RESOLVED THAT 1. Option 2 be approved i.e. dispose of Arle Nursery site, and procure the plants for our public realm planting externally; and 2. the Head of Property and Asset Management, in consultation with the Cabinet Member Finance, be authorised to determine the most appropriate means of disposing of the property (in one or more parts) in order to obtain best consideration, and to enter into such negotiations as he considers necessary to achieve that outcome 3. the Executive Director, Finance and Assets, in consultation with the Cabinet Member Finance, be authorised to accept an offer (or offers, if sold in more than one part) for the purchase of the property (in one or more parts) which in his reasonable opinion (following receipt of supporting professional advice) represents the best consideration that can reasonably be obtained for the site overall; 4. the Borough Solicitor be authorised to conclude such documents as she considers reasonably necessary or advisable to reflect the terms agreed under paragraph 3 above
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 10th July 2018 Arle Nursery Strategic Review
Accountable members Councillor Rowena Hay, Cabinet Member Finance
Accountable officer Mark Sheldon, Director of Corporate Projects
Ward(s) affected All
Key/Significant Yes Decision
Executive summary This report considers the business case for retaining Arle Nursery site, selling it or developing it to be a fully-fledged garden centre for the public.
Each option assesses the community, economic, environmental, legal, HR and technological implications. A detailed financial assessment of each option is also provided.
The recommendation supports the delivery of additional affordable housing units which is a priority for the Cabinet.
Recommendations Cabinet is recommended to:-
1. Approve option 2 i.e. dispose of Arle Nursery site, and procure the plants for our public realm planting externally; and
2. Authorise the Head of Property and Asset Management to determine the most appropriate means of disposing of the property (in one or more parts) in order to obtain best consideration, and to enter into such negotiations as he considers necessary to achieve that outcome
3. Authorise the Executive Director, Finance and Assets, in consultation with the Cabinet Member Finance, to accept an offer (or offers, if sold in more than one part) for the purchase of the property (in one or more parts) which in his reasonable opinion (following receipt of supporting professional advice) represents the best consideration that can reasonably be obtained for the site overall;
4. Authorise the Borough Solicitor to conclude such documents as she considers reasonably necessary or advisable to reflect the terms agreed under paragraph 3 above
2018_06_26_CAB_Arle Nursery v4
Page 1 of 6 Financial implications A summary of the business case that has been created for the 2 options to retain or dispose is included at section 5 and a detailed analysis of the business case is set out at Appendix 2.
Legal implications If Option 1 is adopted, the Council would have to ensure that the buildings are in a fit state for use by employees, and meets current statutory environmental requirements.
If Option 2 is adopted, the Council has a statutory obligation under s123 of the Local Government Act 1972 to secure the best consideration reasonably obtainable when disposing of a freehold or long leasehold interest in a property.
If Option 3 is adopted, the Council would have do so through an existing or new company due to the statutory requirements of the Localism Act 2011 and Local Government Act 2003.
Contact Officer (legal property implications): Rose Gemmell [email protected]
Any purchasing requirements of the Council will need to be carried out in accordance with the Council’s contract rules and the Public Contracts Regulations 2015.
Contact officer (legal contract/procurement implications): Donna Ruck [email protected]
HR implications There are no direct HR implications arising from this report for employees (including learning and of Cheltenham Borough Council. organisational development) There are a number of HR implications arising from the report for Ubico Ltd and these are being managed by the Publica HR team.
Key risks If cabinet members decide not to select the option with greatest financial benefit then the MTFS will be negatively impacted.
Corporate and This review supports CBC’s review of its property portfolio, specifically for community plan appropriate disinvestment opportunities in order to deliver additional Implications income to support the MTFS provision of housing.
Environmental and Disposal of the nursery will save on fuel and carbon emissions. climate change The impact of the sale of the land has already been considered as part of implications the JCS strategy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.