Resolved
RESOLVED That approval be given to the corporate branding for Shared Services to be applied in an appropriate manner, and that the communications implementation plan be agreed.
Shared Services Joint Committee approved this item on Monday 13 July 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That approval be given to the corporate branding for Shared Services to be applied in an appropriate manner, and that the communications implementation plan be agreed.
2.1To agree the corporate branding for the Shared Services and to agree the communications implementation plan.
3.1To support the effective delivery and implementation of Shared Services through corporate branding and communications.
4.1Shared Services are pan Cheshire and will apply across all Wards.
5.0Local Ward Members
5.1As Shared Services are pan Cheshire there will no issues that will affect particular Ward Members.
6.0Policy Implications including - Climate change - Health
6.1None apply.
7.0Financial Implications for Transition Costs (Authorised by the Borough Treasurer)
7.1The branding and communications plan has been developed by the in-house communications, marketing and design teams for the two councils. There are no direct costs associated with this work.
The purchase of a website domain name will cost in the region of £50 - £70.
Version 1 April 2009 (SH) 8.0 Financial Implications 2009/10 and beyond (Authorised by the Borough Treasurer)
8.1Once the branding has been agreed it will be for each service to procure its own branded items e.g. stationery, uniforms, livery, signage.
The decision for purchase of goods will be dealt with on a service by service case, based on the comparative costs of the need for goods and the life of the Service.
Most of the communications activity is internally focussed and will take the form of e-communications. This work will be conducted by the respective web teams and service content managers.
9.0Legal Implications (Authorised by the Borough Solicitor)
9.1There no legal implications in relation to communications.
10.1Services need to be able to order their branded items quickly, particularly those that are public facing in order to conduct their business and not resort to using unbranded material as this does not enhance the professional reputation of either authority.
10.2The reputation of both councils could be compromised if publicly facing services lack clear identity.
10.3Clarity and reassurance for staff about their position as part of a Shared Service will be reinforced through effective branding and regular communication about their service.
10.4Shared Services staff need to be issued with appropriately branded identity badges to fulfil the need for official identification for both internal and external (publicly facing) purposes, including security.
11.0Background and Options
11.1Branding achieved to date Good progress has been made on branding. Development has taken account of the need to properly represent the separate identity of Shared Services while retaining a look and feel that is relevant and in keeping with the branding developed for both the West and East councils.
Visual presentations for a range of items were submitted to the first formal board on 10 June.
Version 1 April 2009 (SH) To enable Shared Services business to proceed unhindered in the short term the following items have been agreed for use: • Letterhead • Business cards • Compliment slips.
11.2Branding to be approved Further work has been done to develop other items that will need to be branded. Decisions will need to be made on a case by case basis on whether it is prudent to provide new branded items, for example vehicle livery or signage depending on the expected life of the service.
Items still to be approved include: • T-shirts • Name badges • High visibility jackets • Identity badges • Intranet • Signage - time related for certain services • Vehicle signage – time related.
Further adjusments were made to the branding of some of these items following feedback from the cabinet meeting held on 10 June in Sandbach.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Branding and CommunicationsMinutes | 70 KB | DownloadRead as text |
Follow Shared Services Joint Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jun 2025 | Appointment of ChairThat Councillor Jill Rhodes be appointed as chair for the 2025/26 municipal year. | Decided | Open |
| 27 Jun 2025 | Appointment of Vice ChairThat Councillor Carol Gahan be appointed as vice-chair for the 2025/26 municipal year. | Decided | Open |
| 27 Jun 2025 | Minutes of Previous MeetingThat the minutes of the meeting held on 25 April 2025 be approved as a correct record. | Approved | Open |
| 27 Jun 2025 | Shared Services Business Plans 2024-25 - End of Year ReportThat the Joint Committee note the Shared Services performance for 2024/25. | Noted | Open |
| 27 Jun 2025 | The Future Model for ICT: Programme Gemini UpdateThat the Joint Committee notes the progress made and current status of the Phase 1 Gemini Programme and recommends to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.