Publication of the Infrastructure Funding Statement and CIL Rate Summary Statement
ApprovedExecutive4 papers
AI summaryCheltenham Cabinet approves publication of the 2024/25 Infrastructure Funding Statement and December 2025 CIL Rate Summary, with CIL receipts of £3,469,533.19 reported for the year, both to be published by 31 December 2025.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBoth documents to be published by 31 December 2025
Money£3,469,533.19Cheltenham CIL receipts for 2024/25
What happens nextPublish by 31 December 2025Submit CIL and S106 data to Government
Who it affectsDevelopers and parish councilsPlus infrastructure providers and members of public
What was decided
Cabinet approved publication of the Infrastructure Funding Statement 2024/25, covering the financial year ending 31 March 2025, and the submission of its CIL and S106 information to Government.
Cabinet approved the Annual CIL Rate Summary Statement December 2025 for publication on the Council's website by 31 December 2025.
Why
It is a statutory obligation under the Community Infrastructure Levy Regulations 2010 (as amended), particularly Regulations 121A and 121C. Report P17, P115, P116
The regulations require publication no later than 31 December in a given calendar year after the financial reporting year. Report P7, P115
Publication makes information on developer contributions available to members, the public and infrastructure providers. Report P148, P150, P153
What happens next
Publish the IFS on the Council's website and notify the Ministry of Housing, Communities and Local Government by end December 2025. Report 6.1
Publish the CIL Annual Rate Summary Statement December 2025 on the Council's website by 31 December 2025. Report 6.2
Continue work to improve S106 and CIL monitoring processes during 2025/26 and into 2026/27, and review CIL administration costs. Report P38, 3.6
The money
£3,469,533.19 Cheltenham CIL receipts for reporting year 2024/25 Report P56
£228,872.38 Total CIL expenditure by the borough council in 2024/25 Report P57
£161,753.28 Neighbourhood CIL transferred to Parish Councils in 2024/25 Report P59
£2,778,075.61 Held in the Strategic Infrastructure Fund at end of 2024/25 Report P67
£3,570,964.99 S106 closing balance at end of March 2025
£270,000 Off-site affordable housing contributions spent on Medway Court, Whaddon Road, for 6 social rent flats Report P85, 3.10
£209,640.72 Off-site affordable housing contribution received from 19/00111/FUL Report P85, 3.10
£19,382.74 CBC Borough Neighbourhood Fund Projects, Round 1 Report P60
Options considered
Chosen: Approve publication of the IFS 2024/25 and CIL Rate Summary Statement December 2025. Statutory requirement under CIL Regulations 2010 (as amended); no alternative options identified. Report P118
Implications
Legal: Publication of an IFS and Annual CIL Rate Summary is a statutory obligation under the CIL Regulations 2010 (as amended); failure to publish by 31 December would be a breach of regulations. Report P17, P132, P133
Financial: No direct financial implications from the recommendations; the Council must ensure funds are available to make payments against S106 and CIL funded projects when required. Report P12, P13
Equalities: No full screening assessment required; the report is for statutory compliance only. Report P34, P163
Climate: Infrastructure List includes projects supporting modal shift, Bus Rapid Transit, EV charging and strategic green infrastructure, with potential positive environmental impact and support for the 2030 net zero target. Report P23, P24
Risk: Risk of breach of Government Regulations if not published by 31 December 2025; risk register being maintained by the CIL Joint Committee. Report P132, P133, P134
Staffing: A Planning Research and Monitoring Officer role is in place; a review of CIL administration costs and resources for the CIL Joint Committee is underway. Report P37, 3.4, 3.6
Who and where
Developers and landowners considering CIL liable development in 2026 Report P149, P154
Members of the public and infrastructure providers Report P148, P150, P153
Households in need of affordable housing Report 3.10, P84, P85
Gloucester City Council and Tewkesbury Borough Council as CIL Joint Committee partners Report 2.6, 2.7
Gloucestershire County Council as a separate S106 reporter for county matters Report 3.12
Timeline
12 November 2024: Inaugural meeting of the CIL Joint Committee Report 2.7
04 March 2025: CIL Joint Committee decision to split the CIL Regulation 59(1) Infrastructure Fund, ringfencing 25% for local strategic projects Report 4.3
31 March 2025: End of the reporting year for the IFS 2024/25 Report 3.3, P65
27 October 2025: CIL rate for 1 November 2025 published online, with an index value of 400 for 2026 Report 5.2
31 December 2025: Deadline for publication of the IFS and CIL Annual Rate Summary Statement on the Council's website Report 6.1, 6.2, P7
01 January 2026 to 31 December 2026: Period during which the new indexed CIL rates will apply Report P154
