Cheltenham Borough Council
Cabinet, Tuesday 7 March 2017 at 6.00pm

Financing arrangements for improvements to Leisure-at-Cheltenham

Approved Executive 3 papers

Cabinet approved this item on Tuesday 7 March 2017. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED THAT 1. the proposed improvements to Leisure-at-Cheltenham as set out in this report be approved 2. Council, subject to the conditions set out in section 6 being met to the satisfaction of the Section 151 Officer in consultation with the Cabinet Member Finance be recommended to authorise : 3. The Authority to offer a loan of up to £1.5million at an interest rate of 3% per annum to the Cheltenham Trust for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report; 4. The Authority entering into a loan agreement with The Cheltenham Trust for the sum of up to £1.5m at an interest rate of 3% per annum for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet 7 March 2017 Council 27 March 2017 Financing arrangements for improvements to Leisure-at- Cheltenham

Accountable member Cllr. Flo Clucas; Cabinet Member Healthy Lifestyles

Accountable officer Richard Gibson, Strategy and Engagement Manager

Ward(s) affected All

Key/Significant Yes Decision

Executive summary The Cheltenham Trust has asked Cheltenham Borough Council for assistance with funding a range of improvements to the facilities within Leisure-at-Cheltenham, which is owned by Cheltenham Borough Council and currently leased to the Trust on a 15 year term. The proposed improvements are as follows:  Convert two existing squash courts into new studios to enable an increase in the number of class and activity programmes.  Upgrade the existing dry-side changing spaces to reflect the quality of offer that customers expect and that competes well with the local market.  The provision of a new sauna and steam room suite adjacent to the new changing rooms, strengthening the link with health and fitness and replacing the outdated existing health suite facilities.  Extend the existing fitness suite on the ground floor into the current dance studio enabling an increased capacity to meet demand and enable improved functional training space and health support related activities.  Conversion of the existing health suite into an aquatics play space, developing and extending the aquatics opportunities for families with young children and also the commercial hires for children’s birthday parties The improvement scheme will deliver much needed investment into Leisure- at-Cheltenham to keep it competitive and to enable a growth in income and footfall. Although gym equipment was refurbished in 2013, there has been no significant investment into the fabric of the building since the post-flood refurbishment in 2007. The council plans to support this request via a loan of up to £1.5m which will be repaid by the Trust at an interest rate of 3% per annum.

Financing of improvements to Leisure@ Page 1 of 11 Last updated 27 February 2017 Recommendations 1 Cabinet approves the proposed improvements to Leisure-at- Cheltenham as set out in this report and recommends that Council;

2 Subject to the conditions set out in section 6 being met to the satisfaction of the Section 151 Officer in consultation with the Cabinet Member Finance authorises:

3 The Authority to offer a loan of up to £1.5million at an interest rate of 3% per annum to the Cheltenham Trust for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report;

4 The Authority entering into a loan agreement with The Cheltenham Trust for the sum of up to £1.5m at an interest rate of 3% per annum for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report.

Financial implications The proposed loan will be a 3% annuity loan for 10 years with twice yearly repayment of capital and interest.

The loan will be unsecured because the Trust does not itself own any land or buildings. It should be noted that the remaining 8 year period of the current management agreement is less than the 10 year period of the proposed loan, as detailed in the key risks section below. However, the council could, if both parties were willing, extend the management agreement to cover the remaining term of the loan.

The business case submitted by the Trust (Appendix 2) has been reviewed in terms of the proposed capital costs of the scheme, affordability and expected rate of return. This is based on a proposed capital cost of £1.43m. However for the basis of this report to Cabinet / Council we have based our workings on the maximum loan of £1.5m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2017_03_07_CAB_Financial_Improvement_Leisure_At_Cheltenham_Appendix_2Appendix 3.4 MB Download
PDF
2017_03_07_CAB_Financial_Improvement_Leisure_At_Cheltenham_Appendix_3Appendix 171 KB Download
PDF
Financing arrangements for improvements to Leisure-at-CheltenhamReport 144 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
FC
Councillor Flo Clucas Cabinet Member Healthy LifestylesCommittee Member, present
CC
Councillor Chris Coleman Cabinet Member Clean and Green EnvironmentCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member FinanceCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member HousingCommittee Member, expected
AM
Councillor Andrew McKinlay Cabinet Member Development and SafetyCommittee Member, present
RW
Councillor Roger Whyborn Cabinet Member Corporate ServicesCommittee Member, present
PP
Pat PratleyOfficer, present
MS
Mark SheldonOfficer, present
MR
Mike RedmanOfficer, expected
BT
Beverly ThomasOfficer, expected
RR
Rosalind ReevesSecretary, expected

All 14 on the meeting page

On this subject at Cheltenham

Search all
  1. Financing arrangements for improvements to Leisure-at-CheltenhamThis decision
  2. Revised financing arrangements for improvements to Leisure-at-CheltenhamDecided
  3. Revised financing arrangements for improvements to Leisure-at-CheltenhamApproved

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies