Resolved
RESOLVED (unanimously) To allocate the budgets for financing Option E as detailed in Appendix 4 (exempt).
Council decided this item on Monday 19 October 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (unanimously) To allocate the budgets for financing Option E as detailed in Appendix 4 (exempt).
Cheltenham Borough Council Cabinet – 15 September, 2015 Council – 19 October, 2015
Recommended option for the future provision of the Cheltenham Crematorium service
Accountable member Councillor Chris Coleman, Cabinet Member Clean and Green Environment
Accountable officer Mike Redman, Director of Environmental and Regulatory Services
Ward(s) affected All, but Oakley and Prestbury in particular
Key Decision Yes
Executive summary Investment is needed to improve public facilities and in particular, the reliability of the cremators at Cheltenham’s cemetery and crematorium. This follows the poor quality cremator installation which took place in 2011, during which the main contractor went into liquidation, leaving a number of authorities with sub-standard equipment issues.
To ensure that the best solution is secured, architects Robert Potter and Partners were commissioned to look at a number of options ranging from installing new cremators in the current building, to building a new chapel and crematorium.
The options identified are diverse and have different operational, customer service and financial implications. This report covers the results of the public consultation process and seeks Cabinet endorsement of the recommended preferred option for implementation, subject to Council agreement to the financial implications of the project.
Recommendations Cabinet at their meeting on 15 September:-
1. Agreed to progress Option E - a new build facility on Council- owned land to the east of the current cemetery site - as the preferred option for the future provision of its crematorium service;
2. Delegated authority to the Director of Environmental and Regulatory Services, in consultation with the Cabinet Member for Clean and Green Environment and the Head of Property Services to prepare and submit the necessary planning application for the new building, cremator plant and associated works;
$fqlbgij4.docx Page 1 of 14 Last updated 08 October 2015 3. Noted that, subject to Council approving the project budget;
3.1the Head of Property Services will undertake the procurement for the design and construction of the new crematorium, cremators and associated works, in consultation with the Director of Environmental and Regulatory Services, the Cabinet Member for Clean and Green Environment, the Section 151 officer and the Borough Solicitor;
3.2following the procurements referred to in recommendation 3.1 a report will be presented to the Cabinet Member for Clean and Green Environment requesting approval to award the contracts to the successful contractors;
4. Delegated authority to the Head of Property Services in consultation with the Director of Environmental and Regulatory Services to take all necessary steps and undertake all necessary procedures, including the entering into of legal or other documentation, as may be required to implement or facilitate the project;
5. Asked the cross-party Cabinet Member Working Group which has been helpfully acting as a sounding board for the project to continue its role in relation to the new build project, with updated terms of reference as appropriate;
6. Agreed in principle to an increase in the cremation fee by 2017/18 to sufficiently cover additional revenue costs.
Cabinet agreed to recommend to Council that :
7. Council allocates the budgets for financing Option E as detailed in Appendix 4 (exempt).
Financial implications As set out within section 6 below.
Contact officer: Nina Philippidis - Accountant, [email protected] (01242) 264121
$fqlbgij4.docx Page 2 of 14 Last updated 08 October 2015 Legal implications The Council owns the land on which it is proposed to build the new crematorium and associated car parking. The land on which the crematorium would be constructed lies within the administrative area of Tewkesbury Borough Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2015_09_15_CAB_Crem_Appendix_2Appendix | 113 KB | Download |
PDF |
2015_09_15_CAB_Crem_Appendix_3Appendix | 106 KB | Download |
PDF |
2015_09_15_CAB_Crem_Appendix_6Appendix | 46 KB | Download |
PDF |
2015_10_13_COU_Crem_Appendix_1Appendix | 96 KB | Download |
PDF |
Recommended option for the future provision of the Cheltenham Crematorium serviceReport | 207 KB | DownloadRead as text |
Follow Council at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | General Fund & Housing Revenue Account Outturn Report 2025-26RESOLVED THAT: Council has: 1. noted the General Fund revenue outturn position for 2025/26 after the application of c... | Noted | Open |
| 20 Jul 2026 | Delegation of planning enforcement to Gloucestershire County CouncilRESOLVED THAT: 1. the delegation of planning enforcement powers to Gloucestershire County Council under Section 101 o... | Approved | Open |
| 20 Jul 2026 | Community Safety Partnership Strategy 2026-28RESOLVED THAT: 1. the Cheltenham Community Safety Partnership Strategy 2026–2028 (Appendix 2), as the strategic frame... | Noted | Open |
| 22 Jun 2026 | Member QuestionsDecision Chair of Planning Reason for Decision Date delegated decision issued 26/00442/FUL Self-build dwelling at Cha... | Decided | Open |
| 22 Jun 2026 | Revisions to Sexual Entertainment Venue (SEV) Licensing policyRESOLVED ... view the full minutes text for item 9. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.