Resolved
RESOLVED THAT : The contents of this report including the key projected variances to the revised 2011/12 budget and the projected total budget saving of £302,700 be noted.
Cabinet noted this item on Tuesday 17 April 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT : The contents of this report including the key projected variances to the revised 2011/12 budget and the projected total budget saving of £302,700 be noted.
Cheltenham Borough Council Cabinet – 17 April 2012 Budget Monitoring Report 2011/12 – position as at February 2012
Accountable member Councillor John Webster, Cabinet Member for Finance and Community Development
Accountable officer Paul Jones, Head of Financial Services
Accountable scrutiny All committee
Ward(s) affected All
Key Decision No
Executive summary To update Members on the council’s current financial position for 2011/12 based on the monitoring exercise at the end of February 2012. The report covers the council’s revenue, capital, treasury management and the housing revenue account. The report identifies any known variations to the 2011/12 revised budget and a position statement on major schemes.
Recommendations 1. Note the contents of this report including the key projected variances to the revised 2011/12 budget and the projected total budget saving of £302,700.
Financial implications As detailed throughout this report.
Contact officer: Sarah Didcote, [email protected], 01242 264125
Legal implications None directly arising from this report.
Contact officer: Peter Lewis, [email protected], 01684 272695
HR implications Directors and HR Advisors have worked together to ensure vacancies are (including learning and managed effectively, via the vacancy authorisation process. organisational development) Contact officer: Julie McCarthy , [email protected], 01242 264355
Key risks As outlined in Appendix 1.
Corporate and Key elements of the budget are aimed at delivering the corporate community plan objectives within the Corporate Business Plan. Implications
Environmental and None. climate change implications
February budget monitoring report 17-4-2012 Page 1 of 12 Last updated 19 April 2012 1. Background
1.1This report provides the last monitoring position statement for the financial year 2011/12. The purpose of this report is to notify Members of the anticipated outturn position for 2011/12 including any known requests for budgets to be carried forward into 2012/13.
1.2The budget monitoring report to the end of August 2012 projected an overspend for the year of £476,400. As a result of that projection, officers were instructed to reduce spend on supplies and services to essentials for the remainder of the financial year.
1.3This measure enabled the council to address the potential in year budget deficit and deliver a revised balanced budget which does not require a contribution from general balances. It is pleasing to note that the anticipated outturn position will deliver a saving of £302,700 against this revised budget, equating to 2.1% of the 2011/12 net budget requirement of £14,077k.
1.4A number of savings are the result of delays or slippage in carrying out particular tasks which are still necessary and will need to be completed in the 2012/13 financial year. Where this applies, requests for carry forwards are noted in this report.
2. Net revenue position
2.1The table below summarises the net impact of the variances identified on the overall 2011/12 revised budget position.
Budget variances (Overspend) / para. ref: Underspend £
Commissioning Corporate Management 2,000 Divisional Overheads 25,400 Neighbourhood Management 10,400 Farmers Market 1,200 Equal Opportunity 2,200 Community Pride 20,600 Racial Equality Service Level Agreement 6,100 Glos. Association for Voluntary & Community Action 20,000 GGGG(GAVCA) (GAVCA) Resource Centre (400) Community Development 7,100 Elections & Electoral registration (13,600)
Youth Affairs 65,300 2.4 Democratic & Civic 22,400
Total Commissioning 168,700
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2012_04_17_CAB_Quarterly_budget_monitoring_Appendix_2Appendix | 23 KB | Download |
PDF |
Quarterly Budget Monitoring ReportReport | 108 KB | DownloadRead as text |
Follow Cabinet at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... | Noted | Open |
| 15 Sep 2026 | Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... | Approved | Open |
| 15 Sep 2026 | Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... | Decided | Open |
| 15 Sep 2026 | Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... | Agreed | Open |
| 15 Sep 2026 | Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.