Resolved
RESOLVED THAT The review of performance in 2017-18 be noted.
Cabinet noted this item on Tuesday 10 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT The review of performance in 2017-18 be noted.
Cheltenham Borough Council Cabinet – 10 July 2018 Review of the council’s performance at end of 2017-18
Accountable member Cllr. Steve Jordan, Leader of the Council
Accountable officer Richard Gibson, Strategy and Engagement Manager
Accountable scrutiny Overview and Scrutiny Committee committee
Ward(s) affected All
Key Decision No
Executive summary The performance report takes information and data from our performance management system to provide elected members with an overview of how the council is performing. This enables elected members to input into discussions about how to resolve areas where there maybe performance concerns and also to recognise where performance is better than expected.
The report summarises how the council performed in regard to the published milestones as set out in the 2017-18 action plan that was agreed by Council on 27th March 2017.
The full performance report is attached as appendix 2.
Recommendations Cabinet to note the review of performance in 2017-18
Financial implications None as a result of this report
Legal implications None as the result of this report
HR implications None as the result of this report (including learning and organisational development) Key risks The business planning process helps the council manage risk in a number of areas, but particularly through creating a strategic framework for the management of projects and initiatives.
If we do not respond to performance information, then we may not direct change and improvement in a positive direction. Corporate and This report sets out performance information relating to the delivery of community plan corporate priorities in 2017-18 Implications Environmental and None identified as a result of this report climate change implications
Cabinet 10 July 2018 Page 1 of 4 Last updated 10 July 2018 1. Background
1.1The performance report takes information and data from our performance management system to provide elected members with an overview of how the council is performing. This enables elected members to input into discussions about how to resolve areas where there maybe performance concerns and also to recognise where performance is better than expected.
1.2The report summarises how the council performed in regard to the published milestones, performance indicators and outcomes set out in the 2017-18 action plan that was agreed by Council on 27th March 2017
1.3The full performance report is attached as appendix 2.
2. End of year performance overview
Corporate Strategy milestones 2.1 In the 2017-18 action plan, we identified 82 milestones to track our progress. Out of these:
51 (62%) are complete within the financial year. 7 (9%) are green and are on track to be delivered on time within agreed timescales. 23 (28%) are amber. These are projects that were not delivered within the financial year but have been pushed back into the current financial year with commitments set out in the 2018/19 corporate strategy. 1 (1%) is red.
2.2The red milestone relates to the highways agency agreement.
ENV 7 Working with GCC As part of the Mar-18 Tim Red This work was being led to develop a sustainable Highways Collaborative Atkins by GCC as the approach to managing working consultation, Highways Authority. highway matters in work with GCC to Phase 1 on the Cheltenham increase local influence consultation was in the management of completed in March highways matters in 2017. The first stage of Cheltenham stage 2 was commenced. CBC await the next steps to be initiated by GCC.
3. Consultation and feedback 3.1 The draft performance report was presented to the Council’s Overview and Scrutiny Committee on 25 June 2018. Members of the committee raised the following issues.
3.2There was a desire to understand more about the issues relating to the delays in developing a sustainable approach to managing highway matters in Cheltenham and how members can help resolve this.
3.3There was interest in receiving an update on the proposed improvements to Cheltenham Spa Railway station.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2018_07_10_CAB_Review_Council_Performance_appendixAppendix | 188 KB | Download |
PDF |
Review of the council's performance at end of 2017-18Report | 95 KB | DownloadRead as text |
Follow Cabinet at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... | Noted | Open |
| 15 Sep 2026 | Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... | Approved | Open |
| 15 Sep 2026 | Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... | Decided | Open |
| 15 Sep 2026 | Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... | Agreed | Open |
| 15 Sep 2026 | Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.