That a) Subject to the inclusion of development management and housing provision, the programme outlined in Appendix A be approved; b) Sessions be open to all members of the Strategic Planning Board and the Northern and Southern Planning Committees; and c) The scheduling of half day events be based on a six week cycle.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
1.1To consider a programme of training for Councillors on Strategic Planning Board and Planning Committees post Vesting day.
2.0Decision Required
2.1To propose that arrangements for an on-going programme of Councillor training be put in place to initially cover the matters identified in Appendix 1.
3.0Financial Implications for Transition Costs
3.1None.
4.0Financial Implications 2009/10 and beyond
4.1The bulk of training will be provided by Cheshire East staff or those working as part of a shared service arrangement, for which the only cost to the Authority will be their time. It is not expected that any external speakers or consultee would charge for their involvement in such sessions.
Legal implications
5.1The Council has accepted that all Members who sit on Planning Board or Planning Committees should be trained and it is important that such training is on-going so Councillors develop a deep understanding of the planning system to allow them to make sound decisions.
6.0Risk Assessment
6.1Should Councillors take decisions without being fully aware of all of the facts and issues regarding a particular development, or misunderstand particular evidence, this may increase the likelihood of a Judicial Review by an aggrieved party who would question the soundness of that decision. 7.0 Background and Options
7.1In 1997 as part of the Committee on Standards in Public Life (the Nolan Committee) various aspects of local government were addressed. One chapter was devoted to the planning system. This made a number of recommendations designed to ensure full public confidence in the planning process. One was that “All members of an authority’s planning committee (or equivalent) should receive training in the planning system, either before serving on the committee, or as soon as possible after their appointment to the committee”.
7.2Central and Local Government embraced this recommendation and initial training was completed by Cheshire East’s planning councillors on the 17th and 19th March in advance of Vesting Day. These sessions were a basic introduction to the planning system for Members unfamiliar with this area, or acted as a refresher for more experienced Members.
7.3Planning is an increasingly complex subject area with case law, advice and legislation constantly changing. It is therefore important that Members involved in Planning are kept up to date with changes through an on-going training programme to inform their decision making.
7.4Areas to be addressed in training split into three broad groups:
• The Development Plan - from national and regional policies through to the saved policies of the existing five Local Plans and the Structure Plan; • Other material considerations e.g. highways issues; archaeology • Other new challenges for Cheshire East that are particularly pressing as a result of a proposed development or government initiative e.g. municipal waste technologies in advance of an application to determine a planning application for an Energy From Waste Plant.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.