Resolved
Defer Letters of Rep: 19 Update Report: None CH introduced the application as described above. The outline application was originally submitted in 1999, with an S106 agreement attached, and was followed by an application to extend the time period to 2016. The Phase 1 REM application was approved in 2006, including the supermarket, and Phase 2 in 2007. The proposed dwellings range from one to five bedrooms, and from two to three storeys, with some apartments included. The proposed finish is brick and/or render, with main access via Hales Road , and access to 40 dwellings at the top of the site via Harp Hill. Public Speaking: [name removed], agent for applicant, in support Told Members a full suite of pre-app discussions took place in May 2013, with CBC, GCC, the Civic Society and the Architects’ Panel. CBC urban design team welcomed the design, the Civic Society gave a positive response, and the Architects’ Panel is comfortable with the masterplan with regard to principle, density and relationship to the AONB among other things. The design and lay-out of the masterplan has been incorporated, including better connections, but the density has been reduced, with 20dph on land adjacent to the AONB, and 40dph further into the site, averaging at 30dph in total. There is amenity green space for recreation and to assist with surface water, TPO’d trees are retained, an over-provision of car parking, ten car-parking spaces retained for allotments, as required by CBC, and secondary and tertiary streets incorporated. A bus route has been agreed with GCC, there is full access for emergency services, and landscaping and green connections are all in place. The design of the buildings is a mix of traditional, modern and contemporary, using locally requisitioned materials. Councillor Colin Hay, on behalf of local residents Would like some more in-depth answer to questions – the reason he is addressing Committee. The outline permission was given a long time ago and things have moved on since then. Residents of Priors Road are very worried about the impact of the proposal on the junction with Priors Road , in addition to concerns about the impact on the Hales Road/London Road and Priors Road/Prestbury Road junctions. Recalls the decision on the Starvehall Farm application and the objections that this road could end up a London Road to Evesham Road through-route, and this proposal could make it even worse – highways officers need to be quizzed to make sure that this road is up to scratch. Regarding drainage, the developer has done a lot to get sustainable urban drainage right, using 100 years plus 30% as a criterion – we need to be clear that this ... view the full minutes text for item 78.