Recommended option for the future provision of the Cheltenham Crematorium service

Agreed Executive 4 papers

Cabinet agreed this item on Tuesday 15 September 2015. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED THAT 1. it be agreed that Option E be progressed- a new build facility on Council-owned land to the east of the current cemetery site - as the preferred option for the future provision of its crematorium service; 2. authority be delegated to the Director of Environmental and Regulatory Services, in consultation with the Cabinet Member for Clean and Green Environment and the Head of Property Services to prepare and submit the necessary planning application for the new building, cremator plant and associated works; 3. it be noted that, subject to Council approving the project budget; ... view the full minutes text for item 7.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet – 15th September, 2015 Council – 19th October, 2015

Recommended option for the future provision of the Cheltenham Crematorium service

Accountable member Councillor Chris Coleman, Cabinet Member Clean and Green Environment

Accountable officer Mike Redman, Director of Environmental and Regulatory Services

Ward(s) affected All, but Oakley and Prestbury in particular

Key Decision Yes

Executive summary Investment is needed to improve public facilities and in particular, the reliability of the cremators at Cheltenham’s cemetery and crematorium. This follows the poor quality cremator installation which took place in 2011, during which the main contractor went into liquidation, leaving a number of authorities with sub-standard equipment issues.

To ensure that the best solution is secured, architects Robert Potter and Partners were commissioned to look at a number of options ranging from installing new cremators in the current building, to building a new chapel and crematorium.

The options identified are diverse and have different operational, customer service and financial implications. This report covers the results of the public consultation process and seeks Cabinet endorsement of the recommended preferred option for implementation, subject to Council agreement to the financial implications of the project.

Recommendations That Cabinet:-

1. Agrees to progress Option E - a new build facility on Council- owned land to the east of the current cemetery site - as the preferred option for the future provision of its crematorium service;

2. Delegates authority to the Director of Environmental and Regulatory Services, in consultation with the Cabinet Member for Clean and Green Environment and the Head of Property Services to prepare and submit the necessary planning application for the new building, cremator plant and associated

$oro5ircj.docx Page 1 of 14 Last updated 03 September

2015 works;

3. Notes that, subject to Council approving the project budget;

3.1the Head of Property Services will undertake the procurement for the design and construction of the new crematorium, cremators and associated works, in consultation with the Director of Environmental and Regulatory Services, the Cabinet Member for Clean and Green Environment, the Section 151 officer and the Borough Solicitor;

3.2following the procurements referred to in recommendation 3.1 a report will be presented to the Cabinet Member for Clean and Green Environment requesting approval to award the contracts to the successful contractors;

4. Delegates authority to the Head of Property Services in consultation with the Director of Environmental and Regulatory Services to take all necessary steps and undertake all necessary procedures, including the entering into of legal or other documentation, as may be required to implement or facilitate the project;

5. Asks the cross-party Cabinet Member Working Group which has been helpfully acting as a sounding board for the project to continue its role in relation to the new build project, with updated terms of reference as appropriate;

6. Agrees in principle to an increase in the cremation fee by 2017/18 to sufficiently cover additional revenue costs.

Cabinet recommends that Council:

7. Allocates the budgets for financing Option E as detailed in Appendix 4 (exempt).

Financial implications As set out within section 6 below.

Contact officer: Nina Philippidis - Accountant, [email protected] (01242) 264121

$oro5ircj.docx Page 2 of 14 Last updated 03 September

2015 Legal implications The Council owns the land on which it is proposed to build the new crematorium and associated car parking. The land on which the crematorium would be constructed lies within the administrative area of Tewkesbury Borough Council.

By virtue of section 214(1) and (2) of the Local Government Act 1972 and Section 4 of the Cremation Act 1902, the Authority has the power to build and operate a crematorium outside of its own administrative area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2015_09_15_CAB_Crem_Appendix_1Appendix 93 KB Download
PDF
2015_09_15_CAB_Crem_Appendix_2Appendix 113 KB Download
PDF
2015_09_15_CAB_Crem_Appendix_3Appendix 106 KB Download
PDF
Recommended option for the future provision of the Cheltenham Crematorium serviceReport 207 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
JR
Councillor John Rawson Cabinet Member FinanceCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member Healthy LifestylesCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member HousingCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Development and SafetyCommittee Member, present
JW
Councillor Jon Walklett Cabinet Member Corporate ServicesCommittee Member, present
CC
Councillor Chris Coleman Cabinet Member Clean and Green EnvironmentCommittee Member, present
PP
Pat PratleyOfficer, expected
MS
Mark SheldonOfficer, expected
MR
Mike RedmanOfficer, in attendance
BT
Beverly ThomasOfficer, expected
RR
Rosalind ReevesSecretary, expected

All 13 on the meeting page

On this subject at Cheltenham

Search all
  1. Recommended option for the future provision of the Cheltenham Crematorium serviceThis decision
  2. Recommended option for the future provision of the Cheltenham Crematorium serviceDecided

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open