RESOLVED THAT 1. the proposed improvements to Leisure-at-Cheltenham as set out in this report be approved 2. Council, subject to the conditions set out in section 6 being met to the satisfaction of the Section 151 Officer in consultation with the Cabinet Member Finance be recommended to authorise : 3. The Authority to offer a loan of up to £1.5million at an interest rate of 3% per annum to the Cheltenham Trust for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report; 4. The Authority entering into a loan agreement with The Cheltenham Trust for the sum of up to £1.5m at an interest rate of 3% per annum for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet 7 March 2017 Council 27 March 2017 Financing arrangements for improvements to Leisure-at- Cheltenham
Accountable member Cllr. Flo Clucas; Cabinet Member Healthy Lifestyles
Accountable officer Richard Gibson, Strategy and Engagement Manager
Ward(s) affected All
Key/Significant Yes Decision
Executive summary The Cheltenham Trust has asked Cheltenham Borough Council for assistance with funding a range of improvements to the facilities within Leisure-at-Cheltenham, which is owned by Cheltenham Borough Council and currently leased to the Trust on a 15 year term. The proposed improvements are as follows: Convert two existing squash courts into new studios to enable an increase in the number of class and activity programmes. Upgrade the existing dry-side changing spaces to reflect the quality of offer that customers expect and that competes well with the local market. The provision of a new sauna and steam room suite adjacent to the new changing rooms, strengthening the link with health and fitness and replacing the outdated existing health suite facilities. Extend the existing fitness suite on the ground floor into the current dance studio enabling an increased capacity to meet demand and enable improved functional training space and health support related activities. Conversion of the existing health suite into an aquatics play space, developing and extending the aquatics opportunities for families with young children and also the commercial hires for children’s birthday parties The improvement scheme will deliver much needed investment into Leisure- at-Cheltenham to keep it competitive and to enable a growth in income and footfall. Although gym equipment was refurbished in 2013, there has been no significant investment into the fabric of the building since the post-flood refurbishment in 2007. The council plans to support this request via a loan of up to £1.5m which will be repaid by the Trust at an interest rate of 3% per annum.
Financing of improvements to Leisure@ Page 1 of 11 Last updated 27 February 2017 Recommendations 1 Cabinet approves the proposed improvements to Leisure-at- Cheltenham as set out in this report and recommends that Council;
2 Subject to the conditions set out in section 6 being met to the satisfaction of the Section 151 Officer in consultation with the Cabinet Member Finance authorises:
3 The Authority to offer a loan of up to £1.5million at an interest rate of 3% per annum to the Cheltenham Trust for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report;
4 The Authority entering into a loan agreement with The Cheltenham Trust for the sum of up to £1.5m at an interest rate of 3% per annum for onward funding of the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report.
Financial implications The proposed loan will be a 3% annuity loan for 10 years with twice yearly repayment of capital and interest.
The loan will be unsecured because the Trust does not itself own any land or buildings. It should be noted that the remaining 8 year period of the current management agreement is less than the 10 year period of the proposed loan, as detailed in the key risks section below. However, the council could, if both parties were willing, extend the management agreement to cover the remaining term of the loan.
The business case submitted by the Trust (Appendix 2) has been reviewed in terms of the proposed capital costs of the scheme, affordability and expected rate of return. This is based on a proposed capital cost of £1.43m. However for the basis of this report to Cabinet / Council we have based our workings on the maximum loan of £1.5m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.