That delegated authority be granted to the Head of Planning and Policy to negotiate upon and secure amendments to the wording of the S106 Agreement to allow alterations to the phasing of delivery of monies required prior to commencement of development for highways contributions and other items such as the provision of playing pitches and sporting facilities, to be carried out in consultation with the Chairman of the Strategic Planning Board and Ward Councillors.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Susan Orrell Macclesfield Borough Council Our ref: DS/JW/WIMM1050 PO Box 40 Your ref: 05/1184P Town Hall E: [email removed] Macclesfield SK10 1DP
Dear Susan
FORMER HENBURY HIGH SCHOOL, WHIRLEY ROAD
th I write further to your meeting with my client on the 8 May 2009 regarding the discharge of conditions and proposed variations to the agreed S106.
As agreed I write to provide you with a summary of the variations to the S106 which were discussed at the meeting. In order for George Wimpey to be able to continue with the development in a viable manner they are unable to outlay the level of expenditure currently required by the S106 in advance of commencement/occupation of the residential units. The only way that the development can proceed is subject to committed sales, without this Wimpey cannot progress. As I have said in earlier correspondence the proposed variations to the S106 would not result in Wimpey reneging on any of its obligations. Rather it is the case that a longer term phased approach is required which is closely linked to the completion of units (following committed sales) as opposed to the release of monies for the leisure facilities ‘prior to the commencement of development’.
The table below details the existing clauses that need to be revisited and the way in which we see each being amended. Also attached is a plan prepared by TPM Landscape which should be read in conjunction with the table (Dwg ref: 380 Phasing Plan 23 April 09).
Deed of Agreement (dated 24.02.06) Revised Heads of Terms
Clause 4.6 GW shall pay the County Council £100,000 for the GW shall pay the CC £100,000 delivery of highway improvements prior to the on the commencement of th commencement of development. development of the 50 residential unit.
Clause 8.2 There shall be 2 junior grass pitches with new There shall be 2 new grass drainage systems and pumping station to lift surface pitches with new drainage water into a public drain. systems.
A new pumping station will be 2
provided.
Clause The reseeding and drainage improvements of the Phase 1: Sports pitch 1 to have 8.3.2 pitches shall be undertaken from April 2009 over the remedial drainage treatment Summer of 2009 and be ready for Autumn 2009. and ground preparation to make it playable for the 2009/10 season.
Clause The pavilion shall be made available at the same time The pavilion is to be completed 8.3.3 as the pitches in Autumn 2009. in two phases:
Phase 2: Sports element of the pavilion to be completed in Autumn 2010.
Phase 4: Community element of pavilion to be completed upon sale of all residential units or 2012.
Clause A construction, provision works, equipment phasing Construction programme to be 8.11.1 plan and programme for the MUGA, LEAP, remainder agreed in writing in accordance of the open space, landscaping arrangements, car with enclosed Phasing Plan. park, pavilion and access shall be agreed in writing prior to the commencement of development.
Clause The open spaces, including the MUGA and LEAP, Delete clause relating to 8.11.2 pavilion and pitches must be provided prior to first occupation of units adjacent to occupation of any residential units abutting to or in the the POS as delivery will be vicinity of the these facilities. based on agreed Phasing Plan at Clause 8.11.1. .
Clause The STP and grass pitches shall remain available for Phase 1: as set above. 8.15 community use throughout the football season Phase 2: Sports pitch 2 to have 2006/07. Drainage works are to be carried out during remedial drainage treatment the closed or the summer season. This should and ground preparation to make continue until alternative facilities are provided off or it playable for 2010 – 2011. on site. 3
I trust that this is sufficient for you and your Members to consider the broad principles of the proposed th revised S106 at the meeting of the Strategic Board on the 27 May. If you require any additional information please do not hesitate to contact me.
Yours sincerely
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.