RESOLVED THAT the contents of this report including the key projected variances to the revised 2012/13 budget and the projected total budget saving of £212,100 be noted. in principle, recommend to Council, as part of the 2012/13 outturn report to Council on 24 th June 2013, that this projected budget saving be used to create a provision to fund any additional expenditure relating to the new business rates retention scheme and any possible future fluctuations on business rates (paragraph 4.2). the write off of irrecoverable business rate debts totalling £68,587.90 (paragraph 4.3) be approved, noting that doing so does not impact adversely on the Council (paragraph 4.4).
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 16 April 2013 Budget Monitoring Report 2012/13 – position as at February 2013
Accountable member Councillor John Rawson, Cabinet Member for Finance
Accountable officer Paul Jones, GO Shared Services Head of Finance
Accountable scrutiny All committee
Ward(s) affected All
Key Decision No
Executive summary To update Members on the council’s current financial position for 2012/13 based on the monitoring exercise at the end of February 2013. The report covers the council’s revenue, capital, treasury management and the housing revenue account. The report identifies any known variations to the 2012/13 revised budget and a position statement on major schemes.
Recommendations That Cabinet:
1. Notes the contents of this report including the key projected variances to the revised 2012/13 budget and the projected total budget saving of £212,100.
2. Resolves in principle to recommend to Council, as part of the 2012/13 outturn report to Council on 24th June 2013, that this projected budget saving be used to create a provision to fund any additional expenditure relating to the new business rates retention scheme and any possible future fluctuations on business rates (paragraph 4.2).
3. Approves the write off of irrecoverable business rate debts totalling £68,587.90 (paragraph 4.3), noting that doing so does not impact adversely on the Council (paragraph 4.4).
Financial implications As detailed throughout this report.
February budget monitoring report 16-4-13 Page 1 of 16 HR implications Directors and HR Advisors have worked together to ensure vacancies are (including learning and managed effectively, via the vacancy authorisation process. organisational development) Contact officer: Julie McCarthy , [email protected], 01242 264355
Key risks As outlined in Appendix 1.
Corporate and Key elements of the budget are aimed at delivering the corporate community plan objectives within the Corporate Business Plan. Implications
Environmental and None. climate change implications
February budget monitoring report 16-4-13 Page 2 of 16 1. Background
1.1This report provides the last monitoring position statement for the financial year 2012/13. The purpose of this report is to notify members of the anticipated outturn position for 2012/13 including any known requests for budgets to be carried forward into 2013/14. Significant variances (minimum £10,000) are highlighted in this report for consideration by members.
1.2The budget monitoring report to the end of August 2012 projected an overspend for the year of £281,000. As a result of that projection, Cabinet approved a recommendation to continue a freeze on supplies and services expenditure, where possible, for the remainder of the financial year.
1.3This measure enabled the council to address the potential in year budget deficit and deliver a revised balanced budget which does not require a contribution from general balances. It is pleasing to note that the anticipated outturn position will deliver a saving of £212,100 against this revised budget, equating to 1.5% of the 2012/13 net budget requirement of £14,551,000.
1.4A number of savings are the result of delays or slippage in carrying out particular tasks which are still necessary and will need to be completed in the 2013/14 financial year. Where this applies, requests for carry forwards are noted in this report.
2. Net revenue position
2.1The table below summarises the net impact of the variances identified on the overall 2012/13 revised budget position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.