Resolved
RESOLVED THAT: - the contents of this summary report of the treasury management activity during the first six months of 2024/25 are noted.
Cabinet noted this item on Tuesday 26 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: - the contents of this summary report of the treasury management activity during the first six months of 2024/25 are noted.
The regulatory environment places responsibility on members for the review and scrutiny of treasury management policy and activities. This report is important in that respect, as it provides details of the treasury management activities for the first six months of this financial year and highlights compliance with the Council’s policies previously approved by members in March 2024. The Treasury Management Strategy for 2024/25 has been determined by the adoption of the Chartered Institute of Public Finance and Accountancy’s Treasury Management in the Public Services: Code of Practice (the CIPFA Code) which requires the council to approve treasury management semi-annual and annual reports.
Recommendation: That Cabinet:
1. notes the contents of this summary report of the treasury management activity during the first six months of 2024/25.
Page 1 of 13 Report for Cabinet 26 November 2024
1. Implications
As detailed throughout this report.
Signed off by: Gemma Bell, Director of Finance and Assets (Deputy s151 Officer), 01242 264124
None arising from the report recommendations.
Signed off by: One Legal [email removed]
1.3HR implications
None arising from the report recommendations.
Signed off by:
1.4Environmental and climate change implications
The Council does have some exposure to investments in a pooled fund which has shares with oil and gas companies. This is detailed in Section 5.9 of the report. As a responsible investor, the Council is committed to considering environmental, social, and governance (ESG) issues, and has a particular interest in taking action against climate change and pursuing activities that have a positive social impact.
Signed off by: Louise Forey, Climate Emergency Programme Officer, 01242 264297
1.5Property/asset implications
None specific directly arising from the recommendations.
Signed off by: Gemma Bell, Director of Finance and Assets, 01242 264124
1.6Corporate policy framework implications
Taking action to ensure overspends are reduced as far as possible by the end of the financial year will help ensure that the council can continue to deliver its corporate objectives as set out in the 2019-2023 Corporate Plan.
Signed off by: Richard Gibson, Head of Communities, Wellbeing and Partnerships, 01242 264280
Page 2 of 13 Report for Cabinet 26 November 2024
2. Economic Background
2.1UK headline consumer price inflation remained around the Bank of England (BoE) target later in the period, falling from an annual rate of 3.2% in March to 2.0% in May and then rebounding marginally to June to 2.2% in July and August, as was expected, due to base effects from energy prices. Core and services price inflation remained higher at 3.6% and 5.6% respectively in August.
2.2With headline inflation lower, the BoE cut Bank Rate from 5.25% to 5.00% at the August Monetary Policy Committee (MPC) meeting. The decision was finely balanced, voted by a 5-4 majority with four members preferring to hold at 5.25%. At the September MPC meeting, committee members voted 8-1 for no change at 5.00%, with the lone dissenter preferring Bank Rate to be cut again to 4.75%. The meeting minutes and vote suggested a reasonably hawkish tilt to rates, with sticky inflation remaining a concern among policymakers.
2.3Arlingclose, the authority’s treasury adviser, maintain its central view that Bank Rate would steadily fall from the 5.25% peak, with the first cut in August being followed by a series of further cuts, with November 2024 the likely next one, taking Bank Rate down to around 3% by the end of 2025.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Mid-term Report 2024-25Report | 839 KB | DownloadRead as text |
Follow Cabinet at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... | Noted | Open |
| 15 Sep 2026 | Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... | Approved | Open |
| 15 Sep 2026 | Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... | Decided | Open |
| 15 Sep 2026 | Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... | Agreed | Open |
| 15 Sep 2026 | Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.