member, Sustainability to agree the exact figure. At the same time, authority be delegated to the Director (Operations) in consultation with the Cabinet Member, Sustainability and the Council Leader to go forward with a tendering process for infrastructure in Montpellier Gardens . Authority be delegated to the Director Operations in consultation with the Cabinet Member, Sustainability and the Council Leader, to submit the relevant sections of the scheme for planning approval ... view the full minutes text for item 5.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 26 July 2011 Imperial Gardens Outline Design and Consultation Accountable member Cabinet Member Sustainability, Councillor Roger Whyborn
Accountable officer Assistant Director Operations, Rob Bell
Accountable scrutiny Environment committee
Ward(s) affected Lansdown
Key Decision Yes / No
Executive summary Following the council’s Cabinet meeting of the 15th March 2011 outline designs have been drawn up for landscape enhancements to Imperial Gardens. As well as improving the public amenity of the gardens for the people of Cheltenham, the designs are part of a strategy that entail reducing the number of festivals that take place in Imperial Gardens, and in so doing reducing the pressure on it’s infrastructure, but at the same time allowing the festivals more space (approximately 2750m2) and the use of Montpellier Gardens so that they may grow to meet the increase in popularity. The design proposals have been drawn up and widely publicised. This report and accompanying appendices presents to Cabinet the results of the consultation process and the largely positive feedback that has been received.
Recommendations 1) That authority be delegated to the Director Operations in consultation with the Cabinet Member, Sustainability and the Council leader, to go forward with a tendering process to undertake the first phase of the proposed works in Imperial Gardens
2) That tentage designs for Montpellier gardens be restricted to approximately 4700M2, (excluding walkways and gazebos) and authority be delegated to the Director Operations in consultation with the Cabinet Member, Sustainability to agree the exact figure.
3) At the same time, authority be delegated to the Director Operations in consultation with the Cabinet Member, Sustainability and the Council leader to go forward with a tendering process for infrastructure in Montpellier Gardens.
4) That authority be delegated to the Director Operations in consultation with the Cabinet Member, Sustainability
Page 1 and the Council leader, to submit the relevant sections of the scheme for planning approval and listed building consent.
5) The final decision to go ahead with works in Imperial Gardens and Montpellier Gardens are to be referred back to Cabinet for decision on the 18th October 2011 in time for completion of works over the winter 2011/2.
Financial implications The 2011/12 budget as approved by Council on 11th February 2011 included a one-off revenue budget of £140,000 for Investment in Imperial and Montpellier Gardens to provide improved facilities for hirers, including Cheltenham Festivals.
It should be noted that the consultation feedback expressed concern that there may be insufficient funding for the proposed scheme or for the additional future costs of maintaining the gardens in accordance with public expectations (paragraph 2.4 to this report).
The final scheme, to be agreed by Cabinet in October 2011 must be delivered within the approved one off revenue budget. exceed the approved one-off budget and the ongoing maintenance of the gardens met from existing annual revenue budgets..
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.