Resolved
Permit Letters of Rep: 11 Update Report: i. Officer update – comments & conditions ii. Letter from resident (emailed to Members, 18 th November) Introduction: MJC introduced the application for works as listed above, with the exception of the floodlighting which, as set out on the blue update, has been withdrawn from the scheme. The proposals stem from a desire to enhance the sports offering at the school, which is not of the quality it would like. There is extant planning permission for improved sports facilities, but this is geared towards elite tennis and has a different design parameter. The current application seeks a multi-use sports hall. It has been thoroughly scrutinised; since being deferred from October Planning Committee, a lot of work regarding the floodlighting aspect of the scheme has been done, but officers still feel it is not ready to be considered by Members, although they consider the rest of the scheme to be compliant with national and local policy. Public Speaking: [name removed], local resident, in objection This planning application has been difficult, protracted and stressful, and without the professional background of some of neighbours, local residents would have struggled or been overwhelmed by it. Is glad that officers have commissioned an independent lighting assessment, and awaits the report with interest. Regarding the proposed sports hall, the increased roof height is not justified; the previously-agreed height was reduced, acknowledging the importance of the view, and in line with local policy. What is the point in having an area plan if it is ignored? Planning decisions should be consistent. The applicant has suggested that the area could/should be re-graded as an E3 zone with regard to light pollution – which could have undesirable consequences on the neighbourhood. Realises that it is important to support local businesses, as emphasised in the NPPF, but is concerned that this application will erode the character of the area. [name removed], principal of Cheltenham Ladies College, applicant, in support This scheme has been 3-4 years in the planning. The college estate is spread over 23 acres, but its central location means it is land-locked and there are no other opportunities to develop the sports facilities in this proposal for the expansion of the current sports hall and multi-use area. Was appointed as Principal in 2010, and understood the extant scheme to be Phase 1 of few years of further planning applications. Decided to re-examine the whole scheme, and the application as submitted is the result of three years of careful planning, considering all the alternatives, re-arranging of spaces and changing ... view the full minutes text for item 218.