CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheltenham Borough Council
Planning Committee, Thursday 20 February 2014 at 6.00pm

13/01239/FUL 32 Church Road

Approved Planning 4 papers

Planning Committee approved this item on Thursday 20 February 2014. Below is the council's own wording, with the papers it was decided on.

Item83

Resolved

Permit Letters of Rep: 19 Update Report: None EP reminded Members that there are two schemes with consent on this site for 10 and 7 dwellings, with a different combination of elements approved on each, one with flat roofs and one with mansard roofs. The application is at committee at the request of Councillors Coleman and Holliday. Public Speaking: [name removed], local resident, in objection On behalf of local residents, said there are two main reasons for objection. The second application, approved in 2012, is preferred by neighbours, as it is the best design and lowest density. People are frustrated with the planning system which allows developers to submit scheme after scheme until they get what they want. Can see the weight of professional opinion and realises that there are two schemes already approved, so residents are pretty much caught in a cleft stick, with the strong impression that this scheme will be approved the CBC or at appeal. The officer has done a good job with the conditions, but three of these could be strengthened. Would like an amendment of Condition 16 or assurances from the Committee that the construction method statement will only be approved after consultation with residents – this would address a number of concerns, such as loss of telephone and internet services when the telegraph pole is removed. Commends the approval of recreational facilities, but would like an amendment of Condition 14 to ensure that these too will only be approved after consultation with residents – a collaborative approach, preferably with the developers, is needed to address local needs. Lastly, regarding Condition 1, considers that five years is too long for implementation – the second application has until 2017, and residents don’t want to be kept in limbo for another two years after this, with the possibility of squatters moving into the derelict property. There are further concerns about traffic which Councillor Holliday will address, but his message is that local people will be happier if these conditions are strengthened and they would like to work in collaboration of the council and developer to see this done. Councillor Holliday, on behalf of local residents Residents are unhappy about the timing of the consultation over Christmas, resulting in some of their comments not being as detailed as they would have liked. Expects Members are frustrated to be considering another application on this site, but while neighbours accept that some development is going to take place, they want to be sure it will be done in consultation with them, in a spirit of collaboration and goodwill. New Dawn Homes have made it clear over the years that they don’t want to consult with residents, which is disappointing. Residents accept the need for the site to be developed, if only to prevent the ... view the full minutes text for item 83.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Planning Committee

APPLICATION NO: 13/02139/FUL OFFICER: [name removed] REGISTERED: 18th December 2013 DATE OF EXPIRY: 19th March 2014

WARD: St Marks PARISH:

APPLICANT: New Dawn Homes

AGENT: Stanley Partnership Architects

LOCATION: 32 Church Road St Marks Cheltenham

PROPOSAL: Redevelopment of site comprising the erection of 6no. 1 bed apartments and 5no. 3 bed houses

RECOMMENDATION: Permit

This site map is for reference purposes only. OS Crown Copyright. All rights reserved Cheltenham Borough Council 100024384 2007 1. DESCRIPTION OF SITE AND PROPOSAL 1.1 The application site comprises a roughly triangular plot which currently accommodates the old police station building. Church Road adjoins to the east and west of the site and the Triumph motorbike show room adjoins to the south. The surrounding area is generally residential in use and character.

1.2This application proposes the demolition of the existing building and the redevelopment of the site for residential purposes. The proposal involves the erection of a terrace of 5 no. 3 bed houses with integral garages along the eastern edge of the site. 6 no. 1 bedroom flats are also proposed, accommodated in two blocks, one in the northern corner of the site, linked to the terrace of housing and one in the south east corner of the site.

1.3In total the scheme provides for 11 dwellings and a total of 19 parking spaces (including 5 garages). The site area is 0.1ha and as such the density equates to 110 dph.

