Cabinet, Tuesday 16 April 2013 at 6.00pm

Quarterly Budget Monitoring Report (as at end of February 2013)

Noted Executive 3 papers

Cabinet noted this item on Tuesday 16 April 2013. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

RESOLVED THAT the contents of this report including the key projected variances to the revised 2012/13 budget and the projected total budget saving of £212,100 be noted. in principle, recommend to Council, as part of the 2012/13 outturn report to Council on 24 th June 2013, that this projected budget saving be used to create a provision to fund any additional expenditure relating to the new business rates retention scheme and any possible future fluctuations on business rates (paragraph 4.2). the write off of irrecoverable business rate debts totalling £68,587.90 (paragraph 4.3) be approved, noting that doing so does not impact adversely on the Council (paragraph 4.4).
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet – 16 April 2013 Budget Monitoring Report 2012/13 – position as at February 2013

Accountable member Councillor John Rawson, Cabinet Member for Finance

Accountable officer Paul Jones, GO Shared Services Head of Finance

Accountable scrutiny All committee

Ward(s) affected All

Key Decision No

Executive summary To update Members on the council’s current financial position for 2012/13 based on the monitoring exercise at the end of February 2013. The report covers the council’s revenue, capital, treasury management and the housing revenue account. The report identifies any known variations to the 2012/13 revised budget and a position statement on major schemes.

Recommendations That Cabinet:

1. Notes the contents of this report including the key projected variances to the revised 2012/13 budget and the projected total budget saving of £212,100.

2. Resolves in principle to recommend to Council, as part of the 2012/13 outturn report to Council on 24th June 2013, that this projected budget saving be used to create a provision to fund any additional expenditure relating to the new business rates retention scheme and any possible future fluctuations on business rates (paragraph 4.2).

3. Approves the write off of irrecoverable business rate debts totalling £68,587.90 (paragraph 4.3), noting that doing so does not impact adversely on the Council (paragraph 4.4).

Financial implications As detailed throughout this report.

Contact officer: Sarah Didcote, [email protected], 01242 264125

Legal implications None directly arising from this report.

Contact officer: Peter Lewis, [email protected], 01684 272695

February budget monitoring report 16-4-13 Page 1 of 16 HR implications Directors and HR Advisors have worked together to ensure vacancies are (including learning and managed effectively, via the vacancy authorisation process. organisational development) Contact officer: Julie McCarthy , [email protected], 01242 264355

Key risks As outlined in Appendix 1.

Corporate and Key elements of the budget are aimed at delivering the corporate community plan objectives within the Corporate Business Plan. Implications

Environmental and None. climate change implications

February budget monitoring report 16-4-13 Page 2 of 16 1. Background

1.1This report provides the last monitoring position statement for the financial year 2012/13. The purpose of this report is to notify members of the anticipated outturn position for 2012/13 including any known requests for budgets to be carried forward into 2013/14. Significant variances (minimum £10,000) are highlighted in this report for consideration by members.

1.2The budget monitoring report to the end of August 2012 projected an overspend for the year of £281,000. As a result of that projection, Cabinet approved a recommendation to continue a freeze on supplies and services expenditure, where possible, for the remainder of the financial year.

1.3This measure enabled the council to address the potential in year budget deficit and deliver a revised balanced budget which does not require a contribution from general balances. It is pleasing to note that the anticipated outturn position will deliver a saving of £212,100 against this revised budget, equating to 1.5% of the 2012/13 net budget requirement of £14,551,000.

1.4A number of savings are the result of delays or slippage in carrying out particular tasks which are still necessary and will need to be completed in the 2013/14 financial year. Where this applies, requests for carry forwards are noted in this report.

2. Net revenue position

2.1The table below summarises the net impact of the variances identified on the overall 2012/13 revised budget position.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2013_04_16_CAB_Budget_Monitoring_Appendix 2Appendix 24 KB Download
PDF
2013_04_16_CAB_Budget_Monitoring_Appendix3Appendix 13 KB Download
PDF
Quarterly Budget Monitoring Report (as at end of February 2013)Report 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 14 attended
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
JR
Councillor John Rawson Cabinet Member FinanceCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member Sport and CultureCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member Housing and SafetyCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Built EnvironmentCommittee Member, present
JW
Councillor Jon Walklett Cabinet Member Corporate ServicesCommittee Member, present
RW
Councillor Roger Whyborn Cabinet Member SustainabilityCommittee Member, present
PP
Pat PratleyOfficer, expected
MS
Mark SheldonOfficer, present
GL
Grahame LewisOfficer, present
DS
Councillor Duncan SmithGuest, in attendance
AC
Councillor Andrew ChardCommittee Member, in attendance

All 14 on the meeting page

On this subject at Cheltenham

Search all
  1. Quarterly Budget Monitoring Report (as at end of February 2013)This decision
  2. Quarterly Budget Monitoring Report, July-SeptemberApproved
  3. Final General Revenue and Capital Budget Proposals 2024-25 and Quarterly Budget Monitoring Report, October-December 2023Approved
  4. Final General Fund Revenue and Capital Budget Proposals 2023-24, and Quarterly Budget Monitoring Report, October-December 2022Approved
  5. Quarterly Budget Monitoring Report, July - SeptemberApproved
  6. Quarterly Budget Monitoring Report October 2019 - December 2020Noted

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies