Resolved
RESOLVED (unanimously) 1. To note the contents of the summary report of the treasury management activity during the first six months of 2015/16.
Council noted this item on Monday 14 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (unanimously) 1. To note the contents of the summary report of the treasury management activity during the first six months of 2015/16.
Appendix 1
The Council’s Capital Position (Prudential Indicators) This part of the report is structured to update: The Council’s capital expenditure plans; How these plans are being financed; The impact of the changes in the capital expenditure plans on the prudential indicators and the underlying need to borrow; and Compliance with the limits in place for borrowing activity.
Prudential Indicator for Capital Expenditure This table shows the revised estimates for capital expenditure and the changes since the capital programme was agreed at the Budget.
Capital Expenditure by 2015/16 Current 2015/16 Service Original Position Revised Estimate As at 30th Sept Estimate 2015 £m £m £m General Fund 2.309 14.552 23.838 HRA 6.688 2.748 6.780 Total 8.997 17.300 30.618
Changes to the Financing of the Capital Programme The table below draws together the main strategy elements of the capital expenditure plans (above), highlighting the original supported and unsupported elements of the capital programme, and the expected financing arrangements of this capital expenditure. The borrowing element of the table increases the underlying indebtedness of the Council by way of the Capital Financing Requirement (CFR), although this will be reduced in part by revenue charges for the repayment of debt (the Minimum Revenue Provision). This direct borrowing need may also be supplemented by maturing debt and other treasury requirements.
Capital Expenditure 2015/16 2015/165 Original Revised Estimate Estimate
£m £m Financed by: Capital receipts 847 7.809 Capital grants 306 660 Capital reserves 6.184 5.912 Third Party Contribution 50 893 Revenue 804 975 Total financing 8.191 16.249 Borrowing need 806 14.369
Changes to the Prudential Indicators for the Capital Financing Requirement, External Debt and the Operational Boundary The table shows the CFR, which is the underlying external need to incur borrowing for a capital purpose. It also shows the expected debt position over the period. This is termed the Operational Boundary.
Prudential Indicator – Capital Financing Requirement We are on target to achieve the revised forecast Capital Financing Requirement Appendix 1 Prudential Indicator – External Debt / the Operational Boundary
2015/16 Current Position 2015/16 Original As at 30th Sept Revised Estimate 2015 Estimate
£m £m £m Prudential Indicator – Capital Financing Requirement CFR – non housing 38.470 25.975 51.950 CFR – housing 35.400 17.700 35.400 Total CFR 73.870 43.675 87.350
Prudential Indicator – External Debt / the Operational Boundary Borrowing 106.600 106.600 106.600 Other long term liabilities* - - - Total debt 31 March 106.600 106.6000 106.600
Limits to Borrowing Activity The first key control over the treasury activity is a prudential indicator to ensure that over the medium term, net borrowing (borrowings less investments) will only be for a capital purpose. Gross external borrowing should not, except in the short term, exceed the total of CFR in the preceding year plus the estimates of any additional CFR for 2015/16 and next two financial years. This allows some flexibility for limited early borrowing for future years. The Council has approved a policy for borrowing in advance of need which will be adhered to if this proves prudent.
2015/16 Current Position 2015/16 Original As at 30th Sept Revised Estimate 2015 Estimate
£m £m £m Gross borrowing 67.830 74.622 74.504 CFR* (year end position) 73.870 87.350 87.350
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2015_12_08_CAB_Mid term_Treasury_Report_App1Report | 80 KB | DownloadRead as text |
PDF |
2015_12_08_CAB_Mid term_Treasury_Report_App2Report | 47 KB | Download |
PDF |
Treasury Mid-Term Report 2015/16Report | 115 KB | Download |
Follow Council at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | General Fund & Housing Revenue Account Outturn Report 2025-26RESOLVED THAT: Council has: 1. noted the General Fund revenue outturn position for 2025/26 after the application of c... | Noted | Open |
| 20 Jul 2026 | Delegation of planning enforcement to Gloucestershire County CouncilRESOLVED THAT: 1. the delegation of planning enforcement powers to Gloucestershire County Council under Section 101 o... | Approved | Open |
| 20 Jul 2026 | Community Safety Partnership Strategy 2026-28RESOLVED THAT: 1. the Cheltenham Community Safety Partnership Strategy 2026–2028 (Appendix 2), as the strategic frame... | Noted | Open |
| 22 Jun 2026 | Member QuestionsDecision Chair of Planning Reason for Decision Date delegated decision issued 26/00442/FUL Self-build dwelling at Cha... | Decided | Open |
| 22 Jun 2026 | Revisions to Sexual Entertainment Venue (SEV) Licensing policyRESOLVED ... view the full minutes text for item 9. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.