2025/26 and 2026/27: Further work planned to improve S106 and CIL monitoring processes Report P38
December 2026: Planned submission of the Infrastructure Delivery Plan alongside the Strategic Local Plan Report P136
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge that local authorities can levy on new development to fund infrastructure
IFS: Infrastructure Funding Statement, an annual report on developer contributions and infrastructure funding
S106: Section 106 agreements, planning obligations attached to planning permissions to mitigate development impacts
RICS: Royal Institute of Chartered Surveyors, which publishes the CIL Index used to adjust CIL rates for inflation
IDP: Infrastructure Delivery Plan, accompanying the Strategic Local Plan to identify infrastructure needs
SLP: Strategic Local Plan, the development plan being prepared by the partner councils
JCS: Joint Core Strategy, the previous strategic plan shared with Gloucester City and Tewkesbury Borough Councils
MHCLG: Ministry of Housing, Communities and Local Government, recipient of the IFS data submission
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
RESOLVED THAT: 1. the publication by 31 December 2025 of the Infrastructure Funding Statement (IFS) 2024/25, relating to the financial year ending 31 March 2025, and the submission of its CIL and S106 information to Government, is approved; 2. the Annual CIL Rate Summary Statement December 2025 is approved and its publication on the Council’s website by 31 December 2025 is approved.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
All Councils who charge the Community Infrastructure Levy (CIL) and/or secure developer contributions by way of Section 106 (S106) agreements have a statutory obligation to prepare the following:
• Infrastructure Funding Statement (IFS) (Appendix 3 Part 1 CIL Report and Part 2 S106 Report and Appendix 4 Infrastructure List 2025) and
The IFS content relates to the previous financial year to the one in which it is being published. This IFS reports on financial year 2024/25. The IFS must include an Infrastructure List (published as Part 3 of the IFS, see Appendix 5), to help guide future priorities for allocation of the CIL Reg 59(1) strategic infrastructure fund receipts.
To meet the requirements of the CIL Regulations these documents should be
Page 1 of 18 Report for Cabinet, 16.12.2025
published by the Council no later than 31 December in a given calendar year after the financial reporting year.
Recommendations: That Cabinet
1. approves the publication of the Infrastructure Funding Statement (IFS) 2024/25 relating to the financial year ending 31 March 2025 by 31 December 2025 and that its CIL and S106 information be submitted to Government. 2. notes the Annual CIL Rate Summary Statement December 2025 and approves it for publication on the Council’s website by 31 December 2025.
1. Implications
1.1Financial, Property and Asset implications
No financial implications as a result of the recommendations of this report.
Allocation decisions made in the reporting year, will however result in the Council needing to ensure that it has funds available to make payments against s106 funded projects and/or CIL funded projects at the time payment is required to be made.
The financial data contained within the IFS Part 1 CIL Report and Part 2 S106 Report has been reviewed by finance officers.
There are no specific property or asset implications resulting from the CIL Infrastructure Fund allocation decisions in the reporting year.
The production of an IFS, at least annually, including a regulation 121A Infrastructure List is a statutory obligation as a result of amendments to the Community Infrastructure Levy Regulations 2010 (the CIL Regulations) by the Community Infrastructure Levy (Amendment) (England) (No.2) Regulations 2019. As is the publication of the Annual CIL Rate Summary Statement. The Statement must address CIL collection and spend, infrastructure projects and S106 collection and spend. The publication of the IFS fulfils this statutory requirement.
Signed off by: Charlotte Lockwood, Senior Locum Lawyer, One Legal,
Page 2 of 18 Report for Cabinet, 16.12.2025
[email removed], 01684 272691
1.3Environmental and climate change implications
No Climate Change Impact Assessment needed as the report does not relate to a new project or policy.
This is a report primarily on securing, demanded, receipt, allocation, and expenditure of CIL/S106. However, the effective use of CIL/S106 receipts has the potential to have a positive environmental impact. For example, the ‘Infrastructure List’ (Appendix 4) contains proposals including links which will help to deliver modal shift, a replacement recycling facility, developing mass rapid transit (now renamed Bus Rapid Transit), rail related infrastructure enhancements, EV charging infrastructure and strategic green infrastructure, which all have a huge positive potential for tackling climate change.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.