1.4The planning history of this site is particularly pertinent. Two separate schemes have extant consent and therefore represent fall-back positions. These are as follows:

Scheme A - 11/01196/FUL

This application was for 5 no. 3 bed houses and 5 no. 1 bed apartments, a total of 10 dwellings and a density of 100 dph. (The scheme was amended during the course of the application – it was originally for 5 no. 3 bed houses, 7 no. 1 bed apartments and 1no. bedsit – a total of 13 dwellings). 19 Parking spaces were provided (including 5 in garages). This application was refused by planning committee for the following reason:

“This proposal is a high density scheme which by over-developing the irregularly-shaped site with a tall flat-roofed block of buildings, untypical of the locality, fails to complement and respect the essential unity of design and character within the current street scene. The proposal is therefore not compliant with Policy CP7(c) of the Cheltenham Borough Local Plan (2006).”

An appeal was made against this refusal and the appeal was allowed. In their decision the Inspector stated that there was no ‘essential unity’ to the design and character of the street scene. They go on to state the proposed buildings would not be starkly different in height and scale than those which surround the site. They also stated that the density was not inappropriate given the densities of 130 and 138 dph at The Hawthorns and 30 Church Road.

The scheme differed from the current application in that the buildings had flat roofs and the south eastern block had two storeys.

Scheme B - 12/00245/FUL

This application was for 7 houses therefore providing a density of 70dph. Each house would have two parking spaces therefore a total of 14 spaces (5 provided in integral garages). This application was approved by committee following the refusal of the above mentioned application but in advance of the determination of the appeal.

The application was for a terrace of 5 dwellings in the same location as those currently proposed and two detached dwellings in the location of the two proposed elements containing 3 flats each. All of the buildings were three storeys in height and had mansard roofs. Current scheme

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
13/01239/FUL 32 Church RoadReport 94 KB DownloadRead as text
PDF
32 Church Road: additional representation 18th FebruaryReport 11 KB Withheld: personal details
PDF
32 Church Road: report update 18th FebruaryReport 21 KB Download
PDF
32 Church Road: representationsReport 555 KB Withheld: personal details

At this meeting

Whole meeting

Who was there

21 of 23 attended
CC
Councillor Chris ColemanChair, present
PH
Councillor Penny HallVice-Chair, present
HM
Councillor Helena McCloskeyCommittee Member, present
GB
Councillor Garth BarnesCommittee Member, apologies, sent representative
BD
Councillor Barbara DriverCommittee Member, present
JF
Councillor Jacky FletcherCommittee Member, apologies, sent representative
BF
Councillor Bernard FisherCommittee Member, present
RG
Councillor Robert GarnhamCommittee Member, present
LG
Councillor Les GodwinCommittee Member, present
PJ
Councillor Peter JeffriesCommittee Member, present
AM
Councillor Andrew McKinlayCommittee Member, present
MS
Councillor Malcolm StennettCommittee Member, present

All 23 on the meeting page

On this subject at Cheltenham

Search all
  1. 13/01239/FUL 32 Church RoadThis decision
  2. 17/00087/FUL Atherstone, 17 Church RoadRefused
  3. 17/00114/FUL 3 Church Street, Charlton KingsRefused
  4. 16/01402/FUL 64 Church RoadRefused
  5. 15/00517/FUL Hesters Way Baptist ChurchAgreed
  6. 14/02152/FUL 113 Church Road, LeckhamptonApproved

More from Cheltenham Planning Committee

All decisions
MeetingDecisionOutcome
21 Aug 2025 Declarations of InterestIt was agreed that this does not constitute a prejudicial interest, and he was therefore not required to leave the Ch... Agreed Open
17 Jun 2021 Any other items the Chairman determines urgent and requires a decisionIt was agreed that it was not relevant, the Chair disagreed as he thought that it was good to see that it was a mix o... Agreed Open
17 Dec 2020 20/01371/FUL Balcarras School, East End Road, Charlton Kings, Cheltenham GL53 8QFAgreed that the proposal was positive and had to be supported to cover the capacity required. It was the best that co... Agreed Open
17 Sep 2020 Minutes of last meetingRESOLVED THAT The minutes of the meeting held on 20 th August 2020 were approved and signed as a correct record. Approved Open
18 Jun 2020 ApologiesRESOLVED THAT Councillor McCloskey be appointed as Vice-Chair on a temporary basis. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies