18/00934/FUL 68 Sandy Lane

Refused Planning 5 papers

Planning Committee refused this item on Thursday 21 June 2018. Below is the council's own wording, with the papers it was decided on.

Item302

Resolved

Refuse Letters of Rep: 7 Update Report: None BH introduced the application as above, for planning permission for changes to a recently-approved scheme, originally a first floor front and single storey rear extension, first floor side extension, and remodelling of the property. Permission for the majority of the works has been granted, and the current application is only concerned with the changes – the increase of approximately 400mm in the height of the first floor, and removal of fascia, guttering and cladding. The application is part retrospective, as the first floor front extension has already been built at the height now being applied for. It is at committee for transparency, as a senior staff member at CBC lives next door. The officer recommendation is to permit, subject to conditions. Public Speaking: [name removed], neighbour, in objection Is the owner of the property most affected by these changes, and frustrated to be making formal representations about a development not built to the consent granted. At Committee last year, it was clear that the proposal would have considerable impact, but Members were advised that with careful control over detailed design and materials, a high-quality scheme would be delivered. On this basis, they agreed to permit it. The scheme has not been delivered with the careful execution required. Understands that the new scheme is assessed as a new application, and therefore feel it fails to meet the council’s policy requirements as follows: firstly, visual impact – this is an attractive, prominent corner plot, highly visible on a road used by many walkers and residents. The increase of 0.5m results in an over-dominant extension, which detracts from the street scene. The extension becomes the focal point of the plot and breaks the roofline of he existing house. Officers accept that this is an awkward relationship, but Policy CP7 requires a high standard of design, and this falls short of that. Supplementary planning guidance requires extensions to be subservient, not detract, and play a supporting role, but it is clear that the enlarged forward box of this extension is not subservient - policy requirement is therefore not fulfilled, and this is not addressed in the report, although it was highlighted in two other reports of residential extensions on tonight’s agenda. Secondly, loss of amenity: on site visit, Members will have noticed that the additional height of the extension has impacted the light entering her kitchen – the obscure-glazed side window is the only direct light source. Through-light from other secondary windows ... view the full minutes text for item 302.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Planning Committee

APPLICATION NO: 18/00934/FUL OFFICER: [name removed] REGISTERED: 14th May 2018 DATE OF EXPIRY: 9th July 2018

WARD: Charlton Park PARISH: Charlton Kings

APPLICANT: [name removed]: Build Design

LOCATION: 68 Sandy Lane, Charlton Kings, Cheltenham

PROPOSAL: First floor front extension, single storey extension to the rear of the garage, first floor side extension, application of render and timber cladding and replacement windows and doors (revised scheme to previously approved application ref. 17/01984/FUL, changes to include an increase in the overall height of the first floor addition by approx. 400mm, removal of fascia/guttering detail and removal of first floor side elevation cladding) Part-retrospective.

RECOMMENDATION: Permit

This site map is for reference purposes only. OS Crown Copyright. All rights reserved Cheltenham Borough Council 100024384 2007 1. DESCRIPTION OF SITE AND PROPOSAL 1.1 The application site relates to a detached residential property located on the corner of Sandy Lane and Hartley Close.

1.2The applicant is seeking planning permission for changes to an already permitted application 17/01984/FUL. The proposal includes a first floor front extension, single storey rear extension, first floor side extension, application of render and cladding to the existing dwelling and replacement windows and doors. These works are part-retrospective as works have started; the first floor front extension has been erected at the increased height.

1.3The changes to be considered as part of this application are an increase in height of the first floor front extension by approximately 400mm, the removal of the fascia/guttering detail and the removal of the cladding from side elevation of this extension.

1.4The application is before members in the interests of transparency, due to a senior member of Cheltenham Borough Council staff living in close proximity to the application site.

2. CONSTRAINTS AND RELEVANT PLANNING HISTORY

Constraints: Airport Safeguarding over 45m Smoke Control Order

Relevant Planning History: 16/02197/FUL 31st May 2017 PER Two storey side extension, single storey front and rear extension, application of render and timber cladding and replacement windows and doors.

17/01984/FUL 13th November 2017 PER Single storey front extension, single storey extension to the rear of the garage, first floor side extension, application of render and timber cladding and replacement windows and doors. (Revised scheme to 16/02197/FUL)

18/00302/AMEND 16th February 2018 PAMEND Nonmaterial amendment to planning permission 17/01984/FUL - to move position of kitchen window by 1281mm. Reduce the amount of cladding. Change rear to have bifold/patio/french door

18/00303/DISCON 16th February 2018 DISCHA Discharge of condition 3) Cladding and Render and condition 4) Windows and external Doors, of Planning Permission 17/01984/FUL.

3. POLICIES AND GUIDANCE Saved Local Plan Policies CP 1 Sustainable development CP 3 Sustainable environment CP 4 Safe and sustainable living CP 7 Design Adopted Joint Core Strategy Policies SD4 Design Requirements SD14 Health and Environmental Quality

Supplementary Planning Guidance/Documents Residential Alterations and Extensions (2008)

National Guidance National Planning Policy Framework

4. CONSULTATIONS

Gloucestershire Centre For Environmental Records 30th May 2018

Biodiversity report received.

Wales And West Utilities 29th May 2018

Letter and Plan available to view on line.

5. PUBLICITY AND REPRESENTATIONS

Number of letters sent 4 Total comments received 7 Number of objections 3 Number of supporting 0 General comment 1

5.1Four letters were sent to neighbouring properties, Seven letters of representation have been received - six letters of objection and one general comment.

5.2The concerns raised within the letters of objection relate to but are not limited to the following:

 Unacceptable design

 Increase in height of the front extension will be out of keeping with surroundings

 Increased visual impact

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
18/00934/FUL 68 Sandy LaneReport 214 KB DownloadRead as text
PDF
68 Sandy Lane: additional representtions, 18th JuneReport 1.5 MB Download
PDF
68 Sandy Lane: representationsReport 4.1 MB Withheld: personal details
PDF
68 Sandy Lane: statement from applicant, 15th JuneReport 556 KB Download
PDF
68 Sandy lane: report update, 15th JuneReport 119 KB Download

At this meeting

Whole meeting

Who was there

15 of 20 attended
GB
Councillor Garth BarnesChair, apologies, sent representative
PB
Councillor Paul BakerVice-Chair, apologies, sent representative
SC
Councillor Stephen CookeCommittee Member, present
DS
Councillor Diggory SeacomeCommittee Member, present
VA
Councillor Victoria AtherstoneCommittee Member, apologies
BF
Councillor Bernard FisherCommittee Member, expected
DB
Councillor Dilys BarrellCommittee Member, present
MC
Councillor Mike CollinsCommittee Member, apologies, sent representative
WF
Councillor Wendy FlynnCommittee Member, apologies
AH
Councillor Alex HegenbarthCommittee Member, expected
KH
Councillor Karl HobleyCommittee Member, present
PM
Councillor Paul McCloskeyCommittee Member, present

All 20 on the meeting page

On this subject at Cheltenham

Search all
  1. 18/00934/FUL 68 Sandy LaneThis decision
  2. 16/02197/FUL 68 Sandy LaneDeferred
  3. 17/00691/FUL 70 Sandy LaneDecided
  4. 16/02197/FUL 68 Sandy Lane, Charlton KingsDeferred
  5. 15/02131/FUL Land off Sandy LaneDecided
  6. 13/02026/FUL 9 Sandy Lane, Charlton KingsApproved

More from Cheltenham Planning Committee

All decisions
MeetingDecisionOutcome
21 Aug 2025 Declarations of InterestIt was agreed that this does not constitute a prejudicial interest, and he was therefore not required to leave the Ch... Agreed Open
17 Jun 2021 Any other items the Chairman determines urgent and requires a decisionIt was agreed that it was not relevant, the Chair disagreed as he thought that it was good to see that it was a mix o... Agreed Open
17 Dec 2020 20/01371/FUL Balcarras School, East End Road, Charlton Kings, Cheltenham GL53 8QFAgreed that the proposal was positive and had to be supported to cover the capacity required. It was the best that co... Agreed Open
17 Sep 2020 Minutes of last meetingRESOLVED THAT The minutes of the meeting held on 20 th August 2020 were approved and signed as a correct record. Approved Open
18 Jun 2020 ApologiesRESOLVED THAT Councillor McCloskey be appointed as Vice-Chair on a temporary basis. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies