Permit Letters of Rep: 3 Update Report: Additional representation MJC introduced the application, reminding Members that they deferred the previous scheme for a two-storey side and front extension and remodelling with render and cladding finish at March committee. The applicant has taken stock of the issues discussed – privacy, size, width, space between properties, and suggestion he discuss his proposal with the neighbours. In consultation with officers, a very different proposal has been generated which officers consider to be acceptable and are happy to recommend for approval. It is at Committee because the neighbour is a senior member of CBC staff. Public Speaking: SW: this doesn’t very often happen – that a number of Committee requests for redesign and changes have all been taken on board. Is impressed that the applicant has made the changes in line with what Members said, and thanks them for the efforts they have gone to. PB: must congratulate the applicant and architect for taking on board the detailed comments from neighbours and councillors. The proposal is well designed, but still very big – will therefore struggle to support it, as it is not subservient. Having said that, it works with the street scene and the size of the plot. On balance it is a better scheme, and a great example of an application being deferred and sent back, and then coming back to Committee much improved. Vote on officer recommendation to permit 11 in support 0 in objection 1 abstention PERMIT
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
APPLICATION NO: 16/02197/FUL OFFICER: [name removed] REGISTERED: 9th December 2016 DATE OF EXPIRY: 3rd February 2017
WARD: Charlton Park PARISH:
APPLICANT: [name removed]: [name removed]: 68 Sandy Lane, Charlton Kings, Cheltenham Two storey side extension, single storey front and rear extension, application PROPOSAL: of render and timber cladding and replacement windows and doors.
Update to Officer Report
1. OFFICER COMMENTS 1.1. Members should recall this application from March planning committee. The application was deferred in order for further discussions to take place with the applicant to address concerns raised during the debate. The concerns related to the size and scale of the proposed side extension, the close proximity of the proposed balcony to the neighbouring property and the overall design approach.
1.2Discussions have taken place with the applicant and revised plans have been submitted which are 543217-16-2 Rev B, 543217-16-4 Rev E, 543217-16-7 Rev F, 543217-16-8 Rev F, 543217-16-9 Rev B.
1.3Neighbours have been re-consulted for a further 10 days to allow for comments on the revised scheme. One further comment has been received. Which is generally in support of the proposed scheme however raises 3 comments regarding subservience, the projection forward of the single storey extension and its impact on the street scene and the reduction in driveway space.
1.4The revised plans include the following changes:
The proposed side extension has been reduced in width at first floor by 1.5 metres. The proposed balcony has been relocated and is now enclosed on both sides. Changes to the design and appearance of the proposed extension and remodelling of the property.
1.5In light of the changes, the mass, scale and impact on neighbouring amenity is now considered to be acceptable, and a successful response to debate at planning committee. The revised scheme now includes a recessed balcony and a contemporary first floor flat roof form, which if executed successfully, will lift the proposal architecturally. The proposed void to achieve this balcony will prevent the proposal reading as a flat roofed ‘box’; it gives the scheme a degree of drama and is a form of development that has been successfully executed at a different site in the borough (1 Arbemarle Gate).
1.6Officers acknowledge that the proposal has not been presented as successfully as it could be. The elevation drawings do not portray the overall re-modelling of the building but they are sufficient in order to determine the application, the detail that will ensure the successful execution can be controlled by conditions. It is anticipated that further visual representations of the proposal will be received in advance of the committee meeting.
1.7The side extension has been further reduced in size at first floor. This reduction in width creates an increased gap between the properties and enables the property to sit comfortably within its plot.
1.8Members raised concerns with regard to the close proximity of the proposed balcony to the neighbouring properties side elevation bathroom window. The revised plans show the balcony has been more centrally located and within its new design is enclosed on both sides. Offices consider that the location and form of this balcony will not result in any unacceptable loss of privacy to any neighbouring land user.
1.9A contemporary design approach has been adopted and officers consider that the revised form will complement the remodelling of the existing house with the use of render, timber cladding and replacement windows to create a more cohesive and contemporary overall design.
1.10The success of this scheme will be in its finishes and its execution. With that in mind, conditions requiring material samples and specifications of the proposed timber cladding and render to be submitted and approved in writing prior to their application are recommended. In addition, a condition requiring the details of the windows and external doors to be submitted is also suggested.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies